Resolved
Resolved (unanimous) – that the decision be deferred until November and included in the Capital Monitoring Report, to allow sufficient time for further options to be considered and developed through further workshops
Policy and Resources Committee deferred this item on Wednesday 10 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved (unanimous) – that the decision be deferred until November and included in the Capital Monitoring Report, to allow sufficient time for further options to be considered and developed through further workshops
The Policy and Resources Committee is requested to recommend to Council the most suitable options for resource allocation, based upon the options suggested at paragraphs 3.13 to 3.16 to this report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The report recommends that Committee agrees the virements and amendments to the Capital Programme to mitigate the adverse budgetary position of the regeneration works within Birkenhead town centre.
2.0OTHER OPTIONS CONSIDERED
2.1Standard practice for reporting on the Capital Programme is on a quarterly basis, however this additional report is presented to Members due to the importance of addressing the budgetary position of the regeneration works being conducted within Birkenhead town centre.
3.0BACKGROUND INFORMATION
Central Birkenhead Programme
3.1Delivery of the Central Birkenhead Programme, includes works to:
• Conway Street, Europa Boulevard, and Europa /Boulevard project; • Charing Cross and Grange Road project; and • Grange Road West.
3.2As reported to this Committee on 23 July 2025, the Council had been alerted to the requirement to increase funding to meet its legal and contractual obligations. As a consequence, this Committee recommended that an additional £8.000 million of resource be incorporated into the Capital Programme. The recommendation is to be approved by Full council on 13 October 2025.
3.3Within that report, Members were provided with an update regarding the circumstance that had evolved during the project and an estimated revised cost:
“Spend profile to date indicates an estimated contract cost of £21.000 million with the additional £3.500 million anticipated for management fees. Given the type of contract and continual delays with design information these costs will continue to increase throughout the life of the contract.
The original project budget was £11.900m, however the projected outturn currently stands at £24.500m. An additional £4.750m has already been allocated, and an £8.000m projection is a fair reflection of the further pressure. It may yet be able to reduce the value of some of the contractor claims. This additional funding requirement will be added to the Programme as being financed by borrowing, although all efforts will be made to reduce this borrowing requirement and utilise alternative financing if possible.”
3.4Resolution three of the aforementioned report sought that the Council grant the Director of Finance the authority to review the capital programme to identify options to reduce this borrowing requirement to mitigate the forecast overspend. These options are considered within this report. 3.5 There are governance procedures in place that must be adhered to regarding the specific funding of the Central Birkenhead Programme. The most prominent element of the financing of these works is the grant funding associated with the ‘Simplification Pathfinder Pilot.’ The Simplification Pathfinder Pilot aims to give councils increased decision-making ability, ensuring more flexibility when it comes to effectively responding to changing economic conditions. The pilot brought together three different steams of funding which are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Potential Virements to the Central Birkenhead Programme Within the Capital ProgrammeAppendix 1 | 54 KB | Download |
PDF |
Central Birkenhead ProgrammeReport | 162 KB | DownloadRead as text |
Follow Policy and Resources Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2026 | New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... | Approved | Open |
| 22 Jul 2026 | Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... | Approved | Open |
| 22 Jul 2026 | Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... | Decided | Open |
| 22 Jul 2026 | Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... | Noted | Open |
| 22 Jul 2026 | Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.