Nutrient Mitigation programme

Noted Committee 1 paper

AI summaryWinchester City Council's Health and Environment Policy Committee noted a progress update on the Nutrient Mitigation Programme, which upgrades wastewater treatment works to generate nutrient credits for new housing development.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action authorised at this meeting
Money£900,000Capital budget for PfSH WwTW upgrades
What happens nextWwTW upgrade delivery continuesSix tranches running to Q3 2027/28
Who it affectsDevelopers and residentsDevelopers buy credits, septic tank owners can get grants

What was decided

The committee received the Nutrient Mitigation Programme briefing and noted the comments raised.

No new decision was taken; the briefing updates on work already authorised under Cabinet decisions CAB3470 and CAB3459, with £400,000 and £900,000 capital budgets respectively. Report P9, P22, P23

Delivery of WwTW upgrades will continue in six tranches, with no more than three to four active installations at any one time because of limited engineering team capacity. Report P11, P12, P13, P14, P15, P16, P17

Why

New housing in the East Hampshire, Test, and Itchen catchments must be nutrient neutral for nitrogen, with the Itchen also requiring phosphorus neutrality, and the programme provides mitigation to support development. Report P8

Upgrading council WwTWs generates nitrogen and phosphorus credits the council can sell, while also reducing running costs on HRA sites such as Furzeley Corner where annual costs per property fell from £8.3k to £500. Report P9

Some credits support the council's own New Homes developments, helping to deliver affordable council housing, with the remainder sold to developers. Report P9

What happens next

Continue delivery of the six tranches, including Doctors Lane and Meonwara Crescent, plus PfSH priority sites The Brook, Couch Green, and Woodland Close, with a single contractor to be procured for Tranches 2 and 3. Report P9, P13, P14, P15

Winchester City Council will act as Monitoring Authority for the Solent Householder Septic Tank Upgrades Programme, starting with around 33 upgrades in the River Itchen Headwaters around Bishop's Sutton, secured by a 100 year unilateral undertaking. Report P20

Engage with the new Environmental Delivery Plans and Nature Restoration Fund levy being introduced under the Planning and Infrastructure Act 2025, while MHCLG has confirmed existing projects must continue in the meantime. Report P21

The money

  • £113k Total spend to date on Furzeley Corner WwTW works Report P9
  • £3,250 Price per nitrogen credit (or part thereof) Report P9
  • £50,000 Price per phosphorus credit (or part thereof) for most schemes Report P9
  • £100k Higher price per phosphorus credit (or part thereof) at The Goodens because of upstream location Report P9
  • £224k Invoiced to date for Northington Road credits, with £190k further expected Report P9
  • £400,000 Capital budget authorised by Cabinet in July 2024 (CAB3470) for New Homes and HRA WwTW upgrades Report P9, P22
  • £900,000 Capital budget authorised by Cabinet in September 2024 (CAB3459) for PfSH WwTW upgrades Report P9, P23
  • £16,000 Fee included in the Business Case for the council's monitoring role on the Solent Septic Tank Upgrade scheme Report P20

Options considered

  • Rejected: Upgrade Hobbs Close WwTW under Tranche 2. Hydrogeology studies showed lag time prevents phosphorus credits and limits nitrogen credits, so not worth the investment Report P9
  • Rejected: Take forward Hoyle Close and Foresters Cottages cost reduction sites. No viable solution due to local geology; no infiltration possible and no river to discharge to Report P9
  • Rejected: Include Beech Grove, Gorse Down, Lambourne Close, and Westwood View in the PfSH programme. Lag times of 9 to 16 years make them ineffective as phosphorus mitigation Report P9

Implications

  • Financial: Revenue from credit sales at £3,250 per nitrogen credit and £50,000 per phosphorus credit, with £224k already invoiced from Northington Road and £190k further expected. Report P9
  • Legal: Nutrient mitigation is secured through Section 106 agreements with monitoring fees, and the Solent Septic Tank Upgrade scheme uses a 100 year unilateral undertaking that the council will enforce. Report P20, P21
  • Climate: The programme reduces nitrogen and phosphorus entering the East Hampshire, Test, and Itchen catchments, supporting nutrient neutrality for new housing and protecting the Solent. Report P8, P9
  • Risk: The Planning and Infrastructure Act 2025 introduces Environmental Delivery Plans and a Nature Restoration Fund levy; the implications for existing mitigation schemes are not yet clear, although MHCLG has confirmed projects must continue. Report P21
  • Staffing: Only sufficient engineering capacity to oversee a maximum of three to four active WwTW installations at any one time, which shapes the six tranche phasing. Report P11
  • Other: Cross boundary working with neighbouring authorities, including Fareham Borough Council as Lead Authority for the Hinton Ampner scheme and the Solent Mitigation Partnership managing PfSH credit sales. Report P9, P20

Who and where

  • Developers needing nitrogen and phosphorus credits to make new housing nutrient neutral Report P8, P9
  • Households with private septic tanks in the River Itchen Headwaters around Bishop's Sutton, eligible for upgrade grants Report P20
  • Council tenants on HRA sites benefitting from lower WwTW running costs, for example at Furzeley Corner Report P9
  • Future residents of new housing in the East Hampshire, Test, and Itchen catchments Report P8
  • Neighbouring authorities relying on cross boundary mitigation schemes in the Winchester district Report P21
  • The National Trust, as landowner for the Hinton Ampner mitigation scheme Report P20

