Resolved
Resolved – That the valuation basis be approved and authorisation be given to the Fund Actuary to certify the final valuation report containing employers’ contributions payable for the period 1 April 2023 to 31 March 2026.
Pensions Committee approved this item on Wednesday 14 December 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the valuation basis be approved and authorisation be given to the Fund Actuary to certify the final valuation report containing employers’ contributions payable for the period 1 April 2023 to 31 March 2026.
That the Pensions Committee be recommended to approve the valuation basis and authorise the Fund Actuary to certify the final valuation report containing employers’ contributions payable for the period 1 April 2023 to 31 March 2026. SUPPORTING INFORMATION
1.1There is a requirement for Members of the Pensions Committee to be kept up to date with legislative developments as part of their decision-making role.
2.0OTHER OPTIONS CONSIDERED
2.1Not relevant for this report as the report is being shared for information only and it is good practice for the Committee to be aware of the Fund’s deliberations.
3.0BACKGROUND INFORMATION
3.1The Local Government Pension Scheme Regulations 2013 provide the statutory framework for the valuation process. The regulations require an actuarial assessment of the Fund’s assets against the current value of the pension liabilities, with a corresponding funding level to be declared every three years.
3.2In order to undertake the valuation, the Actuary must have regard to the draft funding assumptions which went out for consultation with employers from 31st October to 2nd December 2022.
3.3As part of the consultation employers were asked to consider the affordability versus sustainability of future contribution rates when deciding on the level of contributions payable when reviewing budgets. This is due to the continued uncertainty in relation to the economic and market outlook as well as inflation.
3.4The level of employer contributions and the parameters set out in the draft Funding Strategy Statement (FSS) aim to achieve sustainability when taken in conjunction with the investment strategy. Whilst the Fund is responsible for setting the strategy to achieve this, employers also have a responsibility to consider the sustainability of contributions in the longer term when making decisions on the level of contributions at each valuation.
Valuation Results
3.3The final actuarial outcome will be certified following finalisation of the Funding Strategy Statement, however, preliminary whole Fund results (based on the proposed assumptions in the draft FSS) are set out below, alongside the results from 2019 valuation for comparison purposes:
2019 2022 ASSETS £8,883m £11,001m
LIABILITIES £8,793m £10,362m
SURPLUS £90m £639m
FUNDING LEVEL 101% 106%
AVERAGE EMPLOYER FUTURE SERVICE (PRIMARY) CONTRIBUTION 16.8% of pay 18.5% of pay RATE (% OF PAY)
3.4The emerging preliminary whole fund results present a funding level of 106% with an associated surplus of £639m and an average employer future service cost of 18.5% of pay. The position presented follows in-depth discussions between the Fund Actuary (Mercer), officers and constituent employers in relation to the core financial and demographic assumptions.
3.5These results will be subject to change as the valuation is completed for each employer, in particular, any changes to the assumption for short term pay (the results above assume an average pay award of 4% p.a. for the next 3 years) and the impact of some weaker covenant employers being assessed on the medium or lower risk bucket assumptions. The results will be disclosed within the 2022 valuation report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON 2022 ACTUARIAL VALUATIONReport | 365 KB | DownloadRead as text |
Follow Pensions Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | External audit plan merseyside pension fund 2025-26Resolved – That the external audit plan for 2025/26, as prepared by Grant Thornton, be noted. | Noted | Open |
| 22 Jun 2026 | Local government pension scheme (lgps) access for councillors & mayorsResolved – That the report be noted along with the additional resource requirements in extending access to the Scheme... | Noted | Open |
| 22 Jun 2026 | Merseyside pension fund budget out-turn 2025/26 and final budget 2026/27Resolved - That 1) the out-turn for 2025/26 be noted; and 2) the finalised budget for 2026/27 be endorsed. | Noted | Open |
| 22 Jun 2026 | Update on fit for the future: local government pension scheme (lgps) regulations & guidance, and northern lgpsResolved - 1) The outcome of the consultation and the progress with founding NLGPS be noted and the Director of Pensi... | Noted | Open |
| 22 Jun 2026 | Pensions committee: revised terms of referenceResolved – That: 1. The proposed changes to its terms of reference and to the Scheme of Delegation of Functions be ap... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.