Workforce Report 25/26 (AG186)

Noted Finance 1 paper

AI summaryWinchester City Council's Audit and Governance Committee noted the 2025/26 annual workforce report, covering 472 staff, 10.74% turnover, 4.73 days average sickness absence and ongoing preparation for local government reorganisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport and appendices noted by committee
MoneyNot stated
What happens nextEmployee survey and L&D programmeAnnual survey 24 June to 24 July 2026; L&D delivery June 2026 to March 2028
Who it affectsCouncil workforce472 permanent and fixed-term staff as at 31 March 2026

What was decided

The committee noted the Workforce Report 2025/26 and the supporting data in its appendices. Report P1

Why

The performance of the council's workforce is critical to the delivery of all priorities set out in the Council Plan, and monitoring employment metrics enables proactive employment practices. Report 1.1, 4.1

The report is for information only, with no decisions required and no consultation or communication needed. Report 6.1, 12.1

What happens next

The corporate learning and development programme will be delivered from June 2026 to March 2028, covering leadership and management, digital upskilling, change readiness and health and safety. Report 11.13, 11.14

The 2026 employee survey will run for four weeks from 24 June to 24 July 2026, with five additional Local Government Reorganisation (LGR) specific questions. Report 11.22

HR will review wellbeing support regularly and continue to meet monthly with UNISON, with meetings expected to become more frequent over the next 18 months as LGR progresses. Report 11.40, 11.56

Options considered

  • Chosen: Note the report and appendices. Report is for information only; no decisions required. Report P1, 12.1

Implications

  • Staffing: Headcount rose to 472 (from 460), a 2.61% increase; 64 external appointments and 50 leavers gave a turnover rate of 10.74%. Report 11.3, 11.4, 11.5, 11.7
  • Staffing: Average sickness absence fell to 4.73 days per employee (from 6.71), below the 6.2 day public sector average. Report 11.30, 11.31
  • Legal: The Employment Rights Act 2025 passed into law at the end of 2025; HR will update policies and practises, with particular focus on dismissal processes, contractual arrangements, workforce flexibility and employee relations. Report 11.53, 11.54
  • Equalities: The mean gender pay gap as at 31 March 2025 was 6.4% (6.6%); the council reports no differential impact on any specified group. Report 8.1, 8.2, 11.42
  • Staffing: 'People and Culture' is identified as a critical LGR workstream covering workforce planning, staff engagement and leadership development ahead of transition to a unitary authority. Report P22, 11.56
  • Financial: Financial implications include the cost of recruiting and inducting new joiners, use of agency staff for hard to fill essential vacancies, sickness absence and investment in learning and development. Report 2.1

Who and where

  • Winchester City Council's 472 permanent and fixed-term staff Report 11.3
  • Council managers and team leaders (around 30 attended a management and leadership training programme in June 2025) Report 11.50
  • 7 current full-time apprentices and 3 upskilling apprentices Report 11.16

Timeline

  • April 2025: Statutory Neonatal Care Leave introduced and policies updated Report 11.55
  • 1 April 2025 to 31 March 2026: Reporting period covered by the workforce report Report 11.1
  • July 2025: Council achieved DAHA Gold Accreditation for domestic abuse response Report 11.49
  • End of 2025: Employment Rights Act 2025 passed into law Report 11.53
  • 2025 to 2027: Phased implementation of over 25-30 ERA reforms Report 11.53
  • 31 March 2026: Headcount of 472 staff and as-at date for workforce data Report 11.3
  • June 2026 to March 2028: Delivery of the corporate learning and development programme Report 11.14
  • Summer/autumn 2026: Three current full-time apprentices expected to complete their apprenticeship Report 11.16
  • Next 18 to 24 months: Heightened LGR transition activity, with more frequent UNISON engagement Report 11.46, 11.56
  • 24 June to 24 July 2026: 2026 annual employee survey to run for four weeks Report 11.22

Plain English for the jargon

  • LGR: Local Government Reorganisation, the process of restructuring councils, in this case towards a new unitary authority.
  • FTE: Full-time Equivalent, a unit measuring workforce size by hours worked.
  • L&D: Learning and Development.
  • ELB: Executive Leadership Board, the council's senior management group.
  • SINGs: Staff Identity Networks Groups, staff-led inclusion networks.
  • ERA: Employment Rights Act 2025.
  • DAHA: Domestic Abuse Housing Association, an accreditation scheme.
  • MHCLG: Ministry of Housing, Communities and Local Government.
  • TNA: Training Needs Analysis, an organisation-wide exercise to identify learning priorities.
  • WAP: Wellness Action Plan, a tool to support employee mental health.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the report and the data in the appendices be noted.
Word for word from the decision Winchester published for this meeting. Source: democracy.winchester.gov.uk

Follow this further

Built from Winchester's papers

What the report saysPro

Report to Audit and Governance Committee

Recommendations

1. Note the report and the data in the appendices. AG186

IMPLICATIONS:

1 COUNCIL PLAN OUTCOME

1.1The performance of the council’s workforce is critical to the delivery of all priorities set out in the Council Plan.

