Waterlooville Forum, Thursday 18 June 2026 at 6.00pm

Update on Waterlooville Town Centre Regeneration (Presentation)

Noted Committee 1 paper

AI summaryWaterlooville Forum received an update on the £1.8 million London Road public realm scheme, with construction scheduled February to October 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedForum noted update on the scheme
Money£1.8 millionForecast cost of the scheme
What happens nextConstruction February to October 2027Main build phase after procurement
Who it affectsWaterlooville town centre, London RoadStreetscape enhancements planned

What was decided

The Forum received the presentation on the Waterlooville Public Realm Enhancement Scheme and noted the comments made by members.

Why

The project is a key priority in the Corporate Strategy 2024-26 under the Pride in Place theme, and was set out in the 2024 Waterlooville Masterplan. Report P2, P3

The scheme aims to improve the quality of the environment, stimulate the local economy, and show the councils' commitment to improving Waterlooville town centre. Report P5

What happens next

Detailed design is due to complete in June 2026, followed by approvals in July and a technical review in August 2026. Report P14, P15, P16

A Gateway 3 governance process is planned for August to October 2026, with procurement from October to December 2026. Report P17, P18

Construction is scheduled to run from February to October 2027, lasting 34 weeks. Report P8, P19

The money

  • £1.8 million Forecast cost of the Waterlooville Public Realm Enhancement Scheme Report P8

Implications

  • Financial: The forecast cost of £1.8 million is an increase on earlier feasibility estimates, attributed to higher construction, materials, inflationary and construction risk costs. Report P8
  • Financial: The scheme is funded by Havant Borough Council and governed through Hampshire County Council's Capital Programme. Report P8
  • Other: The scheme sits on Hampshire Highways land and is being delivered through Hampshire County Council's Gen 5 framework, with construction management by Hampshire County Council for 34 weeks. Report P8

Who and where

  • Users of London Road, Waterlooville Report P4
  • Waterlooville town centre visitors and businesses Report P5

Timeline

  • July 2025: Project inception Report P8
  • November 2025: Preliminary design completion by HBC Report P9
  • February 2026: HBC Funding Bid sign off Report P10
  • March 2026: HCC/HBC funding agreement in place Report P11
  • March 2026: HCC Governance Gateway 2 Report P12
  • April 2026: HCC design review Report P13
  • April 2026: HBC commenced detail design Report P14
  • June 2026: Detailed design completion Report P14
  • July 2026: Detailed design approvals Report P15
  • August 2026: Detailed design technical review Report P16
  • August, October 2026: Gateway 3 governance process Report P17
  • October, December 2026: Procurement Report P18
  • February, October 2027: Construction Report P19

Plain English for the jargon

  • HCC: Hampshire County Council
  • HBC: Havant Borough Council
  • Gen 5 framework: Hampshire County Council's contracting framework used to deliver the scheme
  • Gateway 2 / Gateway 3: Stages in Hampshire County Council's governance process for approving progression of a capital scheme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the presentation be received and the comments of the Forum, as set out above, be noted.
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Waterlooville Forum

Waterlooville Public Realm Improvements

West of Waterlooville Forum 18th June 2026 Project Background 1. Project identified as key priority in The Corporate Strategy 2024-26 - it highlights Pride in Place as being one of our key themes

2. Waterlooville Masterplan (2024)

3. Project - deliver enhancements to the streetscape on London Road.

5. Benefits – Improving quality of environment, stimulate local economy & demonstrate councils commitment to improving Waterlooville town centre Waterlooville Public Realm Enhancement Scheme

Maisie Burrows Principal Engineer May 2026 Hampshire Project Team

Maisie Burrows Mike Ellis Principal Engineer and Project Officer Senior Engineer Hampshire County Council Hampshire County Council Hampshire County Council and Havant Borough Council Collaborative Working Havant Borough Council Regeneration Officer

• Hampshire County Council and Havant Borough Hampshire County Council working collaboratively to deliver the Council Project Officer scheme. Hampshire County • On Hampshire Highways land. Havant Borough Council Senior Council Designer Engineer • Havant Borough Council funded. Hampshire Asset Hampshire Road Management Team Safety Team • Delivery through HCC Gen 5 framework. Hampshire • Review and guidance provided by HCC to Contracts Site Engineer ensure design will be acceptable and maintainable by HCC in the future. Hampshire Clerk of Principal Works Contractor • Scheme delivered and governed through HCC Capital Programme. Subcontractor Scheme Forecast Cost • The scheme is forecast to cost £1.8 million. This estimate includes: • Preliminary Design Review • Project Management from Preliminary-Post Construction • Detailed Design by HBC • Detailed Design Review by HCC • Contract Documents by HCC • Procurement • Governance through HCC Capital Programme • Safety and Asset Maintenance checks • Construction costs • Construction Management by HCC for 34 weeks. • HBC post construction design activities • Management of the post-construction maintenance period. • The increase from feasibility cost estimates carried out prior to the combining of the collaborative working arrangement is attributed to increased costs – construction, materials, inflationary impacts and risk associated with construction environments. Progress to date Project inception – July 2025

Preliminary design completion by HBC – November 2025

HBC Funding Bid sign off – February 2026

HCC/HBC funding agreement in place – March 2026

HCC Governance Gateway 2 – March 2026

HCC design review – April 2026

HBC Commenced Detail Design – April 2026 Delivery Programme and next stages Detailed Design Completion (June 2026)

Detailed Design Approvals (July 2026)

Detailed Design Technical Review (August 2026)

Gateway 3 governance process (Exec Member Decision Day) (August – October 2026)

Procurement (October-December 2026)

Construction (February – October 2027) Any Questions?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on Waterlooville Town Centre Regeneration (Presentation)Report 824 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 5 attended
NC
Councillor Neil Cutler OBEChairperson, present
MB
Councillor Michael BennettCommittee Member, present
CC
Councillor Chris ChamberlainCommittee Member, present
PL
Councillor Paula Langford-SmithCommittee Member, present
AC
Councillor Angela ClearObserver, in attendance

On this subject at Winchester

Search all
  1. Update on Waterlooville Town Centre Regeneration (Presentation)This decision
  2. Update on Waterlooville Town Centre Regeneration (Presentation)Noted

More from Winchester Waterlooville Forum

All decisions
MeetingDecisionOutcome
18 Jun 2026 Appointment of Vice Chairperson for the 2026/27 Municipal YearThat, Councillor Harrison be appointed Vice Chairperson of the Forum for the 2026/27 municipal year. Decided Open
18 Jun 2026 To note the future meeting dates for 2026/27That the future meeting dates of the Forum for 2026/27, be noted as set out on the agenda as follows: · 23 November 2... Noted Open
18 Jun 2026 Minutes of the previous meeting held on 3 March 2026 (including any matters arising)That the minutes of the previous meeting, held on 3 March 2026, be approved and adopted. Approved Open
18 Jun 2026 Grainger progress report on West of Waterlooville MDA (report)That the report be received and the comments raised by the forum as set out above, be noted. Noted Open
18 Jun 2026 Open space update (Verbal Update)That the update be received and the comments of the Forum, as set out above, be noted. Noted Open