AI summaryWinchester City Council Cabinet Committee for Housing noted a retrofit programme update covering 308 properties and 1,335 measures, and asked for ward councillor involvement plus a members' briefing on solar panel installation.
Written from the decision and the officer reportPDF Pro
OutcomeNotedWith two added requests
MoneyNot stated
What happens nextMembers' briefing on solar panelsTo be arranged for councillors
Who it affectsCouncil housing tenantsAcross 308 retrofit properties
What was decided
The Cabinet Committee noted the retrofit programme update.
Officers are reminded to involve ward councillors in retrofit programmes in their areas.
A members' briefing on the retrofit programme relating to solar panel installation will be arranged.
Why
The retrofit programme covers measures including door undercuts, trickle vents, solar panels and battery, loft insulation, new windows, extract ventilation and wall insulation across the council's housing stock. Report P1, P2, P3, P4, P5
Currently 71% of Winchester City Council homes are at EPC C, with an anticipated further uplift of 73% from the 2025 delivery programmes and the Social Housing Fund across 308 properties and 1,335 measures. Report P10, P11, P12, P13
Workstreams include the Swedish Cottages, Conservation Area single glazed windows, SHF Wave 3, Winnall estate and a multi-unit blocks retrofit programme. Report P6, P7, P11, P20, P21, P22
What happens next
Complete roofs and windows to the remaining 3 Swedish Cottages properties, work at Coles Mede in Otterbourne, finish remedial works to make homes draft proof, revise the specification to smart heating for EPC C, and produce individual business plans with Housing Options and Housing Services. Report P20
Install the remaining 99 loft hatches at audit properties, check the property list and data, and sample further properties with the contractor through the clerk of works. Report P21
Continue tenant engagement: February home visits for Swedish Cottages Phase 3, in person visits from October for the SHF and Window Programme and the Solar Panel Agreement, and publish the SHF Programme Video in January, alongside progressing engagement strategies and the Equality Impact Assessment. Report P23, P24, P25, P26, P27, P28
Options considered
Chosen: Note the retrofit programme update, with ward councillor involvement and a members' briefing on solar panels
Implications
Climate: Programme targets a 3% improvement in EPC ratings over 2026 to 2028, with 657 of 5,055 properties (around 330 per year from 2028 to 2030) needing retrofit, excluding uplifts through the blocks, Winnall, planned maintenance and mechanical or electrical works. Report P17, P18, P19
Staffing: A Resident Liaison Officer is in place and a new contractor has been appointed for final remedial works at the Swedish Cottages. Report P20, P23
Risk: 9 Conservation Area homes still need ventilation upgrades, 24 other measures remain planned, and 8 of 30 window properties fall within year 26/27 with 13 of 33 yet to move to EPC C. Report P12, P20
Other: 12 multi-unit blocks have been identified for retrofit, with energy assessments in place, pilot selection after surveys, procurement begun and a project plan being drafted. Report P22
Other: Winnall retrofit options appraisal is complete, with scope, high level costs and key milestones to be documented, considering solar and air source heat pumps, and funding to be investigated. Report P21
Who and where
Tenants in 308 properties across the retrofit programme, with 1,335 measures planned Report P13
Tenants of the 14 Swedish Cottages, with 3 still requiring roof and window work Report P20
Tenants in 22 Conservation Area single glazed homes, with 15 completed and 9 still needing ventilation Report P20
Tenants in 12 multi-unit blocks identified for the blocks retrofit programme Report P22
Tenants in 30 audit properties where 99 loft hatches still need installation Report P21
Winchester City Council ward councillors in retrofit areas
Timeline
2025/2026: Total retrofit programme delivery against targets Report P8, P9, P13
February: Swedish Cottages Phase 3 in person home visits Report P24
October onwards: In person visits for SHF and Window Programme Report P26
October onwards: In person visits for Solar Panel Agreement Report P27
January: SHF Programme Video Development Report P28
26/27: 8 of 30 Conservation Area window properties scheduled, 13 of 33 to move to EPC C Report P20
2026 to 2028: EPC targets improved by 3% over this period Report P17, P18, P19
2028 to 2030: Around 330 retrofits per year needed across 657 of 5,055 properties Report P17
Plain English for the jargon
EPC C: Energy Performance Certificate rating of C, a target energy efficiency level
SHF: Social Housing Fund, a grant programme funding retrofit works
SHDF: Social Housing Decarbonisation Fund, a government retrofit grant scheme
CWI: Cavity Wall Insulation, an external wall insulation measure
LI: Loft Insulation, a roof insulation measure
ASHP: Air Source Heat Pump, a low carbon heating technology
RLO: Resident Liaison Officer, a tenant engagement role
EqIA: Equality Impact Assessment, an analysis of equalities effects
WCC: Winchester City Council
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That the update regarding the retrofit programme be noted including the following: a) A reminder to ensure the involvement of ward councillors in retrofit programmes in their areas. b) A members’ briefing to be arranged on the retrofit programme relating to solar panel installation.
