AI summaryWirral Place Based Partnership Board noted the Month 8 2025/26 finance position: a £45.3m year-to-date deficit against a £34.3m plan, and a £4.93m pooled fund forecast overspend, with the Better Care Fund reporting breakeven.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedIncluding system, pooled fund and BCF positions
MoneyNot stated
What happens nextSection 75 agreement signing in progressFor the 2025/26 pooled fund
Who it affectsWirral health and care system partnersICB, trusts, council and residents

What was decided

The Board noted the forecast reported position for the Wirral System and Pooled Fund as at Month 8 2025/26. Report P4, P45

The Board noted that shared risk arrangements are limited to the Better Care Fund, which is reporting a forecast breakeven position. Report P4, P36

The Board noted the 2025/26 Section 75 agreement is complete and signing is in progress. Report P4, P47

Why

The report provides a Month 8 2025/26 update on the financial position of Wirral Place health and care system partners. Report P2, P9

The system reported a £45.3m year-to-date deficit against a £34.3m plan, an £11.0m adverse variance, with NHS partners forecasting a £42.3m deficit and Wirral Council Adult Health and Care £8.9m overspent at Quarter 2. Report 1.2, P11, P12, P15, P16

The Pooled Fund is forecast to overspend by £4.93m, made up of £3.62m on local authority commissioned Health and Care and £1.31m on ICB place, while the Better Care Fund is breakeven. Report P27, P29, P31

What happens next

Risk-sharing arrangements from 2024/25 are to be retained, with 50% risk share applied only to the Better Care Fund; host organisations hold full risk on other areas. Report P35, P36

The Finance and Investment Group will continue detailed oversight of the strategic and financial risks in the Place Delivery Assurance Framework. Report P37

Further work, including Quality and Equality Impact Assessments, is being undertaken to review commissioned services to manage pressures. Report 2.2

The money

  • £45.3m Wirral system actual year-to-date deficit at Month 8 2025/26 Report 1.2, P15
  • £34.3m Planned year-to-date deficit at Month 8 2025/26 Report 1.2, P15
  • £11.0m Adverse variance of actual against plan year-to-date Report 1.2, P15
  • £42.3m Forecast outturn planned deficit for Wirral NHS partner organisations Report P11, P15
  • £8.9m Forecast overspend on Wirral Council Adult Health and Care at Quarter 2 Report P12, P16
  • £333.50m Pooled Fund budget plan for 2025/26 Report P22, P23, P29
  • £4.93m Pooled Fund forecast overspend at Month 8 2025/26 Report P27, P29
  • £3.62m Overspend on Local Authority commissioned Health and Care within Pooled Fund Report P27, P29
  • £1.31m Overspend on ICB place element of Pooled Fund Report P27, P29

Options considered

  • Chosen: Retain 2024/25 risk-sharing approach (50% risk share on BCF only, host organisations hold risk elsewhere). Proposed to keep the more focused risk-sharing arrangements, with BCF currently reporting breakeven Report P35, P36

Implications

  • Financial: Continuing pressures on activity, efficiency savings delivery and demand in MH, ADHD, prescribing, LD and MH services across Wirral partners. Report 2.2, P31
  • Legal: A Section 75 agreement is required to draw down Better Care Fund resources and pool wider funding; 2025/26 agreement is agreed with signing in progress. Report 2.3, P4, P47
  • Risk: Place Delivery Assurance Framework risks identified on service delivery, children and young people, finance and unscheduled care capacity. Report P6, P33, P34
  • Equalities: No Equality Impact Assessment required for this report; detailed EIAs will accompany any future service reviews. Report 2.2, 2.6
  • Climate: No specific environmental or climate issues identified in this report. Report 2.7
  • Other: Community Wealth Building focus on partnerships to reduce health inequalities and support a resilient, inclusive Wirral economy. Report 2.8

Who and where

  • NHS Cheshire and Merseyside (Wirral Place ICB) Report P7, P15
  • Wirral Community Health and Care NHS Foundation Trust Report P15
  • Wirral University Teaching Hospital NHS Foundation Trust Report P15
  • Cheshire and Wirral Partnership NHS Foundation Trust Report P15
  • Wirral Metropolitan Borough Council (Adult Health and Care) Report P12, P16
  • Vulnerable Wirral residents receiving pooled services Report P21

Timeline

  • 2nd September 2025: Joint Health and Care Finance Executive Group approved Commissioning Budget paper 2025/26 Report P7
  • November 2025: Wirral Council Policy and Resources Committee received Quarter 2 Adult Health and Care position Report P12
  • Month 8 2025/26 (end of November 2025): Reported financial position of the Wirral system and Pooled Fund Report P2, 1.2
  • 22nd January 2026: Place Finance Report considered by Wirral Place Based Partnership Board Report P1

Plain English for the jargon

  • BCF: Better Care Fund, a pooled fund for integrated health and social care
  • Section 75 agreement: Contractual agreement under the NHS Act 2006 enabling partners to pool funds and draw down Better Care Fund resources
  • PDAF: Place Delivery Assurance Framework, the partnership's strategic risk register
  • Pooled Fund: Combined budget of NHS and local authority partners used to commission integrated services in Wirral
  • WPBPB: Wirral Place Based Partnership Board
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

Resolved – That 1. The ... view the full minutes text for item 53.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Wirral Place Based Partnership Board

Title Place Finance Report incorporating Pooled Fund Update Martin McDowell, Associate Director of Finance, NHS Cheshire and Authors Merseyside (Wirral) Report for Wirral Place Based Partnership Board Date of Meeting 22nd January 2026

Report Purpose and Recommendations The purpose of this report is to provide the Wirral Place Based Partnership Board with an update on the financial position for the Wirral Place health and care system partners as at the end of November 2025, Month 8 in the financial year 2025/26.

