Resolved
That the progress made to date in achieving this Corporate Plan goal be noted.
Sustainable Communities Overview and Scrutiny Committee noted this item on Monday 26 September 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress made to date in achieving this Corporate Plan goal be noted.
WIRRAL COUNCIL SUSTAINABLE COMMUNITIES OVERVIEW AND SCRUTINY 26TH SEPTEMBER 2011 SUBJECT: CORPORATE GOAL“HAVE A SAFE AND WELL-MAINTAINED HIGHWAY NETWORK FOR ALL USERS” PROGRESS REPORT WARD/S AFFECTED: ALL REPORT OF: DIRECTOR OF TECHNICAL SERVICES RESPONSIBLE PORTFOLIO CLLR HARRY SMITH, STREETSCENE AND HOLDER: TRANSPORT SERVICES KEY DECISION? NO
1.0EXECUTIVE SUMMARY 1.1 The purpose of this report is to provide Members with a progress update on delivering services and plans which will provide assurance that, as prioritised within the Corporate Plan, all aspects of Wirral’s highway network are safe and well maintained, including an update on the performance measures in place for condition of the highway and casualty reduction.
1.2The maintenance of all aspects of the highway infrastructure is a statutory duty imposed on the Council as Highway Authority. The Highway Authority has a duty to prepare and undertake measures to improve road safety.
2.0RECOMMENDATION/S 2.1 Note the progress made to date in achieving this Corporate Plan goal.
3.0REASON/S FOR RECOMMENDATION/S 3.1 The Committee’s scrutiny of the progress of this Corporate Plan aim is an important factor in developing and improving the services provided for the safety and maintenance of highways, and ensuring that service objectives are achieved.
4.0BACKGROUND AND KEY ISSUES 4.1 As part of the ‘Your Neighbourhood’ theme within the Corporate Plan 2011 - 2014, one of the Council’s goals is ‘Have a safe and well-maintained highway network for all users.’ There are two strands to this particular goal: maintenance and road safety, and this report addresses these related activities. 4.1 Highway Maintenance
4.1.1 The highway network and other transport infrastructure assets together represent by far the largest capital asset the Council holds, and the value of replacing those assets is estimated to be £1.65 billion. The highway network for which Wirral Council is responsible comprises approximately 1,185 kilometres of road.
4.1.2 Inspection and maintenance of the highway network is carried out in accordance with policy adopted in 2005, and is broadly in line with published national guidance Well Maintained Highways, Well Lit Highways and Management of Highway Structures. The duty to maintain the highway, and to provide a robust defence against claims against the Council for slips, trips and falls is at the core of the management of the highways service.
4.1.3 The condition of the highway network carriageways is subject to objective annual assessment through condition surveys carried in accordance with national guidance, and has traditionally been measured through Best Value Performance Indicators (BVPI) and more recently National Indicators (NI). The measurement of carriageway condition indicators is still considered to be the most objective and appropriate means of assessing the deterioration of the network and the impact of maintenance investment; particularly in the light of well-documented deterioration caused through successive severe winters.
4.1.4 Accordingly, the success in achieving well-maintained highways within the Corporate Plan is measured through the annual assessment of three carriageway condition indicators, which have been adopted by the Merseyside Authorities within the Local Transport Plan 2011 to 2015 (LTP3):
• The length of principal classified roads requiring maintenance treatment (NI 168);
• The length of non-principal classified roads requiring maintenance treatment (NI 169); and
• The length of unclassified roads requiring maintenance treatment (BVPI 224b).
All of these are measured as a percentage of the network length.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Goal "Have a Safe and Well Maintained Highway Network for all Users": Progress ReportReport | 122 KB | DownloadRead as text |
Follow Sustainable Communities Overview and Scrutiny Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2011 | MinutesThat the of the meeting of the Committee held on 7 June 2011 be confirmed as a correct record. | Decided | Open |
| 26 Sep 2011 | Highways and Traffic Representation PanelThat the Minutes of the meeting of the be received. | Decided | Open |
| 26 Sep 2011 | Waste Strategy Review ScrutinyThat (1) [name removed] be thanked for his informative presentation; (2) the process that has been undertaken to deve... | Noted | Open |
| 26 Sep 2011 | Highway and Engineering Services Contract - Second Annual ReviewThat (1) [name removed] and his team be thanked for their attendance at the meeting; (2) [name removed] be thanked fo... | Noted | Open |
| 26 Sep 2011 | Shale Gas FrackingThat the contents of the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.