Environment Overview and Scrutiny Committee noted this item on Tuesday 24 September 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED : That 1) the Committee note the report and support the continuation of work with Agencies and the Friends of Hilbre Island Group following the fire on Hilbre Island; 2) the Cabinet Member be asked to allow a full options appraisal to be undertaken for a range of actions to be considered based on previous reports and new inspections being conducted; and 3) a Capital bid be produced to improve the listed properties on the island, including vacant properties to bring them back into use.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment Overview and Scrutiny Committee
Environment Overview and Scrutiny Committee Tuesday, 24 September 2019
REPORT TITLE: HILBRE ISLAND INCIDENT REPORT
REPORT OF: DAVID ARMSTRONG, ASSISTANT CHIEF EXECUTIVE
REPORT SUMMARY
In 2016 a report to assess the stability of existing sandstone walls and their likelihood of failure and other health and safety risks associated with maintenance of the walls on Hilbre was undertaken and from this several recommendations were made. The option of infilling an island littoral opening (a cave formed primary by the wave action of the sea) below a section of the cliff face and restoring the dressed sandstone walling was taken and a project was initiated to undertake this work. Work started in July 2019 to seal the island littoral opening. During the construction phase to rebuild the sandstone walls, the polyurethane foam product being used to give additional structural support to the cliff caught fire. Work ceased on the island following the fire and investigations were initiated. Safety measures were immediately put into place to secure the area. The Committee is asked to discuss the options available to either protect the area from further erosion through construction methods or to allow a natural demise of sections of cliff. As this is a live incident Members will be updated on the findings of the investigations as they are gathered.
The report supports the Wirral Plan 20/20 pledges through:
- Attractive Local Environment
- Assets and Buildings are fit for purpose
WARDS AFFECTED: West Kirby
THIS IS NOT A KEY DECISION RECOMMENDATION/S
1. That the Committee be requested to note the report and to support the continuation of work with Agencies and the Friends of Hilbre Island Group following the fire on Hilbre Island
2. That the Committee asks the Cabinet Member to allow a full options appraisal to be undertaken for a range of actions to be considered based on previous reports and new inspections being conducted
3. That a Capital bid be produced to improve the listed properties on the island, including vacant properties to bring them back into use. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The recommendations made will continue to address the concerns raised in the 2016 report and deal with ongoing incident findings. By addressing the preservation needs of assets on the island this will provide a commitment to the special environmental interest of the island going forward.
2.0OTHER OPTIONS CONSIDERED
2.1The 2016 report gave clear expert advice on the safety of Hilbre Island, these options were considered by officers in terms of priority order such as signage and cordoned areas, followed by more engineered projects to provide stability of the cliff and any island littoral openings which had formed.
2.2To do nothing with the wall and island littoral opening would cause the defences to deteriorate and leave the cliff to function naturally thereafter.
2.3Import rock to provide a buttress directly in front of the cliff, this would incur significant cost.
2.3Filling and sealing of the island littoral entrance; the use of polyurethane foam was chosen over more traditional construction materials due to the vehicular access issues of the island, its structural properties and longevity of the repair.
3.0BACKGROUND INFORMATION
3.1Hilbre Island is formed by natural outcropping bedrock that is subject to natural erosion. In the 1830’s Mersey Dock and Harbour Company purchased the islands, during this ownership sections of the sandstone cliffs were reinforced with near vertical profile infills made up of sandstone blocks believed to have been constructed during the second half of the 19th century. It is thought that due to the importance of the buildings and equipment on the island, such works would protect these assets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment Overview and Scrutiny Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
A new climate change strategy for wirralResolved – That (1) the new strategy and the steps taken by the Cool Wirral Partnership to create an up to date frame...
Flood Risk Management Annual ReportResolved – That the content of the report be noted and the action taken with respect to Flood Risk Management during ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.