CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wigan Metropolitan Borough Council
All: Place and Environment Scrutiny Committee, Wednesday 9 September 2026 at 6.30pm

Highways Asset Management Annual Report

Decided Scrutiny 3 papers

AI summaryWigan's Place and Environment Scrutiny Committee notes the Highways Asset Management Annual Report, highlighting over £8.1 million in funding and a top Green DfT transparency rating.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee thanked the officer and noted the report
Money£8.1m securedCombined GMCA CRSTS and Council capital funding
What happens nextOngoing investmentWorkforce and AI-driven asset management continue
Who it affectsHighway usersResidents, businesses and road users across Wigan

What was decided

The Committee thanked the officer for their report and noted its content.

Why

The report sets out the year's performance, achievements, challenges and future opportunities for managing the borough's highway network. Report P6, P31

It supports transparency and shows alignment with Department for Transport expectations, including the new Highways Transparency Reporting framework. Report P6, P8, P28, P29

What happens next

Continue developing the asset management approach, using data and AI-powered condition surveys to target investment and support lifecycle planning. Report P5, P12, P89, P90

Expand use of recycled and resource-efficient materials, increase Sustainable Drainage Systems, and trial low-temperature asphalt products. Report P71, P72, P73, P76, P77

Invest in workforce skills, succession planning, and enhanced communications and partnership working with residents, members and external bodies. Report P91, P92, P93

The money

  • over £8.1 million Combined funding from GMCA CRSTS and internal Council capital allocations Report P9
  • £4.8 million Core Maintenance Funding for annual planned and preventative maintenance Report P10
  • £1.5 million Strategic Maintenance Capital for the Key Route Network Report P10
  • £908,000 Integrated Transport Block Funding for road safety, congestion and sustainable transport Report P10
  • £400,000 Wigan Housing Contribution Funding for footway and service access road resurfacing Report P10
  • £508,000 Additional DfT Incentive Funding to supplement core maintenance Report P10
  • £99,000 Efficiency savings measured through the NHT Customer, Quality and Cost benchmarking framework Report P37

Options considered

  • Chosen: Note the annual report and thank the officer. Standard scrutiny procedure for receiving the annual update Report P6

Implications

  • Financial: Over £8.1 million secured in combined funding, with £99,000 in efficiency savings delivered through the NHT benchmarking framework. Report P9, P10, P37
  • Climate: 38,412 tonnes of resource-efficient surfacing materials used, 99% of excavated materials recycled, and continued LED street lighting rollout. Report P52, P54, P61
  • Risk: Ageing assets exceeding original design life, more frequent severe weather events, and recruitment and retention challenges for technical highway staff. Report P89, P90, P91
  • Staffing: Workforce development continues, with HGV, HNC, LANTRA, IOSH, ILM and Masters qualifications completed, and new recruits in streetworks compliance, flood risk, active travel and parking enforcement. Report P88
  • Other: Wigan was one of only 16 of 154 English local highway authorities to achieve the highest Green rating under the DfT Highways Maintenance Transparency Reporting Framework. Report P30

Who and where

  • Residents, businesses and road users across the Wigan borough Report P4, P6
  • Highway service staff and new recruits Report P88
  • Partner organisations including TfGM, GMCA, DfT, the Environment Agency, United Utilities and Greater Manchester Police Report P92, P93

Timeline

  • 2025/26: Total highway enquiries rose to 10,264 from 6,138 the previous year Report P26
  • 2025/26: 38,412 tonnes of resource-efficient surfacing materials used and 99% of excavated materials recycled Report P52, P54
  • 2025: First year of the Department for Transport's Highways Transparency Reporting requirements Report P8, P29

Plain English for the jargon

  • HAM: Highway Asset Management
  • CRSTS: City Region Sustainable Transport Settlement
  • GMCA: Greater Manchester Combined Authority
  • KRN: Key Route Network (Greater Manchester)
  • TfGM: Transport for Greater Manchester
  • DfT: Department for Transport
  • KPI: Key Performance Indicator
  • SuDS: Sustainable Drainage Systems
  • NHT: National Highways and Transportation benchmarking network
  • APSE: Association for Public Service Excellence
  • LCRIG: Local Council Roads Innovation Group
  • LED: Light Emitting Diode street lighting
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

