ELECTRIC VEHICLE CHARGING INFRASTRUCTURE UPDATE AND CROSS FOOTWAY RESIDENTIAL CHARGING SOLUTIONS PILOT
AgreedCommittee2 papers
AI summaryWirral's Environment Committee backs cross-footway EV charging pilot and authorises legal agreements with Liverpool City Region to roll out public on-street chargepoints using £9.647m LEVI funding.
Money£9.647m LEVI funding, £1.053m further grantHeld centrally by Liverpool City Region Combined Authority
What happens nextCPO contract starts July 2026Cross-footway trial minimum 12 months
Who it affectsResidents without driveways, on-street parking usersAbout 22% of Wirral households rely on on-street parking
What was decided
The committee noted the update on the Electric Vehicle Infrastructure Strategy and the Local Electric Vehicle Infrastructure (LEVI) funding. Report P1, P2
The committee authorised the Director of Neighbourhoods to agree appropriate legal agreements with the Liverpool City Region Combined Authority to progress the public on-street and car park EV charging project. Report P2, P3
The Director of Neighbourhoods was also authorised to work with the Combined Authority to develop and join a Liverpool City Region-wide pilot evaluating cross-footway home charging solutions, subject to technical and safety considerations being properly managed. Report P4, 1.2
Why
Petrol and diesel car sales will be banned from 2030 and hybrids from 2035, and current charging infrastructure in Wirral is not sufficient to support EV rollout. Report 1.1
Around 22% of households in Wirral rely on on-street parking, and those with off-street parking are over three times more likely to switch to an EV. Report 3.9
Cross-footway solutions can be cheaper for residents (5% VAT on domestic electricity versus 20% on public) and reduce trailing cable trip hazards, but need trialling to test safety and practicality. Report 1.2, 3.9, 3.13
What happens next
The Combined Authority is procuring a chargepoint operator for the whole city region, with final tender responses due by 20 May and the contract commencing in July 2026. Report 3.5, 3.6
The council will run a separate trial of low-profile cable protection mats (under 20mm) with residents who already have permission to charge across the footway. Report 3.11
An inter-authority legal agreement will set out the roles, responsibilities, funding, timescales and licences between the Combined Authority, Wirral Council and the appointed chargepoint operator. Report 5.2
The money
£9.647 million LEVI funding awarded to Liverpool City Region Combined Authority Report 3.5, 4.1
£47k LEVI funding allocated to cross-footway channel solutions pilot across the region Report 3.14, 4.2
£1.053 million Further grant allocated to Combined Authority for cross-footway channel charging, subject to bidding exercise Report 3.14, 4.2
£45,083 DfT On-street Residential Chargepoint Scheme funding claimed for installing 53 chargepoints in 2021 Report 3.3
£0.38 p/kWh Tariff introduced in October 2022 for residents using council on-street chargepoints Report 3.3
Options considered
Rejected: Do not work with the Combined Authority on public EV charging rollout. Would contradict the ambitions of the EV Charging Infrastructure Strategy Report 2.1
Rejected: Do not take part in the LCR-wide cross-footway charging pilot. Many residents without driveways have asked for home charging solutions and grant funding is currently available Report 2.2
Rejected: Wait for other Combined Authority councils to trial cross-footway solutions first. Capital funding is available now with no guarantee later, and local learning would be missed Report 2.3
Implications
Financial: LEVI funding is held centrally by the Combined Authority and split equally across the six local authority areas; tariffs on lamp-column and car park chargepoints will be set by the appointed operator. Report 4.1, 4.4
Financial: Maintenance and removal costs for any cross-footway channels in Wirral would fall to the council, to be covered by an annual fee from participating residents. Report 4.3
Legal: A Section 50 street works licence may be required for private installations; cables left across the footway without permission are an offence under Section 162 of the Highway Act 1980. Report 3.10, 5.4
Legal: Participants in the cross-footway trial would need to sign an agreement and evidence household or motor insurance to remove council liability while a channel is in use. Report 5.5
Equalities: An Equality Impact Assessment has been completed and is published on the council's website; no cross-footway solution is currently fully PAS 1899 compliant, which may affect disabled and older users. Report 9.2, P33, P51
Climate: Delivery supports the council's 2019 climate emergency declaration, the Air Quality Strategy approved in December 2023, and the Cool Wirral 3 target of fossil-fuel-free local travel by 2041. Report 1.3, 10.1
Staffing: Existing staff are supporting rollout; further resources for licences, inspections and enforcement are likely to be needed and are expected to be self-funded from chargepoint income. Report 6.1
Risk: Trip, electrocution, earthing and parking-dispute risks are identified, and 15 of the existing 53 chargepoints are currently not operational due to lack of repair funding. Report 3.4, 7.1, P51, P52
Who and where
Residents without off-street parking, around 22% of Wirral households Report 3.9
