PLANNING COMMITTEE
Thursday, 17 September 2015
Present: Councillor A Leech (Chair)
Councillors M Daniel E Boult S Foulkes P Hayes J Walsh K Hodson I Williams D Mitchell D Elderton P Cleary
Deputies: Councillors T Johnson ( for D Realey) R Gregson ( for P Brightmore)
69 MINUTES
The Strategic Director for Transformation and Resources submitted the minutes of the meeting held on 20 August 2015.
Resolved – That the minutes be approved
70 MEMBERS' CODE OF CONDUCT - DECLARATIONS OF INTEREST
Members were asked to declare any disclosable pecuniary or non pecuniary interests in connection with any items on the agenda and to state the nature of the interest.
Councillor Steve Foulkes declared a prejudicial interest in connection with item 9 by virtue of his previous involvement with the application.
71 REQUESTS FOR SITE VISITS
Members were asked to submit requests for site visits before any applications were considered.
No such requests were made.
72 APP/15/00553: RIVERSIDE HOUSE, EAST STREET, SEACOMBE, CH41 1BY - APPLICATION FOR AN ANAEROBIC DIGESTION PLANT (2.8 MWTH) COMPRISING PROCESS TANKS, ASSOCIATED EQUIPMENT AND 1.4 MILE BIOMETHANE PIPELINE. The Strategic Director for Regeneration and Environment submitted the above application for consideration.
A Ward Councillor addressed the Committee
It was moved by Councillor Mitchell and seconded by Councillor Cleary and
Resolved (11:2) That the application be approved subject to the following conditions:
1. The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.
2. No development approved by this planning permission (or such other date or stage in development as may be agreed in writing with the Local Planning Authority), shall take place until a scheme that includes the following components to deal with the risks associated with contamination of the site shall each be submitted to and approved, in writing, by the local planning authority:
1) A preliminary risk assessment which has identified: all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors potentially unacceptable risks arising from contamination at the site.
2) A site investigation scheme, based on (1) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off site.
3) The results of the site investigation and detailed risk assessment referred to in (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken.
4) A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in (3) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. Any changes to these components require the express written consent of the local planning authority. The scheme shall be implemented as approved. 3. No occupation of any part of the permitted development shall take place until a verification report demonstrating completion of works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved, in writing, by the local planning authority. The report shall include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met. It shall also include any plan (a “long-term monitoring and maintenance plan”) for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action, as identified in the verification plan. The long-term monitoring and maintenance plan shall be implemented as approved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 209 KB | DownloadRead as text |
Follow Planning Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | MINUTESResolved – That the minutes of the Planning Committee held on 13 August 2026 be approved as a correct record. The Cha... | Approved | Open |
| 10 Sep 2026 | ADV/26/00958 - Corner Of Duke Street and Beckwith Street, Birkenhead, Wirral, CH41 8BBResolved (unanimously) – That the Assistant Director - Chief Planner be authorised to refuse the application, due to ... | Refused | Open |
| 10 Sep 2026 | APPH/26/01027 - 5 Woodcote Bank, Higher Bebington, Birkenhead, Wirral, CH42 4NLResolved – That the Planning Committee was content for the application to be withdrawn from the agenda and returned t... | Decided | Open |
| 10 Sep 2026 | APP/26/00691 - Lighthouse Inn, 228 Wallasey Village, Wallasey, Wirral, CH45 3LPResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... | Approved | Open |
| 10 Sep 2026 | APP/26/00814 - Grove House Hotel, 45 Grove Road, Wallasey Village, WirralResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.