2023/24 CAPITAL PROGRAMME MONITORING FOR QUARTER ONE (THE PERIOD TO 30 JUN 2023)

Approved Committee 2 papers

Council approved this item on Monday 9 October 2023. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

Resolved (unanimously) – That (1) the revised Capital Programme of £87 million for 2023/24, including the virements of budget referred to in Appendix C of this report be approved. (2) t the additional funding for the schemes referred to in section 3.7 be approved, with proposed extra funding from a variety of sources, new borrowing required from the Council, revenue contributions and the repurposing of previously agreed Council borrowing.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Council

Recommendations

The Policy and Resources Committee is requested to recommend to Council the approval of:

1 the revised Capital Programme of £87 million for 2023/24, including the virements of budget referred to in Appendix C of this report.

2 additional funding for the schemes referred to in section 3.7 in this report. The proposed extra funding is from a variety of sources, new borrowing required from the Council, revenue contributions and the repurposing of previously agreed Council borrowing. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.

2.0OTHER OPTIONS CONSIDERED

2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.

3.0BACKGROUND INFORMATION

3.1Capital Programme 2023/24 Position by Directorate

Table 1: Wirral Council 2023/24 Forecast Position Budget Forecast 1 April 23 Q1 Variance Variance Programme £m £m £m % Adult Care & Health 3.884 2.786 -1.098 -28% Children, Families & Education 16.929 9.310 -7.619 -45% Neighbourhoods 29.143 23.015 -6.128 -21% Regeneration & Place 116.681 46.137 -70.544 -60% Resources 11.421 5.703 -5.718 -50% Total 178.058 86.951 -91.107 -51%

Capital Programme 2023/24 Position by Committee

Table 2: Wirral Council 2023/24 Forecast Position Budget 1 Q1 April 23 Forecast Variance Variance Programme £m £m £m % Adult Social Care & Health 3.884 2.786 -1.098 -28% Children, Young People & Education 16.929 9.310 -7.619 -45% Economy, Regneration & Housing 102.351 39.462 -62.889 -61% Environment, Climate Emergency & Transport 31.008 22.242 -8.766 -28% Policy & Resoures 16.541 8.249 -8.292 -50% Tourism, Communities, Culture & Leisure 7.345 4.902 -2.443 -33% Total 178.058 86.951 -91.107 -51% 3.1.1 Tables 1 and 2 provide an update on the 2023/24 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original programme was agreed at the end of February 2023 and subsequently revised via the 2022/23 Outturn report. These include the re-profiling of expenditure into and out of the 2022/23 financial year, inclusion of additional grant funded schemes and variations to spend forecasts. There are three new capital funding requests, including the repurposing of previously approved budget, see 3.7 of this report. Within Quarter 1 there has been a net decrease of £91.11 million of budget forecast as required in 2023/24. Appendix A of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.

3.1.2 As noted above, the main movements in this year’s programme so far are in respect of deferrals of budget into future years along with the inclusion of new funding and schemes into the programme.

3.1.3 It is anticipated that further reductions and/or deferrals of budget will be made in future quarters. Such deferrals reduce the borrowing costs incurred during 2023/24 and also delays the resultant Minimum Revenue Provision (MRP) charges into future years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2023/24 CAPITAL PROGRAMME MONITORING FOR QUARTER ONE (THE PERIOD TO 30 JUN 2023)Report 565 KB DownloadRead as text
PDF
2023/24 CAPITAL PROGRAMME MONITORING FOR QUARTER ONE (THE PERIOD TO 30 JUN 2023)Report 97 KB Download

At this meeting

Whole meeting

Who was there

60 of 68 attended
JW
Councillor Jerry WilliamsMayor, present
AA
Councillor Ann AinsworthCommittee Member, present
CB
Councillor Colin BaldwinCommittee Member, present
PB
Councillor Paula BasnettCommittee Member, present
GB
Councillor Gary BennettCommittee Member, present
SB
Councillor Stephen BennettCommittee Member, present
JB
Councillor Jo BirdCommittee Member, present
MB
Councillor Max BoothCommittee Member, present
AB
Councillor Allan BrameCommittee Member, present
HC
Councillor Helen CameronCommittee Member, present
CC
Councillor Chris CarubiaCommittee Member, present
PC
Councillor Pat ClearyCommittee Member, present

All 68 on the meeting page

On this subject at Wirral

Search all
  1. 2023/24 CAPITAL PROGRAMME MONITORING FOR QUARTER ONE (THE PERIOD TO 30 JUN 2023)This decision
  2. 2026-33 Capital ProgrammeApproved
  3. 2026-33 Capital ProgrammeApproved
  4. 2025-32 Capital ProgrammeApproved
  5. Capital programme 2024-29Approved
  6. Capital programme 2024-29Approved

More from Wirral Council

All decisions
MeetingDecisionOutcome
20 Jul 2026 MINUTESResolved – That the minutes of the meetings held on 13 May 2026 and 20 May 2026 be approved as a correct record. Approved Open
20 Jul 2026 2025-26 Capital OutturnResolved – That 1. the virements of budget referred to in Appendix F of the report be approved; and 2. the bids in Ap... Approved Open
20 Jul 2026 Revisions to the ConstitutionResolved – That the amendments to the Constitution, as detailed in sections 3.2 to 3.7 of the report, be approved. Approved Open
20 Jul 2026 Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a... Approved Open
20 Jul 2026 Annual Report of the Audit and Risk Management CommitteeResolved – That the ARMC Annual Report for 2025-26 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies