AI summaryWirral Council votes 56 to 0 with 1 abstention to formally oppose the Peak Cluster CO2 pipeline through the borough and to write to the Secretary of State demanding cancellation or an alternative route.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedCalls for project cancellation or rerouting away from the peninsula
MoneyNot stated
What happens nextLetter to Secretary of StateAll 66 councillors asked to sign; Chief Executive to send
Who it affectsWirral residents and environment320,000 residents represented; Green Belt, farms, nature reserves
What was decided
The Council resolved to formally oppose routing the Peak Cluster CO2 pipeline through Wirral and to demand the project's cancellation or, failing that, an alternative route to the Irish Sea that avoids the borough. Report P28, P43
The Council will submit objections to the relevant planning and regulatory authorities, call for an independently verified environmental and safety impact assessment with full public consultation, and demand robust emergency-response planning if the project proceeds. Report P43
All 66 councillors are to be asked to sign a letter to the Secretary of State for Energy Security and Net Zero, copied to Wirral's four MPs, with the Chief Executive tasked to send it as soon as practically possible. Report P7, P43, P44, P45, P59
Why
The motion states that the Wirral does not produce the emissions the pipeline would carry, which originate in the East Midlands and Peak District, and that routing it through the borough would make the peninsula a corridor for other regions' pollution. Report P29
Councillors cited risks to protected Green Belt, high-value habitats and wildlife corridors, the scale of an above-ground facility proposed at Moreton, and the disruption, noise and visual impact of construction through communities and farmland. Report P11, P12, P18, P32, P33, P35, P54
Safety concerns were raised about high-pressure CO2 releases, including a 2020 pipeline rupture near Satartia, Mississippi that led to the evacuation of approximately 200 residents and hospital treatment for dozens. Report P15, P51
What happens next
The Chief Executive is to arrange for the letter to the Secretary of State, signed by councillors, to be sent and copied to Wirral's four Members of Parliament. Report P7, P43
The Council will formally object to relevant planning and regulatory authorities and seek a comprehensive, independently verified environmental and safety impact assessment with full local public consultation. Report P43
The Council will work with neighbouring authorities, community groups and environmental organisations to advocate for alternative climate strategies prioritising renewable energy and local green jobs. Report P41, P43
Options considered
Chosen: Call for full cancellation of the Peak Cluster project. Council says the pipeline is an unacceptable intrusion into the Green Belt and a safety risk to residents. Report P10, P19, P28, P43
Chosen: Demand alternative routes to the Irish Sea that avoid the Wirral. Set out as the fallback if cancellation is not secured; routes could follow existing industrial corridors, motorway verges, rail lines or offshore paths. Report P28, P38, P43
Rejected: Accept the pipeline and proceed without local action. Motion states the development is incompatible with the long-term well-being of the community, resident safety and the protected landscape. Report P19, P55
Implications
Environment and climate: Opposition to construction through Green Belt, farmland, wetlands, woodlands and wildlife corridors on the Wirral, and to the proposed Moreton above-ground facility. Report P11, P18, P34, P35, P54
Risk: Safety concerns about high-pressure CO2 releases, including potential oxygen displacement, health hazards and reference to the 2020 Satartia, Mississippi pipeline rupture that evacuated about 200 people. Report P14, P15, P51
Legal: Council to submit objections to relevant planning and regulatory authorities and to demand a legally binding regulatory framework and long-term monitoring if the project proceeds. Report P43
Equalities: Motion frames the project as imposing risks and burdens on Wirral communities for the benefit of distant industries, a fairness and just-transition concern. Report P31, P39, P41
Other: Council signals support for climate action but favours emissions reduction at source and renewable energy, local green jobs and community-led decarbonisation over expanded fossil-fuel-linked infrastructure. Report P19, P41, P55
Who and where
Wirral residents, described as 320,000 people Report P9, P45
Farmers and rural landowners along the proposed route Report P27, P33
Wildlife, habitats and biodiversity in the borough's Green Belt, wetlands, woodlands and coastal margins Report P12, P35, P37
Communities near the proposed above-ground facility at Moreton Report P18, P54
The Secretary of State for Energy Security and Net Zero and Wirral's four Members of Parliament Report P7, P44, P59
Timeline
9 March 2026: Council meeting at which the amended motion was carried (56 in favour, 0 against, 1 abstention). Report P1
09 March 2026: Date of the proposed letter from Wirral's 66 councillors to the Secretary of State. Report P9, P45
2020: CO2 pipeline rupture near Satartia, Mississippi, cited as a real-world safety precedent. Report P15, P51
Plain English for the jargon
Peak Cluster CC project: A proposed carbon capture and storage scheme collecting CO2 from East Midlands and Peak District industries and transporting it via pipeline to storage under the Irish Sea.
Brownfield only Local Plan: Wirral's unanimously agreed Local Plan that prioritises development on previously used land rather than on Green Belt.
CCUS: Carbon Capture, Usage and Storage: capturing CO2 emissions, transporting them, and storing them underground or under the seabed.
Green Belt: Designated protected open land around built-up areas, intended to prevent urban encroachment and safeguard natural landscape and access to open space.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item58
Resolved
Resolved (56:00) 1 abstention – that, A major scheme, the Peak Cluster CC project, is proposing to drive high-pressure CO ? pipelines through our communities, our farms, and our nature reserves on their way to the Irish Sea. We are told this is “needed”, that it is “for the national good”, and that it is “only a temporary disruption”. But we live here. We know better. We propose that Wirral Borough Council, all parties and stakeholders together, as a unified voice, stand firmly opposed to the Wirral being used as a dumping corridor for industries over 200 km away. Together, we call for the cancellation of the Peak Cluster project in its entirety, or, at the very least, we demand that these pipelines find alternative routes to the Irish Sea; routes that do not sacrifice our residents, our land, and our wildlife. The Wirral does not produce the emissions these pipelines intend to carry. The whole purpose of Peak Cluster is ... view the full minutes text for item 58.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Council – 9 March 2026 Amendments to Motions on Notice
The Council is requested to consider the following amendments submitted in accordance with Standing Order 13.3.
MOTION 1. PEAK CLUSTER CARBON CAPTURE PIPELINE
Conservative Group Amendment
Proposed by Councillor Max Booth Seconded by Councillor Vida Wilson
Add additional recommendation 7 to the original motion:
7. Request all 66 councillors sign the following letter and task the Chief Executive with ensuring it is sent to the Secretary of State, and copied to Wirral’s four Members of Parliament, as soon as practically possible:
Wirral Council
PO Box 290 Brighton Street Rt. Hon Ed Miliband MP Wallasey Secretary of State for CH27 9FQ Energy Security and Net Zero Dept. for Energy Security and Net Zero www.wirral.gov.uk 55 Whitehall London Date: 09 March 2026 SW1A 2HP 55 Whitehall United Kingdom London SW1A 2HP United Kingdom Dear [name removed], Peak Cluster Carbon Capture Pipeline Further to an extraordinary meeting on Monday 9th March we the undersigned elected councillors are formally writing to you on behalf of the 320,000 residents of Wirral we represent, calling for the cancellation of the Peak Cluster project in its entirety. We are told this is “needed” and it is for the “national good” and that it is only a “temporary disruption”. But we live here. Do our views not count?
For the avoidance of any doubt, we are completely opposed to the construction and operation of this pipeline on the Wirral. This project represents a significant and unacceptable intrusion into protected Green Belt, threatens local environments, and risks permanently altering the character of our community.
The Green Belt exists to prevent urban encroachment, safeguard natural landscapes, and provide residents with access to open space. Allowing major industrial infrastructure to be installed within it fundamentally undermines these protections and this country’s first ever, unanimously agreed, Brownfield only Local Plan.
The landscape in this area is not simply open land — it is an established natural environment that supports wildlife, biodiversity, public enjoyment, and the rural character of the Wirral. Once heavy construction machinery, excavation works, access roads, and long-term easements are introduced, the damage cannot truly be undone.
While developers often promise land restoration, it is extremely unlikely that the soil structure, drainage patterns, habitats, mature vegetation, and overall ecological balance could ever be returned to their current condition. The lasting visual and environmental impact should not be underestimated, and this irreplaceable landscape must be protected.
We are also deeply concerned about the safety risks associated with CO₂ pipelines. Transporting pressurised carbon dioxide cannot be without danger. If a pipeline were to rupture or leak, the released gas could displace oxygen and create serious health hazards for people and animals, particularly in low-lying areas. Exposure to high concentrations can cause dizziness, unconsciousness, suffocation, and other acute medical effects. As CO₂ is heavier than air, it will not dissipate into the atmosphere but remain low like a marsh fog.
Real-world incidents demonstrate that these risks are not merely theoretical. In 2020, a CO₂ pipeline ruptured near Satartia, Mississippi in the United States, releasing a large cloud of gas that led to the evacuation of approximately 200 residents and resulted in dozens of people requiring hospital treatment.
More broadly, pipeline safety records have documented numerous CO₂ pipeline incidents over recent decades, many involving leaks or releases requiring emergency response. These examples highlight why communities are understandably concerned about having such infrastructure located close to homes, schools, and public spaces.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.