West Kirby Flood Alleviation - Award of Contract for Construction Phase
ApprovedCommittee1 paper
Environment, Climate Emergency and Transport Committee approved this item on Monday 15 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved – That (1) the proposed procurement process and strategy for the construction of the West Kirby Flood Alleviation Scheme set out at paragraph 3.7 of this report be approved; and (2) authority be delegated to the Director of Neighbourhood Services to award the advanced Engineering Construction Contract and also the main construction phase Engineering Construction Contract .
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Reasons for recommendations
1.1Planning conditions for the West Kirby Flood Alleviation scheme require the main construction activity to be undertaken between April and September in any year in order to minimise disturbance to the natural environment of the Dee Estuary. Some other activities can be undertaken outside this period to facilitate the programme which allows for March to October working. Environment Agency grant funding conditions require construction phase spending commitments commencing by March 2022. The current scheme delivery programme requires the successful contractor to mobilise in February 2022.
1.2By delegating the authority to award an advanced Engineering and Construction Contract, for pre-ordered supplies, and the main Engineering and Construction Contract, for the construction activities, to the Director of Neighbourhood Services, sufficient time can be included in the programme to allow the successful contractor to mobilise in February 2022.
2.0OTHER OPTIONS CONSIDERED
2.1The next available Environment, Climate Emergency and Transport Committee is on 17 January 2022 and the contract award decision could be deferred until then. However, the effective date for any decision made at that Committee would not allow sufficient time to mobilise a contractor in February 2022, and the planning and funding conditions would not be met.
3.0BACKGROUND INFORMATION
3.1On 2 November 2021 the Council’s Strategic Applications Sub Committee, under application reference DPP4/20/01627, granted planning consent for proposed development consisting of the construction of a new linear secondary defence wall, set back along the edge of the South Parade promenade in West Kirby which will offer a high standard of protection to local residential and commercial properties.
3.2The Environment Agency has procured a Collaborative Delivery Framework for the delivery of its own and of Risk Management Authorities’ flood and coastal risk management schemes. Wirral Council was named as a Risk Management Authority during the Office of the Journal of the European Union advertising and procurement of the Collaborative Delivery Framework.
3.3The Collaborative Delivery Framework comprises two elements; Early Supplier Engagement and the Engineering and Construction Contract. The purpose of utilising Early Supplier Engagement is for the supplier to work with the Council and their designers to identify engineering and construction efficiencies which can reduce costs on the main Engineering and Construction Contract
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.