The Committee:- (1) thanks the officer for their report; and (2) notes the content of the report.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to All: Place and Environment Scrutiny Committee

Highways Asset Management Annual Report Author: Martin Barton Date: 30/07/2026

Page 1 of 26 Foreword

CLLR Paul Kenny Portfolio Holder for Planning, Environmental Services and Transport

The highway network is one of the Council’s most significant infrastructure assets, playing a vital role in supporting economic growth, connecting communities, and enabling access to employment, education, healthcare and leisure opportunities. As part of our ambition to create a Well- Connected Borough, we continue to invest in and manage our transport infrastructure to ensure it remains safe, resilient and fit for the future, whilst supporting sustainable travel choices including walking, wheeling and cycling. High-quality highway infrastructure is fundamental to the Borough’s continued growth and prosperity. It supports the efficient movement of people and goods, attracts inward investment, facilitates new housing and employment development, and contributes to the delivery of wider regeneration and place-making objectives. Our approach to managing this critical asset is set out through the Council’s Highway Asset Management Policy, Strategy and Plan, which provides a clear framework for investment and decision-making. Using the principles of whole-life asset management, we seek to maximise the value of our assets, target investment effectively, and ensure that maintenance activities deliver the greatest benefit to residents, businesses and network users. This approach supports the delivery of the Council’s Progress with Unity priorities and wider corporate objectives. In response to increasing pressures, financial constraints and evolving customer expectations, we remain committed to continuous improvement

Page 2 of 26 and innovation. During the year, we have further strengthened our data- led approach through the adoption of advanced technologies, including AI-powered highway condition surveys, enabling more informed investment decisions and improved lifecycle planning. Alongside this, we continue to explore sustainable materials, low-carbon construction techniques and smarter ways of working to improve service outcomes while reducing environmental impact. These initiatives support the Council’s ambition to create a more sustainable, resilient and efficient transport network for future generations. This report highlights the key achievements and performance outcomes delivered during the year and provides an overview of the strategic challenges, risks and opportunities that will shape the future management of the Borough’s highway infrastructure assets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Highways Asset Management Annual ReportReport 1.1 MB DownloadRead as text
PDF
Enc. 2 for Highways Asset Management Annual ReportReport 221 KB Download
PDF
Highways Asset Management Annual ReportReport 156 KB Download

At this meeting

Whole meeting

Who was there

10 of 21 attended
CW
Councillor Clive William MorganChairman, present
KW
Councillor Keith WhalleyVice-Chair, present
PC
Councillor Phyllis CullenCommittee Member, present
DH
Councillor David HurstCommittee Member, present
JM
Councillor Joanne MarshallCommittee Member, apologies
JP
Councillor James PalmerCommittee Member, absent
JP
Councillor Jeanette PrescottCommittee Member, present
MS
Councillor Mike SmithCommittee Member, present
BJ
Councillor Barry John TaylorCommittee Member, present
MF
Councillor Martin FarrimondCommittee Member, present
ML
Councillor Matthew LambertCommittee Member, present
KM
Councillor Kathy Morrill-AshfordCommittee Member, present

All 21 on the meeting page

On this subject at Wigan

Search all
  1. Highways Asset Management Annual ReportThis decision
  2. Highways Asset Management Annual ReportDecided
  3. Highways Asset Management Annual ReportDecided
  4. Highways Asset Management Annual ReportDecided
  5. Asset Management Annual Report 2016/17 (including Highways Drainage and Highways Safety Inspections and Minor Repairs)Approved

More from Wigan All: Place and Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Whipping DeclarationsThere were no declarations Decided Open
9 Sep 2026 Executive's Forward Plan of Key and Non-Key DecisionsThe Committee notes the forthcoming decisions, with no items being requested to be placed on a future agenda of the C... Decided Open
9 Sep 2026 Scoping Report - 'The Restoration of Haigh Hall'The Committee:- (1) directs the Task and Finish Group to undertake further scoping work and resubmit the proposal for... Decided Open
9 Sep 2026 Flood Risk and Resilience UpdateThe Committee:- (1) thanks the officers for their report; and (2) notes the content of the report. Decided Open
9 Sep 2026 Scrutiny Committee WorkplanThat the report be noted, with no further items being requested to be placed on the workplan. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies