APP/22/00334: Cammell Laird, Campbeltown Road, Birkenhead, Wirral, CH41 9BP, Construction of a building for employment purposes Class E(G)IIII, B2 and B8, along with a gatehouse associated infrastructure including: service yard, car parking, drainage and hard and soft landscaping

Approved Planning 1 paper

Planning Committee approved this item on Thursday 8 June 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Resolved (unanimously) – that the application be approved subject to the following conditions: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 2. Except where modified by the conditions attached to this planning permission, the development hereby approved relates to and shall be carried out in accordance with the following approved plans: P21-2391_01-A Detailed Soft Landscaping Proposals P21-2391_02-A Detailed Soft Landscaping Proposals Proposed Boundary Treatments Site Plan P403 Rev. D Proposed Elevations Dwg no. P200 rev. D Gatehouse Information Dwg no. P110 rev. B Proposed Roof Plan Dwg no. P101 rev. B Proposed Floor Plan Dwg no. P100 rev. C Proposed Site Plan Dwg no. P402 rev. E Proposed Surface Treatments Site Plan Dwg no. P404 rev. C Proposed External Lighting Layout Dwg No. 2390/E01 rev. P1 Site Location Plan Dwg no. P401 rev. B 3. Notwithstanding any description of materials in the application, no above ground construction works shall take place until samples and / or full specification of materials to be used externally on the building(s) have been submitted to and approved in writing by the Local Planning Authority. Such details shall include the material type, colour and texture. The development shall be carried out only in accordance with the agreed schedule of materials and method of construction. 4. Prior to commencement of development, a Construction Environmental Management Plan (CEMP) document shall be submitted to and approved in writing by the Local Planning Authority in consultation with Natural England. The CEMP should address and propose measures to minimise the main construction effects of the development and, amongst other things, should include details of ecological mitigation, pollution prevention and soil resource management. The CEMP would normally be expected to include the agreed method statements to mitigate or avoid adverse environmental impacts. The CEMP should include, but not be limited to, the following: · pollution prevention measures as set out in paragraph 6.3.3 of the shadow HRA report (Information for a Habitats Regulations Assessment, RPS, ECO02904 March 2023, Rev E, Final); · details of construction lighting, designed to avoid light spillage into the adjacent Liverpool Bay SPA; · details of measures to reduce significant noise effects to waterbirds during construction. These details should include the location and specification of acoustic fencing to be installed upon site boundary; and · details of the Ecological Clerk of Works ( ECoW ) that will be employed onsite throughout construction period to assist with avoidance of visual disturbance effects to waterbirds within the adjacent Liverpool Bay SPA, as set out in paragraph 6.4.9 of the shadow HRA (Information for a Habitats Regulations Assessment, RPS, ECO02904 March 2023, Rev E, Final). 5. A scheme of noise control for any plants and equipment to be installed ... view the full minutes text for item 7.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Planning Committee

Planning Committee 8th June 2023

Reference: Area Team: Case Officer: Ward: APP/22/00334 DM [name removed]

Location: Camell Laird, Campbeltown Road, Birkenhead, Wirral, CH41 9BP Construction of a building for employment purposes Class E(G)IIII, B2 and Proposal: B8, along with a gatehouse associated infrastructure including: service yard, car parking, drainage and hard and soft landscaping Applicant: Peel L & P & Tungsten Properties Agent: Eleanor Overton (Pegasus Group)

Qualifying Petition No

Site Plan:

© Crown copyright and database rights 2022 Ordnance Survey 100019803 You are not permitted to copy, sub-licence, distribute or sell any of this data to third parties in any form.

Development Plan Primarily Industrial Area designation: Employment Development Site Coastal Zone Waste Disposal Site

Planning History: APP/16/00601 – Temporary warehouse, offices and contractor storage facilities. APPROVED APP/15/00592 - Full planning application for a proposed crew transfer and storage facility. APPROVED APP/12/00729 – Temporary planning permission for three years for a temporary warehouse to be used for the dry storage of high value equipment and components to be used for the construction of Gwynt y Mar Offshore Wind Farm. APPROVED APP/12/00030 – Temporary planning permission for three years to erect amenities to facilitate the coordination of construction of parts of the Gwynt y More Offshore Wind Farm. APPROVED

Reason for listing on Strategic Applications Sub Committee Agenda:

Large scale development of more than 10,000 square metres.

