Resolved – That, under section 100 (A) (4) of the Local Government Act 1972, the public be excluded from the meeting during consideration of the following item of business on the grounds it involves the likely disclosure of exempt information as defined by paragraph 3 of Part I of Schedule 12A (as amended) to that Act. The Public Interest test has been applied and favours exclusion. The Assistant Director of Special Projects introduced the report (of the Director of Finance) which set out the proposed Community Asset Transfer of Woodchurch Leisure Centre to Woodchurch Wellbeing. Following a debate on the matter, it was – Resolved (unanimously) – That (1) Committee notes and concurs with the key objectives set out in the business plan. (2) Committee is minded to support the Community Asset Transfer of Woodchurch Leisure Centre to Woodchurch Wellbeing with capital funding up to a maximum of £330,000 and to that effect will issue a letter of intent accordingly. (3) Such a letter is subject to: a. Receipt of additional grant funding by Woodchurch Wellbeing to match Council capital contribution of £330k plus 20% revenue costs by Friday 27 October 2023. b. Receipt of a revised business plan by Friday 27 October 2023 for consideration by Policy & Resources Committee on 8 November 2023.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
POLICY AND RESOURCES COMMITTEE WEDNESDAY, 12 JULY 2023
REPORT TITLE: COMMUNITY ASSET TRANSFER WOODCHURCH LEISURE CENTRE REPORT OF: DIRECTOR OF FINANCE
REPORT SUMMARY
The Tourism, Communities, Culture and Leisure Committee at its meeting on 22 June 2023, resolved that the Director of Finance should bring a report on the community asset transfer of Woodchurch Leisure Centre to Policy and Resources Committee, on 12 July 2023, for decision.
After the committee meeting and following discussions with both interested parties, Helen Diamond Swimming Limited withdrew their proposal due to their commitment to another venue and other projects.
This report reviews the business plan and recommends a transfer to Woodchurch Wellbeing, although notes that this carries some significant risks due to the underlying condition of the building and volatility around energy prices.
This report meets the following priorities in the Wirral Plan 2021-26
- Safe, vibrant communities where people want to live and raise their families - A prosperous inclusive economy where local people can get good jobs and achieve their aspirations
This matter has the potential to affect all wards.
This is a Key Decision
The Business Plan referred to in this report were submitted confidentially, for commercial reasons. Therefore, Appendix 1 of this report is exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972.
RECOMMENDATION/S
The Policy and Resources Committee is recommended to authorise the Director of Finance to
(1) transfer Woodchurch Leisure Centre to Woodchurch Wellbeing, subject to them achieving additional grant funding, on the basis that it provides the most cost-effective option for the Council whilst continuing to provide an asset that will benefit the community in an area where there is an identified deficiency in provision.
(2) to negotiate and agree Heads of Terms for the transfer, with a target date for completion and transfer of October 2023.
(3) make available a maximum capital grant of £330,000 by way of a grant agreement with Woodchurch Wellbeing to support the transfer and
(4) provide business planning support to Woodchurch Wellbeing to ensure that the risks identified in the business plan are minimised. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To enable a decision to be made on the community asset transfer of Woodchurch Leisure Centre.
2.0OTHER OPTIONS CONSIDERED
2.1The alternative option to asset transfer is the demolition of the asset followed by a repurposing of the site for another use to support Local Plan priorities. This could be playing pitches for various sports and Biodiversity Net Gain. This would support the Local Plan which has identified a deficit of playing pitches that needs to be addressed.
2.2The costs of undertaking the demolition of the leisure centre were originally estimated to be £330k – consistent with the amount that could otherwise be offered as a grant for Community Asset Transfer.
2.3The costs of demolition have not yet been determined through a formal procurement process as the costs associated with the design required would be significant and would represent abortive costs if the transfer was to go ahead.
2.4Given the significant increases in inflation that have been experienced over the past year, it is highly likely that the costs of demolition will have increased beyond that originally projected.
2.5It is anticipated that it would take six months from the time of the decision to procure a contractor and for them to start on site. Holding costs for the site will continue to be incurred for this period, it is estimated that total holding costs of £185k would be incurred for 23/24 for this option.
3.0BACKGROUND INFORMATION
3.1Woodchurch Leisure Centre was closed during Covid and then permanently closed as part of the 2022/23 Budget process due to very high operational costs and deficits. Members decided to put this asset into the community asset transfer process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.