POLICY AND RESOURCES COMMITTEE Wednesday, 17 March 2021
REPORT TITLE: CONTRIBUTION TO THE CONSTRUCTION OF A 3G PITCH AT THE TRANMERE ROVERS TRAINING FACILITY AT SOLAR CAMPUS, LEASOWE REPORT OF: DIRECTOR OF RESOURCES
REPORT SUMMARY
Tranmere Rovers Football Club (the Club) has a long and successful history of working in partnership with the Council to deliver commissioned services on behalf of the Council and to deliver services that are not commissioned or paid for by the Council but support the delivery of beneficial outcomes to Wirral residents.
In September 2019 the Council entered into a Partnering Agreement with the Club that highlights our good historic relationships and our ambition to work together for the benefit of the residents of the Borough. The Club is a key anchor institution within Wirral and provides many functions that support the Council’s 2025 plan. In 2018, with the knowledge of a deficit of 3G football pitches across Wirral, the Club and the council talked about working together to align an initiative to jointly fund the construction of a 3G football pitch at the Solar Campus on Leasowe Road in Wallasey costing £799,779. The need for more 3G pitches in Wirral and the infrastructure of this site makes this location a prioritised option.
A 3G pitch is an all-weather (free draining) Third Generation synthetic surface consisting of a carpet like surface with artificial blades of grass supported by a layer of sand and an infill of rubber crumb. It is developed for intensive use as it is hard-wearing, durable, and resilient and enables more training and matches to be played on it as opposed to a traditional pitch.
The 2019/20 capital programme approved at Full Council on 4 March 2019 included a scheme and budget for the contribution to Tranmere Rovers Football Club for just under 50% of the construction of such a pitch at a maximum total of £375k. Planning consent was given for the construction of the pitch at the Planning Committee on 8 September 2020. This scheme was the continuation of Tranmere Rovers’ plan to relocate its training facilities from Ingleborough Road to the Solar Campus. Planning permission was approved subject to nine conditions that are currently being implemented via a working group of residents, officers and Members.
The grant will be funded from the Council’s existing capital programme, with the relevant conditions laid out in the grant agreement. As the revenue impact of the Capital Programme had already been included in the 2019/20 budget approved by Full Council in March 2019, and carried forward, there are no additional financial implications for the Council taxpayer as a result of awarding the grant.
RECOMMENDATION/S
The Policy & Resources Committee are recommended to:
1. Approve the request from Tranmere Rovers Football Club Limited for a maximum contribution of £375,000 toward the costs of construction of a 3G pitch at the Solar Campus in line with the relevant Community User conditions set out in the Appendix to this report
2. Agree that the Director of Law and Governance be authorised to draw up and finalise a legal agreement between the Council and Tranmere Rovers Football Club Limited to reflect the above arrangements. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1A state of the art facility will be available for residents to use under a Community User Agreement with the Club.
2.0OTHER OPTIONS CONSIDERED
2.1Not to approve the request for a contribution to the construction of a pitch from the Club. This would result in the Club not being able to construct the pitch and not provide any facilities to residents for its use.
2.2The Club could apply for Football Association funding to part-fund the construction of the pitch. However this is a time-consuming process and with conditions attached and the requirement to have the pitch available as soon as possible to meet the current shortage, outweighs the rationale for this.
3.0BACKGROUND INFORMATION
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Agreement of Capital Grant Included within the Capital Programme (3G Pitch)Report | 228 KB | DownloadRead as text |
Follow Policy and Resources Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2026 | New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... | Approved | Open |
| 22 Jul 2026 | Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... | Approved | Open |
| 22 Jul 2026 | Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... | Decided | Open |
| 22 Jul 2026 | Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... | Noted | Open |
| 22 Jul 2026 | Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.