Resolved
Resolved – That the report and presentation be noted and the progress in re-commissioning these services to meet the October 2018 deadline, be endorsed.
Business Overview and Scrutiny Committee noted this item on Wednesday 4 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report and presentation be noted and the progress in re-commissioning these services to meet the October 2018 deadline, be endorsed.
WIRRAL COUNCIL BUSINESS OVERVIEW & SCRUTINY COMMITTEE 4 JULY 2018
REPORT TITLE RE-COMMISSIONING OF HIGHWAY SERVICES FROM OCTOBER 2018
REPORT OF STRATEGIC COMMISSIONER FOR ENVIRONMENT
REPORT SUMMARY
The Council and contractor Bam Nuttall (BAMN) have agreed that the current strategic contract for Highway services will come to an end on 30th September 2018 after one six month extension to the original four year contract that commenced in April 2014.
Taking account of the limited time period to re-commission these services, an options appraisal exercise using the Highway Maintenance Efficiency Programme (HMEP) Procurement Route Choices Toolkit indicates the most viable way forward is to bring these services back under the direct control of the Council.
The re-commissioning of these services based on this ‘direct control/ ownership’ model was approved by the Leader of the Council on 28th November 2017. This report and accompanying presentation by officers provides an update on progress in re-commissioning these services to meet the October 2018 deadline.
These services are delivered across all Wards though there are no changes to specific service policies or standards associated with this re-commissioning exercise. In terms of Wirral Plan Pledges, these services directly contribute to the Transport and Technology Infrastructure Pledge which in turn plays a key role in supporting many of the outcomes under the Business and Environment themes in the Plan.
RECOMMENDATION/S
Committee is requested to note and endorse the progress in re-commissioning these services to meet the October 2018 deadline. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Re-commissioning these services to ensure new arrangements are in place for October 2018 when the current contract expires is important to ensure continuity of service delivery. This is especially important for the day-to-day routine work such as pothole and street lighting repairs that ensure the Council meets its statutory obligations as Highway Authority.
2.0OTHER OPTIONS CONSIDERED
2.1Alternative re-commissioning options were considered as part of the options appraisal exercise using the Highway Maintenance Efficiency Programme (HMEP) Procurement Route Choices Toolkit. Taking account of the limited time period available, this work highlighted the most viable option is to bring these services back under the direct control of the Council.
2.2The following critical success factors were used in the options appraisal process:
Strategic fit – aligns with strategic aims Value for money – delivers value for money Manageable/ flexible – meets the level of service required Affordable – delivered within budget Achievable – delivered within timescale
3.0BACKGROUND INFORMATION
3.1Wirral’s highway network, the Council’s biggest asset, is currently worth £2.48 billion and consists of approximately 1,200 kilometres of road, and is currently maintained via the strategic contract with BAM Nuttall (BAMN).
The contract, which started in April 2014 and is worth around £6 million per year, will come to an end on 30th September 2018 having been extended for 6 months past the original four year term. The following service areas are covered by the current contract:
Carriageways, footways Drainage, culverts and drains Street Lighting Signs and road markings Structures Winter maintenance Coastal protection infrastructure maintenance
3.2In summary, the contract consists of two broad types of work:
Routine/ reactive work – day-to-day revenue-funded activity such as pothole and street lighting repairs, traditionally undertaken by resources directly employed by the main contractor and crucial to enabling the Council to discharge its statutory responsibilities as Highway Authority; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Re-Commissioning of Highway Services from October 2018Report | 120 KB | DownloadRead as text |
Follow Business Overview and Scrutiny Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Mar 2020 | Update on Liverpool City Region DevelopmentsResolved – That the report be noted. | Noted | Open |
| 4 Mar 2020 | NNDR and Business Rates RetentionResolved – That the report be noted. | Noted | Open |
| 4 Mar 2020 | Financial Monitoring Report Quarter 3 2019/20Resolved – That the report be noted. | Noted | Open |
| 4 Mar 2020 | Management of Campervans in Wallasey and New Brighton Scrutiny ReviewResolved – (1) That the findings of the Scrutiny Review Panel be approved. (2) That the report be referred to the mos... | Approved | Open |
| 4 Mar 2020 | 2019/20 Quarter 3 Wirral Plan PerformanceResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.