Wirral Borough Council

Wallasey Embankment Toe Reinforcement

Decided Committee 1 paper

Environment, Climate Emergency and Transport Committee decided this item on Monday 20 June 2022. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Resolved – That (1) the Environment Agency’s Grant in Aid Award of £1,358,000 be accepted. (2) a contract be awarded to Jones Bros Ruthin (Civil Engineering) Co Ltd with a value of £721,277.52 for the delivery of the Scheme.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Environment, Climate Emergency and Transport Committee

ENVIRONMENT, CLIMATE EMERGENCY AND TRANSPORT COMMITTEE Monday, 20 June 2022

REPORT TITLE: WALLASEY EMBANKMENT TOE REINFORCEMENT REPORT OF: DIRECTOR OF NEIGHBOURHOOD SERVICES

REPORT SUMMARY The Wirral Coastal Strategy identified that ongoing erosion at the base of Wallasey Embankment required intervention in the short term. If erosion continues the embankment, which protects large areas of Meols, Moreton and Leasowe from flooding from the sea, would be weakened with an increased risk of failure. An Outline Business Case to reinforce the toe of the embankment has been approved and grant aid secured. A procurement exercise has also been completed to allow for construction of the reinforcement works with a programme that complies with Planning Consent conditions and Marine Licence conditions.

Flood Risk and Coastal Erosion Risk Management aligns with both the Sustainable Environment and Safe and Pleasant Communities themes of the Wirral Plan 2021-26.

The recommendations in this report affect the following wards:  Hoylake and Meols  Moreton West and Saughall Massie  Leasowe and Moreton East

The recommendations in this report constitute a key decision because of expenditure greater than £500,000.

RECOMMENDATION/S

The Environment, Climate Emergency and Transport Committee is requested to:

1. Accept the Environment Agency’s Grant in Aid Award of £1,358,000 2. Award a contract to Jones Bros Ruthin (Civil Engineering) Co Ltd with a value of £721,277.52 for the delivery of the Wallasey Embankment Toe Reinforcement Scheme. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1The Shoreline Management Plan for the Wirral coast was approved by the Cabinet in September 2010. The Shoreline Management Plan identifies a Hold the Line Policy for Wallasey Embankment until 2110. The Wirral Coastal Strategy, approved at Cabinet in October 2013, identified that a Hold the Line Policy could be delivered addressing ongoing erosion at the base of the embankment in the short term.

1.2An Outline Business Case was developed in 2021 and determined the preferred option for reinforcing the base of the embankment was by extending existing rock protection by 1100m. The Outline Business Case, which provides grant aid of £1,358,000 was approved by the Environment Agency’s Area Flood and Coastal Risk Manager in March 2022.

1.3Acceptance of the grant award from the Environment Agency provides the budget for the delivery of the scheme in entirety.

1.4Prior to development of the Outline Business Case applications were made for Planning Consent and a Marine Licence. A Marine Licence is required for all construction works that take place below Mean High Water Spring Tides (MHWST) and is provided by the Marine Management Organisation (MMO) following consultation. Planning and licence conditions only allow for construction between the months May to August.

1.5Following approval of the Outline Business Case in March 2022 tender documentation was developed in order to undertake a procurement exercise that once concluded, would allow for construction within the period set by the planning and marine licence conditions.

1.6Award of the contract to Jones Bros Ruthin (Civil Engineering) Co Ltd of the value £721,277.52 allows for delivery of the scheme in this financial year and in accordance with conditions that have been set to protect the natural environment.

2.0OTHER OPTIONS CONSIDERED

2.1The scheme to protect the base of Wallasey Embankment extends the existing rock armour protection in the vicinity of Leasowe Lighthouse a further 1100m eastwards. The rock armour protection was determined as the preferred option following consideration in the Outline Business Case which included:

2.2Do Nothing This option was assessed as the baseline for economic assessment and rejected as it did not meet Flood Defence Grant in Aid (FDGiA) Investment Objectives or any Critical Success Factors (CSF).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wallasey Embankment Toe ReinforcementReport 418 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 20 attended
EG
Councillor Elizabeth GreyChair, present
SF
Councillor Steve FoulkesCommittee Member, present
SP
Councillor Sue PercyCommittee Member, present
TS
Councillor Tony SmithCommittee Member, present
PC
Councillor Paul ConnollyCommittee Member, apologies, sent representative
AG
Councillor Andrew GardnerSpokesperson, present
LF
Councillor Leah FraserCommittee Member, present
VW
Councillor Vida WilsonCommittee Member, present
HG
Councillor Harry GormanVice-Chair, present
NG
Councillor Naomi GrahamCommittee Member, present
OO
Councillor Orod OsanlouCommittee Member, present
KA
Ken AbrahamOfficer, expected

All 20 on the meeting page

More from Wirral Environment, Climate Emergency and Transport Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 2026-27 budget monitoring report quarter 1Resolved – That the Environment, Climate Emergency and Transport Committee notes: 1. the forecast revenue position fo... Decided Open
8 Jul 2026 Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep... Agreed Open
8 Jul 2026 Environment and Climate Emergency Action Plan Progress Report 2025-26It was agreed that the two agenda items, “Carbon Budget Performance Report 2025-26” and “Environment and Climate Emer... Agreed Open
8 Jul 2026 Environment, climate emergency and transport performance reportResolved – That the Environment, Climate Emergency and Transport Committee notes the content of the report and highli... Decided Open
8 Jul 2026 Work ProgrammeIt was agreed that items requested on weed treatment provisions would be a part of the Hot House briefings. Briefing ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies