Item66
Resolved
RESOLVED (One abstention) - That (1) the Quarter 1 forecast year end overspend of £4.2 million, of which £3.9 million relates to Children’s Services and related legal costs, be noted; (2) the £8.5 million distribution from the Revenue Budget Contingency be approved; (3) the receipt of £0.18 million of New Homes Bonus Returned Funding Grant, which will be added to General Fund Balances, be noted; (4) Officers continue to identify actions and take measures to effectively manage the overall budget and reduce the impact of the projected overspends; (5) the £1.225 million ‘one-off’ funding from General Fund balances for an extended borough wide programme of tree maintenance works be approved; and (6) the £0.125 million for a rolling programme of tree inspection and maintenance be added to the Council budget projections from 2018/19 onwards, be noted.
Word for word from the decision Wirral published for this meeting.
Source: democracy.wirral.gov.uk