Waterlooville Public Realm Improvements
West of Waterlooville Forum 18th June 2026 Project Background 1. Project identified as key priority in The Corporate Strategy 2024-26 - it highlights Pride in Place as being one of our key themes
2. Waterlooville Masterplan (2024)
3. Project - deliver enhancements to the streetscape on London Road.
5. Benefits – Improving quality of environment, stimulate local economy & demonstrate councils commitment to improving Waterlooville town centre Waterlooville Public Realm Enhancement Scheme
Maisie Burrows Principal Engineer May 2026 Hampshire Project Team
Maisie Burrows Mike Ellis Principal Engineer and Project Officer Senior Engineer Hampshire County Council Hampshire County Council Hampshire County Council and Havant Borough Council Collaborative Working Havant Borough Council Regeneration Officer
• Hampshire County Council and Havant Borough Hampshire County Council working collaboratively to deliver the Council Project Officer scheme. Hampshire County • On Hampshire Highways land. Havant Borough Council Senior Council Designer Engineer • Havant Borough Council funded. Hampshire Asset Hampshire Road Management Team Safety Team • Delivery through HCC Gen 5 framework. Hampshire • Review and guidance provided by HCC to Contracts Site Engineer ensure design will be acceptable and maintainable by HCC in the future. Hampshire Clerk of Principal Works Contractor • Scheme delivered and governed through HCC Capital Programme. Subcontractor Scheme Forecast Cost • The scheme is forecast to cost £1.8 million. This estimate includes: • Preliminary Design Review • Project Management from Preliminary-Post Construction • Detailed Design by HBC • Detailed Design Review by HCC • Contract Documents by HCC • Procurement • Governance through HCC Capital Programme • Safety and Asset Maintenance checks • Construction costs • Construction Management by HCC for 34 weeks. • HBC post construction design activities • Management of the post-construction maintenance period. • The increase from feasibility cost estimates carried out prior to the combining of the collaborative working arrangement is attributed to increased costs – construction, materials, inflationary impacts and risk associated with construction environments. Progress to date Project inception – July 2025
Preliminary design completion by HBC – November 2025
HBC Funding Bid sign off – February 2026
HCC/HBC funding agreement in place – March 2026
HCC Governance Gateway 2 – March 2026
HCC design review – April 2026
HBC Commenced Detail Design – April 2026 Delivery Programme and next stages Detailed Design Completion (June 2026)
Detailed Design Approvals (July 2026)
Detailed Design Technical Review (August 2026)
Gateway 3 governance process (Exec Member Decision Day) (August – October 2026)
Procurement (October-December 2026)
Construction (February – October 2027) Any Questions?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Waterlooville Town Centre Regeneration (Presentation)Report | 824 KB | DownloadRead as text |
Follow Waterlooville Forum at Winchester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Appointment of Vice Chairperson for the 2026/27 Municipal YearThat, Councillor Harrison be appointed Vice Chairperson of the Forum for the 2026/27 municipal year. | Decided | Open |
| 18 Jun 2026 | To note the future meeting dates for 2026/27That the future meeting dates of the Forum for 2026/27, be noted as set out on the agenda as follows: · 23 November 2... | Noted | Open |
| 18 Jun 2026 | Minutes of the previous meeting held on 3 March 2026 (including any matters arising)That the minutes of the previous meeting, held on 3 March 2026, be approved and adopted. | Approved | Open |
| 18 Jun 2026 | Grainger progress report on West of Waterlooville MDA (report)That the report be received and the comments raised by the forum as set out above, be noted. | Noted | Open |
| 18 Jun 2026 | Open space update (Verbal Update)That the update be received and the comments of the Forum, as set out above, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.