Decided Committee 1 paper

AI summaryPolicy and Resources Committee authorises open market sale of the closed Heswall Day Centre, ending £41,300 a year in holding costs and aiming for a capital receipt.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided
Money£41,300 a yearHolding costs for the closed building, which will stop once sold
What happens nextMarket the property for saleProperty consultants to be used, fees deducted from proceeds
Who it affectsNot stated

What was decided

The Committee authorised the Assistant Director of Property and Investment to negotiate and finalise a sale of the property on the open market, aiming for the best price reasonably obtainable.

Property consultants will be instructed to market the property and advise on the sale, with their fees taken from the proceeds. Report 5.1

Why

Selling the closed building will generate a capital receipt and remove ongoing holding costs of £41,300 a year. Report 4.1, 4.2

The Council is required by section 123 of the Local Government Act 1972 to obtain the best price reasonably obtainable when disposing of property. Report 5.1

Officers said the disposal fits the Council's Asset Strategy and will cut the risk of anti-social behaviour at a vacant site. Report 6.2, 12.1

What happens next

The Assistant Director will negotiate and finalise the sale on the open market.

An Energy Performance Certificate will be provided if required, and any redevelopment would need to meet current energy efficiency standards. Report 10.1

The money

  • £41,300 per annum Budgeted holding costs for the closed property, which will cease once sold Report 4.2
  • £42,000 per annum Holding cost exposure cited as the risk of failing to sell Report 7.1

Options considered

  • Chosen: Sell on the open market for the best price reasonably obtainable. Meets the legal duty under section 123 Local Government Act 1972 and ends ongoing holding costs Report 5.1, 4.1, 4.2

Implications

  • Financial: A capital receipt will be generated and ongoing holding costs will stop once the property is sold. Report 4.1, 4.2
  • Legal: Disposal must achieve the best price reasonably obtainable under section 123 of the Local Government Act 1972. Report 5.1
  • Risk: If the property fails to sell, the expected capital receipt is lost and holding cost exposure of £42,000 a year continues. Report 7.1
  • Risk: Selling the vacant building is expected to reduce anti-social behaviour risk. Report 12.1
  • Climate: An Energy Performance Certificate may be required, and any redevelopment must meet current energy efficiency standards. Report 10.1
  • Equalities: Officers identified no direct equality implications from the disposal. Report 9.1
  • Staffing: Officers identified no staffing implications from the disposal. Report 6.1
  • Other: The disposal is presented as bringing forward a redevelopment opportunity for the site. Report 11.1

Who and where

  • Prospective buyers approached during the open market sale
  • The local area, where the former day centre site could be redeveloped Report 11.1
  • Council taxpayers, who currently bear the £41,300 a year holding costs Report 4.2

Timeline

  • 10 June 2025: Adult Day Care and Public Health Committee considered the property Report P24
  • 10 September 2025: Policy and Resources Committee considered the property Report P24
  • 13 November 2025: Officers and members of Policy and Resources Committee held a workshop on this and other properties Report 8.1
  • 14 January 2026: Policy and Resources Committee authorises the open market sale

Plain English for the jargon

  • Section 123 of the Local Government Act 1972: The legal duty on councils to obtain the best price reasonably obtainable when disposing of property
  • Capital receipt: A one-off income payment received by the Council from selling an asset
  • Energy Performance Certificate: A document showing the energy efficiency rating of a building and ways to improve it
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item96

Resolved

Resolved – That Policy and Resources Committee authorises the Assistant Director of Property and Investment to negotiate and finalise a sale of on the open market with a view to achieving the best price reasonably obtainable.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

POLICY AND RESOURCES COMMITTEE Wednesday, 14 January 2026

REPORT TITLE: HESWALL DAY CENTRE REPORT OF: ASSISTANT DIRECTOR: PROPERTY AND INVESTMENT

REPORT SUMMARY

The purpose of this report is to seek authority to dispose of Heswall Day Centre on the best terms reasonably possible.

This report has linkages to the Council Plan, specifically the Efficient, Effective and Accessible Council and the People-Focused regeneration themes.

The matter is a key decision as it affects a property with a value in excess of £500,000.

RECOMMENDATION/S

The Policy and Resources Committee is recommended to authorise the Assistant Director of Property and Investment to negotiate and finalise a sale of Heswall Day Centre on the open market with a view to achieving the best price reasonably obtainable. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1The Council no longer requires this surplus asset, and the recommendation will allow the Council to get the best consideration that is reasonably possible. Generating a capital receipt will help support the Council’s Capital Programme.

1.2The Council by releasing the asset will bring the site back into economic use, which will support the economy, both in terms of any physical works undertaken and the end use of the asset.

1.3Functionally this recommendation (if approved) will enable the Council to dispose of this surplus asset, which will relieve the burden of costs and risks associated with holding it.

2.0OTHER OPTIONS CONSIDERED

2.1The other option would be for the Council to retain this asset. However there would be holding costs in the sum of £41,300 per annum pending the premises being used for a different purpose. This option is not recommended given that Policy and Resources Committee at its meeting of 10th September 2025 amongst other matters, declared Heswall Day Centre surplus to the Council’s requirements. . .

3.0BACKGROUND INFORMATION

3.1Heswall Day Centre is a single storey building constructed in the 1970s and has been used latterly by the Council to deliver adult day care to support adults with learning and physical disabilities. The property sits on a plot which extends to approximately one acre and is well located in Heswall town centre.

3.2Due to the need for significant repairs on the asset, the property was closed in September 2024. The Adult Day Care and Public Health Committee at its meeting of June 2025 resolved to:

1. approve that Heswall Day Centre is no longer required by the Directorate of Adult Social Care for the operational provision of day services; and

2. recommend to Policy and Resources Committee that: a. Heswall Day Centre be declared surplus to requirements; and b. The Director of Regeneration and Place be authorised to market the property for sale in accordance with Section 123 of the Local Government Act 1972, to secure the most preferential opportunity to the Council.

3.3Policy and Resources Committee at its meeting of 10th September 2025 resolved (amongst other matters) to:

1. Declare as surplus to the Council’s requirements the Heswall Day Centre.

2 Authorise the Assistant Director of Property and Investment to arrange a member workshop to understand the possible options on future use of Heswall Day Centre including, but not limited to, the viability for the provision of Extra Care Housing, either general, specialist or a mixed model or progressing a sale on the open market. The outcome of such workshop to be reported to a future meeting of this Committee.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heswall Day CentreReport 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 22 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, present
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, apologies
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, apologies, sent representative
MS
Councillor Mark SkillicornCommittee Member, present

All 22 on the meeting page

On this subject at Wirral

Search all
  1. Heswall Day CentreThis decision
  2. Heswall Day Service AssetApproved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open