Existing users of the 53 on-street chargepoints installed in 2021, 15 of which are not currently operational Report 3.3, 3.4
94 households already authorised to charge across the footway using a cable protection mat Report 3.10
Disabled residents and those with mobility issues, for whom no cross-footway solution is currently fully PAS 1899 compliant Report P33
Port Sunlight Village Trust, with whom initial discussions on the residential trial have begun Report 8.5
Timeline
2019: Council submitted bid to DfT On-street Residential Chargepoint Scheme Report 3.3
Between July and September 2021: 53 slow/standard 7kW chargepoints installed with £45,083 DfT funding Report 3.3
October 2022: Tariff of £0.38 p/kWh introduced on on-street chargepoints Report 3.3
October 2023: Office for Zero Emission Vehicles announced LEVI fund, with £9.647m to the Combined Authority Report 3.5
21 October 2024 to 6 February 2025: Public consultation on locations for on-street chargepoints, 464 responses received Report 8.2
21 October 2024: Committee requested update on usage of existing chargepoints Report 3.4, P84
3 November 2025: Procurement Specific Questionnaires from chargepoint operators anticipated to be completed Report 3.6
29 January 2026: Initial tender responses due Report 3.6
27 February to 25 March 2026: Negotiation period with up to 8 bidders Report 3.6
20 May 2026: Final tender responses due for evaluation Report 3.6
July 2026: Chargepoint operator concession contract due to commence Report 3.6, 6.5
Minimum 12 months: Envisaged length of cross-footway residential charging trial to capture seasonal issues Report 3.16
15-year concession period: Chargepoint operator will own, operate and maintain infrastructure, with assets refreshed at least once Report 6.5
Plain English for the jargon
LEVI: Local Electric Vehicle Infrastructure fund, administered by the Office for Zero Emission Vehicles to support on-street residential charging
LCRCA: Liverpool City Region Combined Authority, holding LEVI funding centrally and leading procurement
CPO: Chargepoint Operator, the private company that will install, own and run the EV charging network under a concession contract
ORCS: On-street Residential Chargepoint Scheme, the DfT fund used in 2019 to install the existing 53 Wirral chargepoints
Cross-footway charging: Running an EV charging cable across the pavement from a home or a dedicated channel/gully to a parked car
PAS 1899: Accessibility standard for electric vehicle chargepoints covering placement, design and information
OZEV: Office for Zero Emission Vehicles, the government body providing LEVI and other EV grants
Section 50 licence: Street works licence under the New Roads and Street Works Act 1991, required for private installation of apparatus in the public highway
Section 162 Highway Act 1980: The offence of placing rope, wire or apparatus across a highway that may endanger other users, including EV charging cables
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55
Resolved
Resolved – That the Environment, Climate Emergency and Transport Committee: 1. notes the update regarding the Electric Vehicle Infrastructure Strategy and the Local Electric Vehicle Infrastructure funding; and 2. authorises the Director of Neighbourhoods to: (a) agree with the Liverpool City Region Combined Authority any appropriate legal agreements (such as that set out in paragraph 5.2) that may be required to progress the delivery of the Local Electric Vehicle Infrastructure project for public on street and car park electric vehicle charging infrastructure; and ... view the full minutes text for item 55.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Recommendation
The Environment, Climate Emergency and Transport Committee is recommended to:
1. note the update regarding the Electric Vehicle Infrastructure Strategy and the Local Electric Vehicle Infrastructure funding; and 2. authorise the Director of Neighbourhoods to:
a) agree with the Liverpool City Region Combined Authority any appropriate legal agreements (such as that set out in paragraph 5.2) that may be required to progress the delivery of the Local Electric Vehicle Infrastructure project for public on street and car park electric vehicle charging infrastructure; and
b) work with the LCRCA to develop and participate in an LCR wide pilot project to evaluate various cross footway solutions for charging vehicles using a home chargepoint where residents do not have a private driveway, subject to all technical and safety considerations being appropriately managed. SUPPORTING INFORMATION
Reasons for recommendation
1.1The sale of new petrol and diesel cars and vans will be banned from 2030, and hybrids will be banned from 2035. The current charging infrastructure in Wirral is not sufficient to support the roll out of electric vehicles. The Council is receiving regular requests for additional electric vehicle charging, both public infrastructure and to support residents to charge using home chargers at residential properties without private driveways. The ongoing delivery of the EVCI Strategy, including the delivery of new public charging points and taking part in a pilot regarding options to support cross footway charging for residential properties without off street parking, will enable the Council to work towards addressing this demand.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.