Timeline

  • May 2026: Furzeley Corner WwTW works completed (paragraph 9 records June 2026) Report P9, P13
  • End of May 2026: Solent Householder Septic Tank Upgrades Programme launched Report P20
  • Q2 2026/27: Doctors Lane WwTW delivery due, subject to easement completion by Legal team Report P9, P13
  • Q3 2026/27: Meonwara Crescent WwTW delivery due, and Tranche 2 New Homes and HRA sites installation Report P9, P13, P14
  • Q4 2026/27: Tranche 3 PfSH priority sites (The Brook, Couch Green, Woodland Close) installation Report P15
  • Q1 2027/28: Tranche 4 PfSH sites (North Drive, The Hallway, Woodlark Cottages) installation, subject to PfSH agreement Report P16
  • Q2 to Q3 2027/28: Tranches 5 and 6 cost reduction sites installation Report P17
  • 8 July 2026: Health and Environment Policy Committee considers Nutrient Mitigation Programme briefing Report P1

Plain English for the jargon

  • WwTW: Wastewater Treatment Works
  • LPA: Local Planning Authority
  • PfSH: Partnership for South Hampshire
  • SMP: Solent Mitigation Partnership, based at Fareham Borough Council
  • PTP: Package Treatment Plant
  • HRA: Housing Revenue Account
  • S106: Section 106 planning obligation used to secure mitigation and monitoring
  • LMNF: Local Nutrient Mitigation Fund
  • EDP: Environmental Delivery Plan under the Planning and Infrastructure Act 2025
  • NRF: Nature Restoration Fund levy under the Planning and Infrastructure Act 2025
  • OBC: Outline Business Case
  • MHCLG: Ministry for Housing, Communities and Local Government
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the briefing paper be received and the comments raised by the committee, as summarised above, be noted.
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Health and Environment Policy Committee

HEP Briefing Note Subject: Nutrient Mitigation Programme Service Area: Sustainability and Natural Environment Date: 8th July 2026

Matters for the Committee to Consider: 1. The progress update on the council’s WwTW upgrade projects across the three delivery strands: i.e., cost reduction sites; New Housing/HRA sites; and PfSH sites.

2. The programme management and governance framework, delivery timescales, and current risks for the programme.

3. The emerging third-party nutrient mitigation schemes being delivered within the Winchester district including the Solent Householder Septic Tank Upgrades Programme and the Hinton Ampner Nutrient Mitigation Scheme.

4. The role of the council as Local Planning Authority (LPA) in securing nutrient mitigation and monitoring, and the increasing number of third-party Strategic Mitigation schemes.

Purpose This note provides councillors with a comprehensive overview of the council’s nutrient mitigation programme. It provides an update on the delivery progress of the various constituent projects and activities within the programme. It also sets out the programme management and governance framework and delivery timescales and a summary of emerging third-party nutrient mitigation schemes in the Winchester district.

The information shared here, together with the water management briefing also being considered at this meeting, aligns with the points considered by the Committee Nutrient Neutrality Members’ Working Group.

Introduction The Winchester district falls within three riverine catchments in relation to nutrient neutrality – the East Hampshire, Test, and Itchen catchments. Within the East Hampshire and Test catchments, new housing development is required to be nutrient neutral for nitrogen. Within the Itchen catchment new housing development is required to be nutrient neutral for both phosphorus and nitrogen. The council is currently developing a programme of mitigation solutions to reduce nutrient pollution and facilitate the delivery of new development within the Winchester district. The council is upgrading its wastewater treatment works (WwTW) within the district to generate nitrogen and phosphorus mitigation and generate additional revenue through the sale of credits. The council is also supporting the Solent Mitigation Partnership (SMP) and other third-party developers to develop additional mitigation schemes within the district. Additional programme management resource has been put in place to manage and coordinate the delivery of the various projects and activities within the council’s nutrient mitigation programme. This report provides an update on the delivery of the council’s WwTW upgrades; sets out the governance framework and delivery plan for the programme; identifies emerging third-party mitigation schemes in the district; and highlights current programme risks and issues. It also considers the role of the council as competent authority in considering nutrient mitigation strategies that facilitate development proposals and ensuring that it is legally secured and properly monitored for the requisite period.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Nutrient Mitigation programmeReport 348 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
JP
Councillor Jerry PettChairperson, present
VA
Councillor Vivian AchwalCommittee Member, present
AB
Councillor Adrian BrophyCommittee Member, present
DL
Councillor Danny LeeCommittee Member, present
CP
Councillor Clare PinnigerCommittee Member, present
MP
Councillor Margot PowerCommittee Member, present
JT
Councillor John Tippett-CooperCommittee Member, present
JW
Councillor Jan WarwickCommittee Member, apologies, sent representative
CW
Councillor Chris WestwoodCommittee Member, present
PL
Councillor Paula Langford-SmithDeputy, present as substitute

More from Winchester Health and Environment Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThat the minutes of the previous meeting held on the 8 July 2026 be approved and adopted. Approved Open
17 Sep 2026 To note the Work Programme for 2026/27That the work programme for 2026/27 be received and noted. Noted Open
8 Jul 2026 Appointment of Vice-Chairperson for Municipal Year 2026/27That Councillor Brophy be appointed Vice-Chairperson for the 2026/27 municipal year Decided Open
8 Jul 2026 To note the dates and times of future meetings of this committee.That the date of future meetings for 2026/27, as set out on the agenda, be noted. Noted Open
8 Jul 2026 MinutesThat the minutes of the previous meetings held on the 25 February 2026 be approved and adopted. Approved Open