Resolved
That the report be noted.
Environment Overview and Scrutiny Committee noted this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
Environment Overview and Scrutiny Committee Wednesday, 13 March 2019
REPORT TITLE: Financial Monitoring Report Quarter 3 2018/19
REPORT OF: Director of Finance & Investment (S151)
REPORT SUMMARY This report sets out the financial monitoring information for the Environment Overview & Scrutiny Committee. The report provides Members with detail to scrutinise budget performance for this area of activity. The financial information is at close of quarter 3 2018/19.
Information has been drawn from the relevant sections of the most recent Cabinet revenue and capital monitoring reports and combined with additional relevant service information to produce a bespoke report for this Overview & Scrutiny Committee. The report includes the following:
• Performance against the revenue budget (including savings) • Performance against the capital budget
RECOMMENDATION/S 1 That members note the report and appendices. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S 1.1 Overview and Scrutiny Committees receive regular financial updates throughout the year. These allow Committees to understand the financial position of the council and to scrutinise decisions and performance as required.
2.0OTHER OPTIONS CONSIDERED 2.1 Not applicable
3.0BACKGROUND INFORMATION
3.1The position financially at quarter 3 for the council as a whole was presented at Cabinet on the 18th of February 2019. The quarter 3 revenue forecast is an overall overspend of £0.72 million for the year. Delivery Services forecast overspends make up all of this amount of which £0.2 million belongs under the Environment theme.
The quarter 3 capital report recommends that Cabinet agree the 2018/19 Capital Programme of £53.5 million which takes into account re-profiling identified during 2018/19. Expenditure to date is £33.3 million.
3.1.0 CHANGES TO THE AGREED BUDGET ENVIRONMENT
3.1.1 The 2018/19 Budget was agreed by Council on 5 March 2018. Any increase to the overall Council Budget (but not use of the existing budget contingency) requires agreement by full Council. The Environment Theme includes activity from 5 Cabinet portfolios as shown in table 1 below.
Table 1: 2018/19 Original & Revised Net Budget Theme Portfolio Q2 Budget Revised Budget Changes Net Q3 Budget
£000 £000 £000 Environment Environment 28,632 16 28,648 Housing and 19,687 414 20,101 Planning Leisure and 17,761 1 17,762 Recreation Services Net Cost of Services 66,080 431 66,511
Budget movements in quarter three cover a number of issues. The largest of these is the movement of £0.4m into Housing and Planning. This is a reorganisation of staffing budgets within customer services. These movements have no effect on the bottom line budget of the Council and are just adjustments to better reflect where budgets should be placed. 3.2.0 PROJECTIONS AND KEY ISSUES
3.2.1 The projected outturn position as at the end of December 2018 and Wirral Plan: 2020 Vision Themes updates are detailed in the following sections.
Table 2: 2018/19 Projected Budget variations Theme Portfolio Revised Forecast (Under) Budget Outturn Overspend Quarter 3 Environment Environment 28,648 29,174 526 Housing and Planning 20,101 19,954 -147 Leisure and Recreation 17,762 17,586 -176 Services TOTAL 66,511 66,714 203
Environment
The Environment portfolio continues to face pressures from the non- achievement of savings within Waste & Environment being £0.4m from expected contract efficiencies and £0.2m from reduced targeted garden waste income where attracting additional users has not matched budgeted expectations
Housing and Planning
The underspend in this area is due to in year savings from contract efficiencies found within supported housing.
Leisure and Recreation Services
Within Parks and Gardens there is a £0.2m underspend that includes extra income from Bereavement Services and delays in recruiting to vacant posts. This is netted down by overspends elsewhere in Leisure and Recreation Services.
3.3.0 IMPLEMENTATION OF SAVINGS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Report Quarter 3 2018/19Report | 120 KB | DownloadRead as text |
Follow Environment Overview and Scrutiny Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Mar 2020 | 2019/20 Q3 Financial Monitoring ReportResolved - That the report and appendices be noted . | Noted | Open |
| 12 Mar 2020 | Tree Strategy Scrutiny ReviewResolved - That (1) the findings and recommendations contained within the report be approved (2) the report be presen... | Approved | Open |
| 12 Mar 2020 | A new climate change strategy for wirralResolved – That (1) the new strategy and the steps taken by the Cool Wirral Partnership to create an up to date frame... | Noted | Open |
| 12 Mar 2020 | Future provision of floral pavilion theatre and conference centre - updateResolved - T hat: (1) the offer received following the bid process detailed in the report does not fulfil the aspirat... | Decided | Open |
| 12 Mar 2020 | Flood Risk Management Annual ReportResolved – That the content of the report be noted and the action taken with respect to Flood Risk Management during ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.