Resolved – That ? 1. ???? the procurement process as outlined within the report be endorsed; and ? 2. ???? the Director of Merseyside Pension Fund be delegated authority to appoint a main contractor for refurbishment works of Castle Chambers, Liverpool. The outcome of the procurement and contract award to be reported to a future Pensions Committee for noting.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
As part of its investment portfolio, Merseyside Pension Fund (MPF) owns a number of properties across the UK. It is essential that these properties are well maintained to ensure compliance with regulatory/environmental standards and to retain and attract tenants. This report seeks approval from Pensions Committee for the appointment of a main contractor to undertake refurbishment works at Castle Chambers, Liverpool, one of the Fund’s property holdings.
The report supports the Council Plan: Wirral Working Together 2023-27, specifically the Efficient, Effective and Accessible Council theme.
This is a Key Decision due to the value of the contract likely to be in the region of £5m. There are no specific ward implications.
RECOMMENDATION/S The Pensions Committee is recommended to:
(1) endorse the procurement process as outlined within this report; and (2) delegate to the Director of Merseyside Pension Fund the appointment of a main contractor for refurbishment works of Castle Chambers, Liverpool. The outcome of the procurement and contract award to be reported to a future Pensions Committee for noting. SUPPORTING INFORMATION 1.0 REASON/S FOR RECOMMENDATION
1.1Merseyside Pension Fund (MPF) has more than £1bn in real estate investments of which around £400m is invested directly in a portfolio of UK properties. It is essential that the Fund’s properties are well maintained to ensure compliance with regulatory/environmental standards and to retain and attract tenants.
2.0OTHER OPTIONS CONSIDERED
2.1Not relevant to this report. The Council’s Constitution requires contracts for a value of more than £1.5m to be approved by the relevant Committee.
3.0BACKGROUND INFORMATION
3.1CBRE Ltd, MPF’s strategic property advisors have reviewed the Fund’s property portfolio to ensure the property holdings remain fit for purpose, meet existing and future regulatory and environmental standards and align with the Fund’s commitment to net zero climate targets. Castle Chambers, Liverpool has been identified as requiring works to attract new tenants and to comply with the environmental standards coming into effect in 2028 and beyond.
3.2Following an options appraisal, CBRE Ltd was instructed by MPF to carry out the design and management of the works - both pre and post construction activities. The project goal is to undertake refurbishment works to the basement, forming a cycle store and shower facility, first floor forming CAT A offices and terraces, second floor forming CAT B office, and sixth floor forming CAT A offices and terraces. (A CAT A fit out refers to the basic level of interior construction provided by landlords to make a commercial space functional and ready for occupancy. A CAT B fit out is the process of bringing all the office design elements together to create a functional workplace).
3.3This report sets out the tender process undertaken and the Project Team’s recommendation for the appointment of a Main Contractor to undertake the masterplan refurbishment works at Castle Chambers, Liverpool.
The areas within the site are to include: • Basement; • First Floor; • Second Floor; • Sixth Floor.
3.4Tender documents were issued on 26 November 2024 with a deadline submission date of 31 January 2025, a tender period of 66 days. All the contractors confirmed their intention to submit tenders. During the tender period queries were raised and subsequently the tender submission deadline was extended to 14 February 2025. 3.5 In line with the Instructions to Tenderers all six contractors returned tender submissions via the CHEST System. The tender assessment was based on the criteria and weightings captured in the table below.
No Theme Sub Weighting
1 Delivery of Works 7.5%
1 Health and Safety 7.5%
2 Resource 7.5%
3 Programme 5%
4 Supply Chain Management 2.5%
Quality Total 30.00%
Price 70.00%
Total Weighting 100.00%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.