Resolved (unanimously) – That this Committee: (1) approves the implementation and upgrade from the current unsupported version of Oracle (Release 11) to a new cloud solution; (2) approves the budget and allocation of funding of £4.6 million (£2m capital / £2.6m revenue) for transformation projects that deliver ongoing savings; (3) approves the award of a five-year contract with the option to extend for another two years to the company named in the Full Business Case (FBC) via the Crown Commercial Service (CCS) Data and Application Solutions Framework, Agreement (RM3821) for: · New cloud platform licenses for a 5-year (with the option to extend for a further 2: 5+2 years) period · Implementation partner to implement the new platform for a total value detailed in the FBC. (4) re-appoints the existing Members of the Working Group, Councillors Chris Carubia, Jeff Green and Paul Stuart, to monitor project performance during Delivery phase.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
POLICY AND RESOURCES COMMITTEE Wednesday, 20 January 2021
REPORT TITLE: SMARTBUSINESS FULL BUSINESS CASE REPORT OF: DIRECTOR OF RESOURCES
The SmartBusiness Project concerns the upgrade of the council’s enterprise resources planning systems.
Enterprise Resource Planning (ERP) systems integrate key business processes across finance, human resources, procurement and other areas. The approach standardises and streamlines procedures and approaches to the administration of a number of key business activities. The Council’s current ERP system, Oracle - 1 Business has been in operation since April 2005 and is now obsolete.
This report and supporting Full Business Case (FBC) discusses the future of the system and the requirement to implement an alternative to the current ERP that is now over 15 years old.
ERP systems have evolved rapidly over the last 10 years in response to changing technical confirmations and hardware approaches. New systems normally present a cost-effective way to replace older systems with greater standardisation and integration built in to the packages. It is envisaged that by replacing the current systems the Council will take full advantage of recent developments to make a step change to its operational effectiveness.
To date, the SmartBusiness Project has gone through extensive Discovery and Design phases which has resulted in a successful tender and evaluation process.
The Full Business Case (FBC) for the Policy and Resources Committee is attached as Appendix 1 to this report.
RECOMMENDATION/S
The Policy &Resources Committee are recommended to:
1. Approve the implementation and upgrade from our current unsupported version of Oracle (Release 11) to a new cloud solution.
2. Approve the budget and allocation of funding of £4.6 million (£2m capital/(£2.6m revenue) for transformation projects that deliver ongoing savings.
3. Approve the award of: A five-year contract with the option to extend for another two years to company named in the FBC via the Crown Commercial Service (CCS) Data and Application Solutions Framework, Agreement (RM3821) for New cloud platform licenses for 5-years (with the option to extend for a further 2: 5+2 years) period Implementation partner to implement the new platform for a total value detailed in the FBC.
4. Appoint members to a Member working Group to monitor project performance during Delivery phase. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The replacement of the Council’s existing ERP systems is a significant investment and will be essential to future operational effectiveness.
1.2The approach advocated will help rationalise multiple contracts with different suppliers and renewal dates.
2.0OTHER OPTIONS CONSIDERED
2.1Alternative options have been extensively explored through the discovery phase of the project and are contained within the FBC Appendix 1. This also includes an option of “Do Nothing” and maintaining the current approach
3.0BACKGROUND INFORMATION
3.1The full business case for this project is attached as Appendix A giving further information and detail to support this report.
3.2It is common for organisations, such as the Council, to manage their finances through an ERP System. This is through processes such as accounting, budget setting, forecasting, HR administration, business administration, income recording/reporting and procurement activity. These functions are currently conducted across many different, ageing systems through a mixed approach of ERP and stand-alone platforms with “patchwork” integration and manual intervention.
3.3The current ERP system Oracle 1Business was implemented in April 2005 and has not been updated since 2011.
3.4The SmartBusiness Project is a project to deliver a new ERP Platform for the Council and will align with the priorities of the Council and its partners. This has been informed by:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.