Summary Of Representations and Consultations Received:

1. Ward Member None. Comments 2. Summary of REPRESENTATIONS Representations In response to the public consultation exercise a total of 2 responses were received raising the following comments:

- Overdevelopment - Increased traffic with pressures on local roads, junctions and prejudicial to highway safety

In addition, objections from Eversheds on behalf of neighbouring operator Essar Oil Limited as well as Stanlow Terminals Limited (Essar) were received on 15 April 2022, 29 April 2022, 23rd June 2022 and 13th February 2023.

The first objection states that Essar operates Tranmere Oil Terminal which is considered Critical National Infrastructure along with the Stanlow Manufacturing Complex. The Tranmere Terminal receives vessels carrying up to 170,000 tonnes of crude oil and up to 9 million tonnes of crude oil a year which is processed at Stanlow. The site is designated as a top tier site under the Control of Major Accident Hazards Regulations 2015 (“COMAH”) because of the quantity of dangerous substances present. It has an existing Hazardous Substance Consent (HSC) issued by Wirral Council in 2017 in connection with the maximum quantity of flammable liquids, petroleum products and alternative fuels present.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APP/22/00334: Cammell Laird, Campbeltown Road, Birkenhead, Wirral, CH41 9BP, Construction of a building for employment purposes Class E(G)IIII, B2 and B8, along with a gatehouse associated infrastructure including: service yard, car parking, drainage and hard and soft landscapingReport 960 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 16 attended
SK
Councillor Stuart KellyChair, present
SF
Councillor Steve FoulkesVice-Chair, present
HG
Councillor Harry GormanSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, apologies, sent representative
CB
Councillor Colin BaldwinCommittee Member, present
MB
Councillor Max BoothCommittee Member, apologies, sent representative
BK
Councillor Brian KennyCommittee Member, present
JS
Councillor James Stewart LaingCommittee Member, present
GM
Councillor Grahame McManusCommittee Member, present
SP
Councillor Sue Powell-WildeCommittee Member, present
AG
Councillor Andrew GardnerCommittee Member, present as substitute
SR
Councillor Simon R MountneyCommittee Member, present as substitute

All 16 on the meeting page

On this subject at Wirral

Search all
  1. APP/22/00334: Cammell Laird, Campbeltown Road, Birkenhead, Wirral, CH41 9BP, Construction of a building for employment purposes Class E(G)IIII, B2 and B8, along with a gatehouse associated infrastructure including: service yard, car parking, drainage and hard and soft landscapingThis decision
  2. APP/19/01479 - Lairds Sports Club 93 & Cammell Laird 1907 FC, ST PETERS ROAD, ROCK FERRY, CH42 1PY, Construction of new single-storey clubhouse (to south-eastern corner of the site) together with a new 25no. space car park (to north-west of site) and associated worksApproved
  3. APP/15/00952: Cammell Laird, CAMPBELTOWN ROAD, TRANMERE, CH41 9BP - Full planning application for a proposed crew transfer and storage facility.Approved

More from Wirral Planning Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 MINUTESResolved – That the minutes of the Planning Committee held on 13 August 2026 be approved as a correct record. The Cha... Approved Open
10 Sep 2026 ADV/26/00958 - Corner Of Duke Street and Beckwith Street, Birkenhead, Wirral, CH41 8BBResolved (unanimously) – That the Assistant Director - Chief Planner be authorised to refuse the application, due to ... Refused Open
10 Sep 2026 APPH/26/01027 - 5 Woodcote Bank, Higher Bebington, Birkenhead, Wirral, CH42 4NLResolved – That the Planning Committee was content for the application to be withdrawn from the agenda and returned t... Decided Open
10 Sep 2026 APP/26/00691 - Lighthouse Inn, 228 Wallasey Village, Wallasey, Wirral, CH45 3LPResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open
10 Sep 2026 APP/26/00814 - Grove House Hotel, 45 Grove Road, Wallasey Village, WirralResolved (unanimously) – That for the reasons set out in the report, the Assistant Director - Chief Planner be author... Approved Open