West Kirby Flood Alleviation - Award of Contract for Construction Phase

Approved Committee 1 paper

Environment, Climate Emergency and Transport Committee approved this item on Monday 15 November 2021. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

Resolved – That (1) the proposed procurement process and strategy for the construction of the West Kirby Flood Alleviation Scheme set out at paragraph 3.7 of this report be approved; and (2) authority be delegated to the Director of Neighbourhood Services to award the advanced Engineering Construction Contract and also the main construction phase Engineering Construction Contract .
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Environment, Climate Emergency and Transport Committee

Reasons for recommendations

1.1Planning conditions for the West Kirby Flood Alleviation scheme require the main construction activity to be undertaken between April and September in any year in order to minimise disturbance to the natural environment of the Dee Estuary. Some other activities can be undertaken outside this period to facilitate the programme which allows for March to October working. Environment Agency grant funding conditions require construction phase spending commitments commencing by March 2022. The current scheme delivery programme requires the successful contractor to mobilise in February 2022.

1.2By delegating the authority to award an advanced Engineering and Construction Contract, for pre-ordered supplies, and the main Engineering and Construction Contract, for the construction activities, to the Director of Neighbourhood Services, sufficient time can be included in the programme to allow the successful contractor to mobilise in February 2022.

2.0OTHER OPTIONS CONSIDERED

2.1The next available Environment, Climate Emergency and Transport Committee is on 17 January 2022 and the contract award decision could be deferred until then. However, the effective date for any decision made at that Committee would not allow sufficient time to mobilise a contractor in February 2022, and the planning and funding conditions would not be met.

3.0BACKGROUND INFORMATION

3.1On 2 November 2021 the Council’s Strategic Applications Sub Committee, under application reference DPP4/20/01627, granted planning consent for proposed development consisting of the construction of a new linear secondary defence wall, set back along the edge of the South Parade promenade in West Kirby which will offer a high standard of protection to local residential and commercial properties.

3.2The Environment Agency has procured a Collaborative Delivery Framework for the delivery of its own and of Risk Management Authorities’ flood and coastal risk management schemes. Wirral Council was named as a Risk Management Authority during the Office of the Journal of the European Union advertising and procurement of the Collaborative Delivery Framework.

3.3The Collaborative Delivery Framework comprises two elements; Early Supplier Engagement and the Engineering and Construction Contract. The purpose of utilising Early Supplier Engagement is for the supplier to work with the Council and their designers to identify engineering and construction efficiencies which can reduce costs on the main Engineering and Construction Contract

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
West Kirby Flood Alleviation: Award of Contract for Construction PhaseReport 107 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
EG
Councillor Elizabeth GreyChair, present
HC
Councillor Helen CollinsonCommittee Member, present
SF
Councillor Steve FoulkesCommittee Member, present
CO
Councillor Clare O'HaganCommittee Member, present
IW
Councillor Irene WilliamsCommittee Member, present
BB
Councillor Bruce BerryCommittee Member, present
MC
Councillor Michael CollinsCommittee Member, present
SR
Councillor Simon R MountneySpokesperson, present
LR
Councillor Les RowlandsCommittee Member, present
CC
Councillor Christopher CookeVice-Chair, present
AB
Councillor Allan BrameSpokesperson, present
MJ
Mike JonesCommittee Officer, in attendance

All 20 on the meeting page

On this subject at Wirral

Search all
  1. West Kirby Flood Alleviation - Award of Contract for Construction PhaseThis decision
  2. APP/26/00261 - The Links, 100 - 102 Meols Drive, West Kirby, Wirral, CH48 5DBApproved
  3. West kirby marine lake managementApproved
  4. APP-24-00816 - WEST KIRBY GRAMMAR SCHOOL FOR GIRLS, GRAHAM ROAD, WEST KIRBY, WIRRAL, CH48 5DP - Proposed (isolated) demolition to enable the erection of a Sports Hall, 6th Form Centre with dining facilities and associated re-modelling works to facade, means of access, parking and landscapingApproved
  5. APP/23/00551: The Grange, Grange Road, West Kirby, Wirral, CH48 4EE Demolition of house and out buildings to provide 12 apartments together with associated parking, access and landscaping and works including the relocation of the substation. (Amended Description)Approved
  6. APP/23/00551; The Grange, Grange Road, West Kirby, Wirral, CH48 4EE, Demolition of house and outbuildings to provide 12 apartments together with associated parking, access and landscaping and works including the relocation of the substation.Deferred

More from Wirral Environment, Climate Emergency and Transport Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 2026-27 budget monitoring report quarter 1Resolved – That the Environment, Climate Emergency and Transport Committee notes: 1. the forecast revenue position fo... Decided Open
8 Jul 2026 Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep... Agreed Open
8 Jul 2026 Environment and Climate Emergency Action Plan Progress Report 2025-26It was agreed that the two agenda items, “Carbon Budget Performance Report 2025-26” and “Environment and Climate Emer... Agreed Open
8 Jul 2026 Environment, climate emergency and transport performance reportResolved – That the Environment, Climate Emergency and Transport Committee notes the content of the report and highli... Decided Open
8 Jul 2026 Work ProgrammeIt was agreed that items requested on weed treatment provisions would be a part of the Hot House briefings. Briefing ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies