Resolved
Resolved – That the report be noted.
Policy and Performance - Transformation and Resources Committee noted this item on Tuesday 22 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report be noted.
Policy and Performance - Transformation and Resources Committee Tuesday, 22 March 2016
REPORT TITLE: FINANCIAL MONITORING 2015/16 QUARTER 3
REPORT OF: Strategic Director: Transformation and Resources
REPORT SUMMARY This report sets out the financial monitoring information for Transformation and Resources in a format consistent across the Policy and Performance Committees. The report aims to give Members the detail to scrutinise budget performance for the Directorate. The financial information is for Quarter 3 (October-December 2015) and was reported to Cabinet on 22 February 2016.
RECOMMENDATION/S
1. That the forecast year end underspend of £3.45 million in the Transformation and Resources 2015/16 Revenue Budget position and actions taken during quarter 3 be noted.
2. That the capital expenditure position at the close of quarter 3 totalling £3.6 million against a revised Capital Programme of £7.3 million be noted
3. Members are requested to review the information presented to determine if they have any specific questions relating to the budget for the Transformation and Resources Directorate. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To ensure Members have the appropriate information to review the budget performance of the directorate.
2.0OTHER OPTIONS CONSIDERED
2.1This is a monitoring report but any options to improve the monitoring and budget accuracy will be considered.
3.0BACKGROUND INFORMATION
3.1CHANGES TO THE AGREED BUDGET
3.1.1 The 2015/16 Budget was agreed by Council on 24 February 2015; any increase in the Budget has to be agreed by full Council. Changes to the Budget since it was set are summarised in Table 1.
Table 1: 2015/16 Original & Revised Net Budget by Directorate £000’s OriginalApproved Approved Revised Net Budget Budget Net Budget Budget Changes Changes Prior Qtrs Qtr 3 Transformation & 31,947 -797 -110 31,040 Resources Net Cost of Services 31,947 -797 -110 31,040
3.1.2 The main budget movements in quarter three relate to adjustments within the support services budget. These adjustments have no effect on the net bottom line of the council as a whole.
3.2PROJECTIONS AND KEY ISSUES
3.2.1 The projected outturn position as at the end of December 2015, key issues emerging and Directorate updates are detailed in the following sections.
Table 2: 2015/16 Projected Budget variations by Directorate £000’s Directorates Revised Forecast (Under) RAGBY Change Budget Outturn Overspend Class from Quarter 3 prev Transformation & Resources 31,040 27,590 -3,450 Y -450 TOTAL 31,040 27,590 -3,450 -450
The report classifies the forecast under/overspends for the above areas using a colour RAGBY rating. The ratings are defined as follows: Extreme: Overspends Red (over +£301k), Underspend Yellow (over - £301k). Acceptable: Amber (+£141k to +£300k), Green (range from +£140k to - £140k); Blue (-£141k to -£300k). 3.3 DIRECTORATE UPDATES
Transformation & Resources
3.3.1 The projected saving has increased by £0.45 million in quarter 3 to £3.45 million. The increase is mainly due to increased vacancies within the directorate. The major element of the existing underspend (£2.5 million of the overall total) is within Treasury Management. This is from the continued use of internal cash flow to delay external borrowing and projected slippage within the Capital Programme (which delivers one-off in year savings). Other savings have arisen from continued vacancies during the year across a number of service areas.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring 2015/16 Quarter 3Report | 166 KB | DownloadRead as text |
Follow Policy and Performance - Transformation and Resources Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2016 | Customer Relationship Management System Update ReportResolved – (1) That the report be noted. (2) That the CRM development be placed on the Work Programme. (3) That an up... | Noted | Open |
| 22 Mar 2016 | Community Safety PartnershipResolved – (1) That the content of the report and the progress made in the delivery of the two 2020 pledges, be noted... | Noted | Open |
| 22 Mar 2016 | Work Programme Update ReportResolved –That with the addition of an item on the Customer Relationship Management System, the work programme be app... | Approved | Open |
| 1 Feb 2016 | Local Welfare Assistance SchemeResolved – (1) That this Committee acknowledges the progress made and recommends to Cabinet that the actions introduc... | Decided | Open |
| 1 Feb 2016 | Policy Inform Briefing PaperResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.