It is recommended that the Wirral Place Based Partnership Board notes the report and the specific recommendations in relation to the Pooled Budget, listed below:

• Note the forecast reported position for the Wirral System and Pooled Fund as at Month 8 2025/26. • Note that the shared risk arrangements are limited to the Better Care Fund only, which is reporting a forecast breakeven position. • Note the 2025/26 Section 75 agreement is complete and the signing of the agreement is in progress.

Key Risks The report relates to the following key risks identified in the Place Delivery Assurance Framework presented to the Wirral Place Based Partnership Board:

• PDAF 1 Service Delivery: Wirral system partners are unable to deliver the priority programmes within the Wirral Health and Care Plan which will result in poorer outcomes and greater inequalities for our population. • PDAF 2 Children and Young People: The Wirral health and care system is unable to meet the needs of children and young people with complex and/or additional needs leading to long term health issues, increased inequalities and demand on services. • PDAF 5 Finance: Financial pressures in the Wirral health and care system could impact on the quality of care and patient experience. • PDAF 7 Unscheduled Care: The is a risk that a lack of Urgent and Emergency Care capacity and restricted flow across all sectors in Wirra (primary care, community, mental health, acute hospitals and social care) results in patient harm and poor patient experience.

Governance journey Date Forum Report Title Purpose/Decision Joint Health and Care Finance Pooled Fund 2nd September 2025 Approved Commissioning Budget paper 2025/26 Executive Group 1 Narrative 1.1 Background 1.1.1 NHS Cheshire and Merseyside continue to work with each of the nine Places in the Cheshire and Merseyside Integrated Care System (ICS) to establish robust governance and assurance mechanisms through strong partnership arrangements.

The Wirral Place Based Partnership Board (WPBPB) is the forum where NHS Cheshire and Merseyside will conduct business pertaining to the Borough transparently in the public domain and in collaboration with system partners. These arrangements will also support further delegation of decision making and resources to each Borough.

1.1.2 The Place Finance Report incorporating Pooled Fund Update has been developed to update the WPBPB on progress in terms of delivering the 2025/26 financial plan during the year and will advise upon risks and mitigations as required.

1.2Wirral Place System Financial Update (Month 8, November 2025) 1.2.1 The Wirral system financial performance is shown in Table 1, and notes that the system had an actual reported deficit of £45.3m compared with a planned year-to- date deficit of £34.3m, which represents an adverse variance of £11.0m.

The reported collective forecast out-turn position for Wirral NHS partner organisations is planned deficit of £42.3m, although all partners have acknowledged financial risks to the delivery of this position in terms of activity levels and efficiency delivery.

Wirral Metropolitan Borough Council (MBC) financial position at Quarter 2 for Adult Health and Care was reported to the Council’s Policy and Resources Committee in its November 2025 meeting. This an adverse variance due to increased activity and costs in social care services and are predicted to be £8.9m overspent unless further mitigating actions can be identified.

Table 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Place Finance Report incorporating Pooled Fund UpdateReport 178 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 26 attended
RE
Rhys EdwardsCommittee Officer, expected
KL
Karen LiveseyChair, apologies
GC
Councillor Graeme CooperCommittee Member, present
SR
Councillor Simon R MountneyCommittee Member, present
KM
Councillor Kieran MurphyCommittee Member, present
SB
Simon BanksCommittee Member, present
TW
Tim WelchCommittee Member, present
JH
Janelle HolmesCommittee Member, apologies, sent representative
AA
Abel AdegokeCommittee Member, apologies
DJ
Dr David JonesCommittee Member, present
SW
Dr Stephen WrightCommittee Member, present
IC
Ian CubbinCommittee Member, present

All 26 on the meeting page

On this subject at Wirral

Search all
  1. Place Finance Report incorporating Pooled Fund UpdateThis decision
  2. Place Finance Report incorporating Pooled Fund UpdateNoted
  3. Place Finance Report incorporating Pooled Fund UpdateNoted
  4. Place Finance Report incorporating Pooled Fund UpdateNoted
  5. Place Finance Report incorporating Pooled Fund UpdateNoted
  6. Place Finance Report incorporating Pooled Fund UpdateNoted

More from Wirral Wirral Place Based Partnership Board

All decisions
MeetingDecisionOutcome
26 Mar 2026 Minutes of Previous MeetingResolved – That the minutes of the meeting held on 22 January 2026 be agreed. Agreed Open
26 Mar 2026 Quality and Performance ReportResolved – That the report be noted. Noted Open
26 Mar 2026 Place Finance Report incorporating Pooled Fund UpdateResolved – That 1. The forecast reported position for the Wirral System and Pooled Fund as at Month 10 2025/26 be not... Noted Open
26 Mar 2026 Unscheduled Care Improvement Programme UpdateResolved – That the report be noted. Noted Open
26 Mar 2026 Wirral Provider Alliance UpdateResolved – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies