Cabinet Committee: Housing, Monday 6 July 2026 at 10.00am

Repairs and Maintenance Procurement and Audit update

Noted Executive 5 papers

AI summaryWinchester's housing cabinet noted three new housing maintenance contracts to Wates Property Services and Signix Ltd and progress on a 2025 repairs audit.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedR&M to Wates, Heating and Electrical to Signix Ltd
MoneyRevenue £56.7m, capital £43.7mHeating £1,700.00.00 pa; Electrical £1,500.00.00 pa
What happens nextR&M go live 1 August 2026Heating and Electrical already started 11 May 2026
Who it affectsCouncil housing tenants, leaseholders, shared ownersRepairs and maintenance for the housing stock

What was decided

The committee noted the R&M contract award to Wates Property Services on a 4+3 year term, with anticipated go live on 1 August 2026. Report 11.4, P28

The committee noted the Heating and Electrical contract awards to Signix Ltd, each for 3+1+1+1 years, mobilised on 11 May 2026. Report 11.11, P4, P5

The committee noted progress on the R&M audit action plan arising from the October 2025 internal audit, which found no overall assurance in three areas. Report 11.15, 11.16, 11.17, P49

Why

The previous contracts were expiring, leaving no alternative to putting the work out to tender under procurement law. Report 12.1, P6

The October 2025 internal audit found weaknesses in process notes, job raising, variations, job authorisation and billing, requiring immediate action ahead of the new contracts. Report 11.16, 11.17, P49, P51, P52, P53, P54, P55, P56, P57

The procurement used a 60% quality and 40% cost weighting, with 10% of quality focused on environmental and social value, to prioritise service quality over lowest price. Report 3.1, 3.2

What happens next

Officers will continue progressing the R&M audit action plan, with full adoption of new process notes by 30 June 2026 and increased assurance from 1 July 2026. Report 11.22, P63

Progress will be reported monthly to the PAC board and to the Housing Leadership Board, with the Head of Landlord Services and the Repairs and Maintenance Manager overseeing delivery. Report 11.18, 11.20

New asbestos and water hygiene contracts will be procured in Q4 of 2026/27 to avoid overlapping go live dates with the new R&M, Heating and Electrical contracts. Report 11.14

The money

  • £56.7m Overall R&M revenue budget over the contract period, in the agreed HRA business plan Report 2.3
  • £43.7m Overall R&M capital budget over the contract period, in the agreed HRA business plan Report 2.3
  • £1,700.00.00 pa Heating contract sum, excluding VAT Report P4
  • £1,500.00.00 pa Electrical contract sum, excluding VAT Report P5

Options considered

  • Rejected: Delay the R&M audit action plan until the new contract goes live in August 2026. Audit findings were serious enough to need immediate action before the new contract go live Report 12.2

Implications

  • Financial: Tender budgets referenced in the ITT were in line with the prior approved HRA business plan budgets, with assumed inflation and repairs growth included. Report 2.1, 2.2, 2.3
  • Legal: The procurement was carried out in line with the Procurement Act 2023, the Public Contracts Regulations 2015 and the council's Contract Procedure Rules, following the May 2025 Cabinet agreement (CAB3506). Report P6, 3.1, 11.6, P71
  • Equalities: The tender process and contract must uphold equality, transparency and fairness; bidders were screened for upheld Equality and Human Rights Commission complaints in the last three years. Report 8.1, P22
  • Climate: The successful bidder must support the council's Carbon Neutrality objectives and Nature Emergency, with sustainability team input and support to the Retrofit Team. Report 7.1, P20
  • Risk: A schedule of rates approach using NHF V8 SOR values is intended to reduce financial exposure; other risks include innovation, reputation, outcome delivery and Local Government Reorganisation. Report P24, P25, P26
  • Staffing: Existing housing repairs staff remain employed by the council, with no TUPE implications at this time. Report 4.1, P11

Who and where

  • Council housing tenants, leaseholders and shared owners across the district Report 2.1, 6.1, P15
  • TACT board members, who were consulted and two of whom were involved in procurement evaluation Report 6.3, P18
  • Existing housing repairs staff, who remain council employees under the new contracts Report 4.1, P11
  • PAC board and Housing Leadership Board members, who monitor action plan progress Report 11.18, 11.20

Timeline

  • October 2025: Southern Internal Audit Partnership completed the R&M internal audit Report 11.16
  • January 2026: Action plan developed to address the audit findings Report 11.18
  • 29 January 2026: Audit update presented to the Audit and Governance Committee Report 11.19
  • 11/05/2026: Heating and Electrical contracts with Signix Ltd mobilised Report 11.11
  • 31/05/2026: New staff trained on the Cardo to Orchard payment process Report P63
  • 30/06/2026: Target for full adoption of new process notes for officers and contractors Report P63
  • 1st August 2026: Anticipated go live date for the Wates Property Services R&M contract Report 11.4
  • Q4 of 2026/27: New asbestos and water hygiene contracts to be procured Report 11.14

Plain English for the jargon

  • ITT: Invitation to Tender, the second stage of a two-stage procurement where shortlisted bidders submit their tender.
  • RFT: Request for Tender, the first stage of a two-stage procurement where bidders express interest and provide detail for evaluation.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the following be noted: 1. That the repairs and maintenance contract has been awarded to Wates Property Services. 2. That the Heating contract has been awarded to Signix Ltd. 3. That the Electrical contract has been awarded to Signix Ltd. 4. The Repairs and Maintenance audit action plan and progress made to date.
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Cabinet Committee: Housing

CAB3557(H) CABINET COMMITTEE: HOUSING

REPORT TITLE: REPAIRS AND MAINTENANCE PROCUREMENT AND AUDIT UPDATE

6 JULY 2026

REPORT OF CABINET MEMBER: Cllr Mark Reach Cabinet Member for Good Homes for All

Contact Officer: Paul Woodham Email [email protected]

WARD(S) ALL

PURPOSE

This report supports the council’s corporate priority, Good Homes for All.

The procurement of the repairs and maintenance contract was agreed by Cabinet in May 2025, including approval of a seven-year contract term and the use of framework arrangements for Heating, Electrical, Fire Safety, Asbestos and Water Hygiene contracts (Cabinet paper CAB3506). Cabinet also set the evaluation methodology, based on a 60% quality and 40% cost weighting, to ensure best value for tenants, residents and the Council.

This report provides an update to Cabinet Committee Housing on the procurement of new contract delivery for repairs and maintenance, electrical and heating services across the council’s housing stock and associated assets. The report will outline the process the procurement has gone through, including the number of bidders involved, the evaluation methodology applied and the outcomes of the assessment, such as scoring and how the preferred bidders were identified for each contract.

The procurement of the repairs and maintenance contract was conducted under the new Procurement Act 2023 (PA23) procedures with a go live date of August 2026 and the electrical and heating contracts were procured under a Public Contracts Regulations 2015 framework to ensure a go live date of 7th May 2026.

The paper also provides an update on the status of the contracts for Water Hygiene, Asbestos, Lifts and Fire Safety The report will also provide an update on recommendations relating to a repairs and maintenance audit, including the development of an action plan, progress made and the governance framework that has been put in place to ensure effective oversight and continuous improvement. RECOMMENDATIONS:

Cabinet Committee Housing is asked to note:

1. The repairs and maintenance contract has been awarded to Wates Property Services. 2. The Heating contract has been awarded to Signix Ltd. 3. The Electrical contract has been awarded to Signix Ltd. 4. The Repairs and Maintenance audit action plan and progress made to date. CAB3557(H)

IMPLICATIONS:

1 COUNCIL PLAN OUTCOME

1.1Greener Faster

Greener Homes’ is one of the key strategic objectives within the Housing Strategy 2023 to 2028 and will help develop and support a greener district and address the climate emergency. A key driver is to improve thermal performance of existing council homes through planned works and the retrofit carbon reduction programme to aid residents with maintaining warm homes. It is intended to require contractors to demonstrate how they will reduce their carbon footprint in service delivery.

1.2Thriving Places

Delivering a quality repairs service is essential. Residents often view how well the repairs service is run as representative of the performance of the council as a whole. The views of residents were key ill therefore be a key driver in designing and setting the new service standards. The tender sought to seek to understand the use of the local market in delivery of services thus aiding the prosperity of the local economy.

1.3Healthy Communities

The tender evaluation process assessed the social value that contractors will deliver and in so doing enhance and support local communities.

1.4Good Homes for All

Repairs and maintenance have a direct influence on the quality of the council’s housing stock and the wellbeing of residents. Homes are improved and repaired to increase the lifespan of a property’s fabric whilst ensuring that residents’ homes meet decency standards and comply with the Housing Health and Safety Rating system (HHSRS)

1.5Efficient and Effective

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAB3557(H) APDX 4 ITT: Annex 01: Specification: A: Term Brief: 02 Repairs and VoidsAppendix 209 KB Download
PDF
CAB3557(H) Appendix 1 Tender Evaluation Report: WCC Electrical services ProcurementAppendix 278 KB Download
PDF
CAB3557(H) Appendix 2 ITT Evaluation Report: WCC Heating ProcurementAppendix 277 KB Download
PDF
CAB3557(H) Appendix 3- RFT Evaluation Report: WCC Repairs and Maintenance ProcurementAppendix 366 KB Download
PDF
Repairs and Maintenance Procurement and Audit updateReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
MR
Councillor Mark ReachChairperson, present
KB
Councillor Kathleen BeckerCommittee Member, apologies, sent representative
NC
Councillor Neil Cutler OBECommittee Member, present
AC
Councillor Angela ClearNon-voting Member, present
CH
Councillor Caroline HorrillNon-voting Member, present
MP
Councillor Margot PowerNon-voting Member, present
SW
Councillor Suzanne WhiteNon-voting Member, apologies, sent representative
AA
Councillor Andrew AdamsGuest, in attendance
DL
Councillor Danny LeeNon-voting Deputy, present as substitute
MT
Councillor Martin TodDeputy, present as substitute

More from Winchester Cabinet Committee: Housing

All decisions
MeetingDecisionOutcome
6 Jul 2026 Minutes of the previous meeting held on 2 February 2026That the minutes of the previous meeting held 2 February 2026 be agreed as a correct record. Agreed Open
6 Jul 2026 New homes programme update (presentation)That the update regarding the new homes programme be noted. Noted Open
6 Jul 2026 Retrofit programme update (presentation)That the update regarding the retrofit programme be noted. Noted Open
6 Jul 2026 Housing Consumer StandardsThat it be noted that HQN have been commissioned to assess the Landlord S ervice agains t the C onsumer S tandards . ... Noted Open
6 Jul 2026 Tenancy Strategy and Tenancy Management StrategyThat the Tenancy Strategy 2026–2031 attached at Appendix 1 to report CAB3558(H) be approved. 2. That the Housing Serv... Approved Open