Financial implications

2.1Maintaining staffing levels and having the right staff with the right skills is critical to the delivery of the council’s services and priorities. Financial implications of the workforce matters covered in this report include: the cost of recruiting and inducting new joiners; the use of agency staff for difficult to fill essential vacancies; sickness absence; and investment in learning and development.

3 LEGAL AND PROCUREMENT IMPLICATIONS

3.1None.

4 WORKFORCE IMPLICATIONS

4.1Employees are critical to the delivery of the council’s services and priorities and monitoring and reporting on key employment metrics enables proactive employment practises.

5 PROPERTY AND ASSET IMPLICATIONS

5.1None.

6 CONSULTATION AND COMMUNICATION

6.1This report is for information only and therefore no consultation or communication is required.

7 ENVIRONMENTAL CONSIDERATIONS

7.1None.

8 PUBLIC SECTOR EQUALITY DUTY

8.1There is no differential impact on a specified group as all HR matters are applied consistently.

8.2As required nationally, the council reports on any potential discrepancies in pay, based on gender (“Gender Pay Gap” reporting), in accordance with the statutory timeframe. AG186

9 DATA PROTECTION IMPACT ASSESSMENT

9.1This report does not include any confidential data and therefore a data protection impact assessment is not required.

Risk management

Risk Mitigation Opportunities Financial Exposure Failure to apply pay Consistent Positioning the principles and rules application of pay council as an fairly and consistently principles and rules. Employer of Choice. leading to discrimination and/or legal challenge. Exposure to challenge Statutory reporting is Failure to comply with embedded within statutory reporting HR’s annual work requirements, programme, and resulting in adverse within the committee local media coverage work programme or legal challenge. where appropriate, to ensure publication within statutory timeframes. Reputation Ongoing workforce Failure to deliver monitoring to enable public services and early identification the Council Plan due and remedial action to reduced workforce where recruitment capacity, leading to difficulties and/or high public criticism and/or sickness levels could adverse local media impact on the coverage. council’s ability to deliver public services and the Council Plan. Innovation None None Property None None Community Support None None Timescales None None Project capacity None None Local Government This report provides a Reorganisation ‘snapshot’ of workforce metrics AG186

and commentary for the 2025/26 financial year and its content has limited impact on LGR. However, ‘People and Culture’ will be a critical LGR workstream as we prepare for change and transition to any new Unitary Authority. Other None None

11 SUPPORTING INFORMATION:

11.1The purpose of this report is to provide the Audit and Governance Committee with an overview of the workforce of the council and a summary of key HR activities for the year 1 April 2025 to 31 March 2026. Figures throughout the report show prior year equivalents in brackets.

11.2Appendix 1 provides a range of indicators supporting the report commentary relating to: (i) the council’s staff establishment (ii) recruitment and turnover (iii) sickness absence (iv) equality

Staff Establishment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Workforce Report 25/26 (AG186)Report 281 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
JM
Councillor Jonny MorrisChairperson, apologies
CC
Councillor Chris ChamberlainVice-Chair, in the Chair, present
SA
Councillor Sudhakar AchwalCommittee Member, apologies, sent representative
AA
Councillor Andrew AdamsCommittee Member, present
RA
Councillor Rachel AronCommittee Member, present
LB
Councillor Liam Bailey-MorganCommittee Member, present
MB
Councillor Michael BennettCommittee Member, present
AB
Councillor Adrian BrophyCommittee Member, present
SG
Councillor Stephen GodfreyCommittee Member, present
CP
Councillor Clare PinnigerDeputy, present as substitute
NC
Councillor Neil Cutler OBEGuest, in attendance

More from Winchester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 To note the Audit & Governance work programme 2026/27RESOLVED: That, subject to the above correction, the work programme for 2026/27 be noted. Noted Open
24 Sep 2026 Minutes of the previous meeting held on 16 July 2026RESOLVED: That the minutes of the previous meeting held 16 July 2026 be agreed as a correct record. Agreed Open
24 Sep 2026 Reserve Risk Assessment Update Report (AG196)RESOLVED: That the external auditor’s risk assessment and the implications for the 2025/26 audit be noted. Noted Open
24 Sep 2026 Internal Audit Progress Report (AG194)RESOLVED: That the Internal Audit Progress Report 2026-27 (August 2026) be noted. Noted Open
24 Sep 2026 Q1 Governance Monitoring (AG193)RESOLVED: That the contents of the report be noted, including the progress made against the actions in the Annual Gov... Noted Open