Resolved
That this report, which provides assurance on the delivery and oversight of the Health and Care Pan programmes, be noted.
Wirral Place Based Partnership Board noted this item on Thursday 20 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That this report, which provides assurance on the delivery and oversight of the Health and Care Pan programmes, be noted.
Title Wirral Health and Care Plan Programme Delivery Dashboard Authors Julian Eyre: Programme Director, Wirral Improvement team Report for Wirral Place Based Partnership Board Date of Meeting 20th February 2025
Report Purpose and Recommendations The purpose of this report is to present to Place based partners the performance dashboard for the programmes within the Wirral Place Health and Care Plan. The dashboard structure has been developed and agreed with the Strategic Transformation Group (STG), and the live dashboard is reviewed by the STG monthly, where programme Senior Responsible Officers (SRO’s) attend.
The report aims to provide the Board with information and assurance on the progress of the Programmes associated with the Wirral Health and Care plan 2024-25.
It is recommended that the Wirral Place Based Partnership Board note this report which provides assurance on the delivery and oversight of the Health and Care plan programmes.
Key Risks This report relates to the Place Delivery Assurance Framework (PDAF) and the associated high-level risks, namely: • Service Delivery • Children and Young People • Collaboration • Workforce • Finance • Community Wealth Building
The Programme Delivery Dashboard presented in this paper forms part of the assurance framework that measures the strength and effectiveness of the controls that have been put in place to mitigate the risks to Place objectives.
Governance journey Date Forum Report Title Purpose/Decision 3rd February 2025 Strategy and Health and Care Plan To Update STG on Transformation progress update progress on Health Group members and Care plan
1 Narrative 1.1 Background 1.1.1 The Wirral Place Health and Care Plan 2024-25 was endorsed by the Wirral Place Based Partnership Board (WPBPB) on 25th July 2024. A programme delivery dashboard has been developed providing oversight of the whole programme portfolio within the plan. In line with the overall review of the Health and Care Plan, the programme delivery structure, oversight and outcomes measurement will be reviewed in order to ensure that Wirral partners can be assured of progress. 1.1.2 For the avoidance of doubt, the programmes that constitute the portfolio within the Health and Care Plan are summarised in the figure below:
Wirral Place Programmes
Population Health including Health Inequalities prevention Core 20 Plus 5
Neighbourhood Guiding Model Programmes
Use of Resources
At Scale, Primary and Place Unscheduled Children and Mental All Age Delivery Community Supported Care Young People Health Disability Care Programmes Programmes
Place Place Digital Place Estates and Place Medicines Enabling Workforce maturity Sustainability Optimisation Programmes
1.1.3 As part of the refresh of the Wirral Health & Care Plan, and in view of both local and national strategic developments, programme Senior Responsible Officers and programme leads are supporting a series of STG workshops to share programme content and progress, with the aim of identifying collaboration and joint strategic planning opportunities.
1.1.4 The overall delivery Red Amber Green (RAG) rating for the Health and Care plan delivery in December was Amber, with two programmes in the portfolio reporting Red, six reporting Amber and five reporting Green. The current programme status is summarised in the table below:
Programme Current Previous Reason for score/ change RAG RAG Guiding Programmes Neighbourhoods Population Health/ Core20+5 Use of Resources Delivery Programmes Children and Young People Improvement in delivery against programme objectives All Age Disability Mental Health Difficulties in the identification of housing for discharge has increased programme risk status Primary and Community Care Urgent and Emergency Care Advised to improve RAG by C&M as only financial benefit status now red Enabling Programmes Digital Maturity
Estates and Sustainability Medicines Optimisation Workforce Place Supported Delivery Programmes at Scale Elective Care Cancer Diagnostics Maternity
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Wirral Health and Care Plan DashboardAppendix 1 | 17 MB | Download |
PDF |
Wirral Health and Care Plan Programme Delivery DashboardReport | 154 KB | DownloadRead as text |
Follow Wirral Place Based Partnership Board at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Mar 2026 | Minutes of Previous MeetingResolved – That the minutes of the meeting held on 22 January 2026 be agreed. | Agreed | Open |
| 26 Mar 2026 | Quality and Performance ReportResolved – That the report be noted. | Noted | Open |
| 26 Mar 2026 | Place Finance Report incorporating Pooled Fund UpdateResolved – That 1. The forecast reported position for the Wirral System and Pooled Fund as at Month 10 2025/26 be not... | Noted | Open |
| 26 Mar 2026 | Unscheduled Care Improvement Programme UpdateResolved – That the report be noted. | Noted | Open |
| 26 Mar 2026 | Wirral Provider Alliance UpdateResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.