Wood Fold Primary Enlargement - Tender Acceptance Delegation

Agreed Executive 2 papers

AI summaryCabinet authorises procurement for Wood Fold Primary enlargement and delegates tender acceptance to the Director of Place within set financial limits.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTender acceptance delegated to Director of Place
MoneyNot stated
What happens nextProcurement to beginDirector to award contract after tender
Who it affectsStandish area families and pupilsAdditional school places in Standish planning area

What was decided

Cabinet authorised a formal procurement process to appoint a contractor for the proposed enlargement of Wood Fold Primary School in Wigan.

Authority was delegated to the Director of Place to accept the tender, use the project contingency within the budget release figure, and award the contract, subject to financial limits set out in Appendix 1.

The Assistant Director for Legal Governance and Elections was authorised to enter into the necessary agreements on behalf of the Council.

Why

Pupil projections identified a need for additional places in Standish, driven by rising birth rates and growth from housing in the area. Report P4, 5.2

Since 2019, 935 dwellings have been completed in Standish, with a further 397 due for completion by 2029, increasing demand for primary places. Report P5

Births in the catchment area have risen, with 207 births recorded for the 2023/24 intake year against 180 current places, supporting the case for expansion. Report P6

What happens next

Officers will monitor birth rates and housing yield before implementation, with the original September 2026 target modified to within 3 years of the decision. Report P8, P9, P10

If demand does not materialise, a revocation proposal will be published to remove the duty to implement the expansion. Report P11

The expansion will increase capacity at Wood Fold from 180 to 210 places once complete. Report P6, P7

Options considered

  • Chosen: Modify implementation date to within 3 years rather than the original September 2026 target. To allow officers to monitor birth rate and housing yield before implementation Report P9, P10

Implications

  • Staffing: The school will need to employ more staff at the expanded site as more places become available. Report P19
  • Other: The change will offer additional Good or better school places to children in the Standish planning area. Report P17

Who and where

  • Children and families in the Standish planning area Report P4, P17
  • Staff at Wood Fold Primary School Report P19

Timeline

  • Since 2019: 935 dwellings completed in Standish Report P5
  • 2025: 181 first preference applications received for Standish area reception places Report P8
  • By 2029: 397 further dwellings due for completion in Standish Report P5
  • Within 3 years of the decision: Deadline by which the enlargement must be implemented Report P12, P9
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item77

Resolved

The Cabinet:- (1) authorises the commencement of a formal procurement process for the contractor appointment in respect of the proposed enlargement of the Wood Fold Primary School, Wigan; (2) subject to the financial limits described in the Cabinet report at Appendix 1, delegates authority to the Director - Place to authorise:- (i) upon completion of the procurement exercise described in 1 above, formal tender acceptance; (ii) the use of the project contingency described with the report at Appendix 1 if required within the budget release figure; and (iii) formal contract award together with any agreements either in anticipation of or ancillary thereto; and (3) authorises the Assistant Director – Legal Governance and Elections to enter into the necessary agreements on behalf of the Council to give effect to the above.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Cabinet

This is an open report Report to: Cabinet

Date of Meeting(s): Thursday, 20 March 2025

Subject: School Organisation: Proposed Permanent Enlargement of Wood Fold Primary School

Report of: Cath Pealing, Assistant Director - Education

Contact Officer: Darren Stanley ([phone removed]), Catherine Thompson ([phone removed])

Cabinet Portfolio Holder and area: Councillor Jenny Bullen - Portfolio Holder for Children and Families

Summary: To report on the responses following the publication of a statutory notice and representation period on the proposal to permanently enlarge Wood Fold Primary School and ask Cabinet to make a decision on the proposed enlargement.

‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:

Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”

Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”

Outline how this report supports our ‘Progress with Unity’ missions. The expansion of Wood Fold Primary School will ensure that children in the Standish community can access education in the area where they live.

Wards Affected: Standish Ward will be affected as this is the planning area where the proposed expansion will take place. There is also an affect on all wards as any parent can apply for a place for their child at any state funded school, whether they live in the area or not.

Recommendation(s): The Cabinet is recommended to approve the proposal to enlarge Wood Fold Primary School by increasing its physical capacity by 1 form of entry within 3 years of the decision.

Implications:

What are the financial implications? Feasibility to RIBA 2 with an associated cost plan has been completed. This has been value engineered to £6,000,000 with £600,000 associated fees and services costs with some contingency. This capital investment will be met by existing resources of £6,600,000 basic need funding/section 106. It is assumed that scheme costs will be part funded from S106 contributions, subject to Housing Developments progressing as per the S106 agreements. Should there be a shortfall in S106 contributions received then Basic Needs funding will be used to gap fund to the value stated above.

Permission to release capital funds will be requested separately.

Is budget release necessary (Capital Expenditure Only)? Budget release is required, and the LA basic need funding has been confirmed by the Strategic Finance Manager.

What are the legal implications? Local Authorities must ensure that they act in accordance with the relevant legislation namely The School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 and DfE guidance Making significant changes (‘prescribed alterations’) to maintained schools March 2025.

What are the staffing implications? None at this point. If the proposal is agreed, the school will need to employ additional staff to serve the increased school population.

Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. Not required. All views are captured via the consultation carried out as outlined in this report. Relevance Check is attached.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Wood Fold Primary Enlargement Cabinet ReportReport 198 KB DownloadRead as text
PDF
Wood Fold Primary Enlargement: Tender Acceptance DelegationReport 132 KB Download

At this meeting

Whole meeting

Who was there

6 of 23 attended
DT
Councillor David Trevor Molyneux MBEExecutive Leader, present
KC
Councillor Keith CunliffeDeputy Leader, present
KA
Councillor Kevin Anderson B.A (Hons)Committee Member, present
DA
Councillor Dane AndertonCommittee Member, apologies
SG
Councillor Susan GamblesCommittee Member, present
PP
Councillor Paul PrescottCommittee Member, present
CR
Councillor Christopher ReadyCommittee Member, apologies
NR
Councillor Nazia RehmanCommittee Member, present
SC
Stuart CowleyOfficer, in attendance
JD
Janet DaviesOfficer, in attendance
LD
Lucy DownhamOfficer, in attendance
LG
Lewis GreenwoodOfficer, in attendance

All 23 on the meeting page

On this subject at Wigan

Search all
  1. Wood Fold Primary Enlargement - Tender Acceptance DelegationThis decision
  2. Standish Woodfold Expansion - Delegation of Tender AcceptanceApproved
  3. School Organisation: Proposed permanent enlargement of Wood Fold Primary SchoolApproved
  4. School Organisation: Proposed Permanent Enlargement of Wood Fold Primary SchoolApproved

More from Wigan Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open
24 Sep 2026 Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... Approved Open
24 Sep 2026 Annual Standards Report 2025/26The Cabinet approves the . Approved Open
24 Sep 2026 Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... Approved Open
27 Aug 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies