Wigan Metropolitan Borough Council
Cabinet, Thursday 27 August 2026 at 10.30am

Revenue and Treasury Management Monitoring - Quarter 1

Decided Executive 2 papers

AI summaryWigan Council Cabinet notes Q1 2026/27 revenue position showing £0.655m underspend but a forecast year-end overspend of £2.868m, driven mainly by children's services pressures.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet noted the Q1 2026/27 position
Money£2.868m forecast overspendYear-end forecast overspend after mitigations
What happens nextQuarterly monitoring continuesFurther updates to Cabinet each quarter
Who it affectsAll Wigan wardsCouncil-wide revenue budget

What was decided

Cabinet noted the revenue position at the end of Quarter 1 2026/27, with an underspend of £0.655m and a projected year-end overspend of £2.868m. Report 2.1

The report is for information only; there are no alternative options for consideration. Report P26

Why

Children's Services is the main pressure, with external residential placements forecast to overspend by £3.4m and Home to School Transport by £1.4m at year end. Report 2.2, P50, P53

The number of children with Education and Health Care Plans rose by 664 (17.8%) to 4,398 between July 2025 and June 2026, increasing transport demand. Report P54

Corporate mitigations of £5.943m, including £0.578m in Financing and Investment Income and temporary grant funding, reduce the forecast overspend from £8.8m to £2.868m. Report 2.2, P87, P107

What happens next

Further work will be undertaken in year to identify efficiencies and mitigate cost pressures, with savings delivery monitored quarterly. Report 2.3, P90, P108

If the overall projected overspend cannot be mitigated, reserves will need to be used to meet the statutory duty to balance the budget. Report P109

The money

  • £0.655m Q1 underspend Report 2.1
  • £2.868m Forecast year-end overspend Report 2.1
  • £3.4m Looked after children external residential placements forecast overspend Report 2.2
  • £1.4m Home to School Transport pressure Report 2.2
  • £5.943m Corporate budget mitigations including Financing and Investment Income Report 2.2
  • £0.578m Financing and Investment Income saving Report 2.2, P87
  • £14.264m Total 2026/27 savings target Report P90
  • £12.637m Forecast savings achievement by year end Report P90
  • £3.35m Target reduction in external residential placements spend by end of 2028/29 Report P52
  • £0.946m Target reduction in Home to School Transport spend by end of 2028/29 Report P55
  • £3.610m Children's Services savings expected in 2026/27 Report P58
  • £0.7m HRA forecast overspend for 2026/27 Report P93
  • £25.934m Overall DSG deficit position after 2025/26 Report P96
  • £23.340m Potential High Needs Stability grant Report P97
  • £2.594m Remaining DSG deficit after potential grant Report P97
  • £2.3m Forecast use of earmarked reserves in 2026/27 Report P100
  • £83.5m Forecast Earmarked Reserves at 31/03/27 Report P100

Options considered

  • Chosen: Note the Q1 2026/27 revenue position. Report is for information only; no alternatives exist Report P14, P26

Implications

  • Financial: Forecast year-end overspend of £2.868m after £5.943m of corporate mitigations, with service budgets originally £8.8m overspent. Report 2.2, P107
  • Financial: HRA forecast overspend of £0.7m will require use of reserves beyond the £3.28m already approved in the budget. Report P93
  • Financial: DSG High Needs deficit of £25.934m, with potential £23.340m grant leaving £2.594m unfunded and ongoing risk beyond 31/03/2028 statutory override. Report P96, P97, P98
  • Financial: Risks include capital programme cost inflation, interest rate rises, and end of fair funding transitional support. Report P103, P104, P105
  • Legal: The Council is required to set a balanced budget under the Local Government and Finance Act 1992. Report P17
  • Equalities: No Equality and Diversity impact assessment required as no vulnerable groups are impacted by decisions in this report. Report P19
  • Risk: Continuing risks from external children's residential placements and home to school transport costs. Report P22
  • Staffing: No staffing implications identified. Report P18

Who and where

  • All Wigan borough wards Report P13
  • Children's Services service users, particularly looked after children and those with EHCPs Report P51, P54
  • Adult Social Care service users, with potential impact from Minimum Income Guarantee rate changes Report P43
  • Homelessness services users, with continued high demand for temporary accommodation Report P62
  • Council tenants, affected by the HRA forecast overspend Report P93
  • Schools and parents reliant on home to school transport Report P53, P54

Timeline

  • End of June 2026: Q1 revenue position recorded as £0.655m underspend Report 2.1
  • 19/06/2026: Local SEND Reform Plan submitted to the DfE Report P97
  • 31/03/2027: Forecast year-end; earmarked reserves projected to be £83.5m Report P100
  • 31/03/2028: Statutory override on DSG deficits ends Report P98
  • End of 2028/29: Target dates for reductions in external residential placements (£3.35m) and home to school transport (£0.946m) spending Report P52, P55

Plain English for the jargon

  • DSG: Dedicated Schools Grant, the main ring-fenced funding for schools and related services
  • EHCP: Education and Health Care Plan, a document setting out support for children and young people with special educational needs
  • HRA: Housing Revenue Account, a separate statutory account for income and costs relating to council housing
  • MIG: Minimum Income Guarantee, the minimum income a person receiving care must keep after a financial assessment
  • SEND: Special Educational Needs and Disabilities
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30

Resolved

The Cabinet notes the revenue position at the end of Quarter 1 - 2026/27.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Cabinet

This is an open report

Report to: Cabinet

Date of Meeting(s): Thursday, 27 August 2026

Subject: Financial Monitoring - Quarter 1

Report of: Sarah Johnston, Director - Finance and Legal

Contact Officer: John McDonald ([email protected]), Matt Guest ([email protected])

Cabinet Portfolio Holder and area: Councillor Nazia Rehman, Portfolio Holder for Finance, Resources and Transformation (Executive Leader)

Summary: To report on the revenue position at the end of Quarter 1 2026/27 and the use of reserves. This report also includes the Treasury Management activity at Quarter 1 shown as Appendix 1.

‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:

Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”

Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”

Outline how this report supports our ‘Progress with Unity’ missions. Financial sustainability is key to delivering on the Council’s Missions.

Wards Affected: All

Recommendation(s): The Cabinet are requested to note the revenue position at the end of Quarter 1 2026/27. Implications:

What are the financial implications? The report shows that at Quarter 1 the revenue position is showing an underspend of £0.655m, with a forecasted outturn of £2.868m over budget.

Is budget release necessary (Capital Expenditure Only)? N/A

What are the legal implications? The Council is required to set a balanced budget in accordance with the local Government and Finance Act 1992.

What are the staffing implications? None

Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. An Equality and Diversity impact assessment is not required as no vulnerable groups are impacted upon by any decision within this report. Relevance Check is attached.

What are the property implications in terms of reduction, addition or change to the council’s asset base or its occupation? None

What are the Corporate Parenting Implications? None

Risks: The well documented risks with regards to the cost of external children’s residential placements and home to school transport continue to impact on the financial position of the Council.

Sustainability/Environmental/Climate implications: The Council is deemed to be a Going Concern, which means that it is to continue to operate for the foreseeable future. As part of this assessment, I have considered our financial performance including factors on historical, current and future performance.

Has the Chief Legal Officer (Nina Ellement) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution? Yes

Has the Director – Finance and Legal (Sarah Johnston) confirmed that any expenditure referred to within this report is consistent with the Council’s budget? Yes Are any of the recommendations within this report contrary to the Policy Framework of the Council? No

What are the alternative option(s) to be considered? Please give the reason(s) for recommendation(s): There are no alternatives, the report is for information.

Is this a Key Decision and, if so, under which definition? The Non-Key decision made as a result of this report will be published within one working days and cannot be actioned until five working days have elapsed, i.e. before 8 September 2026, unless exempt from call-in.

This item is included on the Forward Plan.

There are no background papers for this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Activity Quarter 1Appendix 1 143 KB Download
PDF
Revenue and Treasury Management Monitoring: Quarter 1Report 399 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 23 attended
NR
Councillor Nazia RehmanExecutive Leader, present
KC
Councillor Keith CunliffeDeputy Leader, present
KA
Councillor Kevin Anderson B.A (Hons)Committee Member, present
DA
Councillor Dane AndertonCommittee Member, present
LF
Councillor Laura FlynnCommittee Member, apologies
SG
Councillor Susan GamblesCommittee Member, apologies
PT
Councillor Paul Terence KennyCommittee Member, present
CR
Councillor Christopher ReadyCommittee Member, present
SC
Stuart CowleyOfficer, in attendance
LD
Lucy DownhamOfficer, in attendance
CD
Colette DuttonOfficer, in attendance
NE
Nina EllementOfficer, in attendance

All 23 on the meeting page

On this subject at Wigan

Search all
  1. Revenue and Treasury Management Monitoring - Quarter 1This decision
  2. Treasury Policy, Prudential Indicators, Capital Programme and Minimum Revenue ProvisionApproved
  3. Treasury Policy, Prudential Indicators, Capital Programme and Minimum Revenue Provision.Approved
  4. Treasury Policy, Prudential Indicators, Capital Programme and Minimum Revenue Provision.Approved
  5. Treasury Policy , Prudential Indicators, Capital Programme and Minimum Revenue ProvisionApproved
  6. Treasury Policy , Prudential Indicators, Capital Programme and Minimum Revenue ProvisionApproved

More from Wigan Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open
24 Sep 2026 Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... Approved Open
24 Sep 2026 Annual Standards Report 2025/26The Cabinet approves the . Approved Open
24 Sep 2026 Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... Approved Open
27 Aug 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies