Resolved – That 1. the procurement process, utilising the Northern LGPS Framework Lot 2 – UK Property Advisory Mandate, as outlined within the report be endorsed; and 2. the appointment of CBRE Limited as strategic property advisors to the Merseyside Pension Fund be approved.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
REPORT TITLE: APPOINTMENT OF STRATEGIC PROPERTY ADVISOR
REPORT OF: DIRECTOR OF PENSIONS
REPORT SUMMARY
This report seeks approval from Pensions Committee for the appointment of Strategic Property Advisors to Merseyside Pension Fund.
This is a Key Decision.
Appendix 1 to this report contains exempt information. This is by virtue of paragraph(s) 3 of Part 1 of Schedule 12A of Local Government Act 1972 i.e. information relating to the financial or business affairs of any particular person (including the authority holding that information).
The report supports the Council Plan: Wirral Working Together 2023-27, specifically the Efficient, Effective and Accessible Council theme.
RECOMMENDATION/S The Pensions Committee is recommended to:
(1) endorse the procurement process, utilising the Northern LGPS Framework Lot 2 – UK Property Advisory Mandate, as outlined within this report; and
(2) approve the appointment of CBRE Limited as strategic property advisors to the Merseyside Pension Fund. SUPPORTING INFORMATION 1.0 REASON/S FOR RECOMMENDATION
1.1Merseyside Pension Fund (MPF) has more than £1bn in real estate investments of which around half is invested directly in a portfolio of UK properties. It is essential that the Fund receives professional advice both in relation to the strategic oversight of its property portfolio and the day-to-day management of the properties.
2.0OTHER OPTIONS CONSIDERED
2.1Not relevant to this report. The Council’s Constitution requires contracts for a value of more than £1.5m to be approved by the relevant Committee.
3.0BACKGROUND INFORMATION
3.1Northern LGPS set up a Framework for the provision of investment property management services. The Framework covers various aspects of property investment and management, and is divided into six Lots:
Lot 1 - UK Property Discretionary Mandate Lot 2 – UK Property Advisory Mandate Lot 3 – UK Property Management Mandate Lot 4 – Regional Property Advisory Mandate Lot 5 – UK Property Valuer Mandate Lot 6 – UK Property Value-Add Management Mandate
3.2Merseyside Pension Fund seeks to appoint from Lot 2 of the Framework after successful completion of a mini competition, including in person interviews held on 23 April 2025.
Overview of Selection Process
3.3Stage 1 – Drafting of Request for Proposal (“RfP”) Documents: RfP documents were drafted for the mini-competition based on internal discussions. The RfP documents assessed bidders across a wide range of criteria that were most pertinent to the Fund’s needs from a UK core property investment adviser. A draft copy of the legal contract was also issued to bidders, with comments or suggested amendments invited.
3.4Stage 2 – RfP Documents Issued: All 7 investment managers appointed to the Lot 2 Framework were issued with the RfP documents and draft legal contract on Thursday 19 December 2024. A deadline for clarification questions was set at 5pm on Friday 10 January 2025, with the final deadline for receipt of each bidder’s submission set at 5pm on Friday 24 January 2025. One of the bidders notified officers to say that they no longer met the minimum criteria and therefore would not be submitting a response to the RfP and would not be participating in this mini-competition process, although they will remain part of the Framework. Six managers submitted responses to the RFP
3.5Stage 3 – Assessment of Submissions: Following receipt of submissions, an initial assessment was made to ensure continued adherence to the minimum criteria established in the Framework selection, along with acceptance of the Fund’s Freedom of Information and Modern Slavery requirements. The purpose of this stage was to reject any submissions that no longer met the mandatory criteria ahead of conducting the formal assessment. All submissions received successfully met these conditions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.