Word for word from the decision Winchester published for this meeting.Source: democracy.winchester.gov.uk
❖ Tenant Engagement Retrofit Programme Total 2025/2026 - Target
PREVIOUS PREVIOS NEW NO. OF TARGET TARGET TARGET NEW TARGET TAREGT EPC C DELIVERED DELIVERED WCC EPC C AND PROPERTIES MEASURES PROPERTIES MEASURES UPLIFTS PROPERTIES MEASURES EPC C ACHIEVED ABOVE TRACKER
Currently 71% SHDF SWEDISH COTTAGES 14 28 0 14 27
SHF – WAVE 3 195 1170 120 600 120 3 9 2%
ENERGY ASSESSMENT 195 195 17 CONSERVATION AREA SINGLE GLAZED 13 65 22 44 3 15 24 OTHER MEASURES RESPONSE: RESPONSE CWI + LI 45 51 RESPONSE WHOLE HOUSE OTHER MEASURES PLANNED PLANNED WINDOWS: 100 100 160 160 0 24 24
Note: 13% of 5055 = 657 (+/-330 per year from 2028 – 2030) numbers exclude EPC uplift through Multi-unit Blocks Programme, Winnall , Planned Maintenance and Mechanical or Electrical upgrades works ❖ EPC targets improved by 3% over 26-28, due to:
❖ Reorganised delivery for increased numbers in 27-28
❖ Analysis of how we streamline delivery
❖ Improved costs SWEDISH COTTAGES 14 homes with new roofs and new windows New contractor appointed for Final remedial works - underway Swedish Customer Matrix completed by Retrofit and Housing Services Internal Meeting held to agree next steps: Complete Roof and Windows to remaining 3 properties Work with 4th Site: Coles Mede, Otterbourne Complete remedial works and necessary repairs to make homes draft proof Revise specification: smart heating to achieve EPC C RLO alongside Housing Options and Housing Services to create individual business plans for each home CONSERVATION WINDOWS SINGLE GLAZED 15 out of 22 Homes Completed Ventilation to 15 homes upgraded, 9 homes remain 8 of 30 Window properties fall within year 26/27 13 of 33 to move to EPC C
AUDIT PROPERTIES 40 loft hatches installed, 99 loft hatches to be installed 30 properties from Year 23/24 retrofit properties surveyed and audited Next steps: Property list and data to be checked. Clerk of works to sample further properties with the Contractor. Winnall Retrofit Options Appraisal Complete and Presented to internal Stakeholders Collaboration with Planned and Compliance Teams Define scope, high level costs and key milestones to be documented Possible technologies: Solar and ASHP Funding to be investigated
Blocks Retrofit 12 Blocks identified – Energy assessments in place. Pilot Blocks to be selected following surveys, collaboration with Planned Stock Condition Report Procurement has begun Tenant Engagement Strategies begun Project Plan/Programme drafted, next draft underway Tenant Engagement 2025/2026
RESIDENT LIAISON OFFICER In Place
Swedish Cottages - Phase 3 In person Home visits February
Tenant Engagement Strategies for new programmes + EqIA In Progress
SHF and Window Programme - In person visits October onwards
Solar Panel Agreement – In person visits October onwards
SHF Programme Video Development: https://f.io/uY2SdO2E January
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.