Environment, Climate Emergency and Transport Committee decided this item on Wednesday 9 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved (8:2)- That the Director of Neighbourhood Services be authorised to implement the design amendments to the New Chester Road scheme set out as Option 1 within this report, with the exception of the speed limit review element which will be considered as part of the forthcoming borough-wide speed limit review.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Recommendation
The Environment, Climate Emergency and Transport Committee is recommended to authorise the Director of Neighbourhood Services to implement the design amendments to the New Chester Road scheme set out as Option 1 within this report, with the exception of the speed limit review element which will be considered as part of the forthcoming borough-wide speed limit review. SUPPORTING INFORMATION
Reasons for recommendation
1.1The New Chester Road cycle scheme has been subject to a detailed design review undertaken by an external consultant. This has included consideration against regional and local policy, design guidance, on-site observations, motor traffic, cycle, and pedestrian data, junction modelling, road safety data and 2024 public and stakeholder consultation responses. The review has been an evidence based process and this information has all been all been considered in preparation of this report and its recommendations.
1.2New Chester Road is identified as a key link within the Core Active Travel Network (CATN) Route 11 adopted in January 2025, which supports the delivery of the Wirral Council Places for People Strategy, which was adopted in January 2024. It improves connectivity and accessibility, to enable safer active and sustainable travel and provides a key link for cyclists improving access between the centre of New Ferry, Rock Ferry and Birkenhead, passing close to Rock Ferry train station and employment areas adjacent to the River Mersey.
2.0OTHER OPTIONS CONSIDERED
2.1The Council could decide to remove the current scheme and reinstate the highway layout as it was ‘pre-scheme’. This option is not considered appropriate as removal could result in reputational issues for the Council in terms of its commitment to active travel which could result in future funding allocations against transport schemes being reduced. Removal of the scheme could be seen to contradict the ambitions of the adopted CATN strategy and would impact the safety and convenience of the cyclists that are currently using the route. If this option was taken forward the marked (painted) cycle lanes would remain as they pre-dated the installation of spaced separators fixed to the ground (known as ‘Orcas’), which was effectively an enhancement to the existing lanes. Section 4.1.1 of the Mott MacDonald Design Review at Appendix 1 sets out further detail.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.