Policy and Resources Committee, Wednesday 11 March 2026

Compliance within the Corporate Estate

Noted Committee 2 papers

AI summaryWirral Council's Policy and Resources Committee has noted a report on compliance failings across the corporate estate, including 1,103 outstanding building actions and £4.3m of non-compliant procurement. A £1m revenue budget will support the Corporate Landlord Model, with a progress review in six months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee to receive progress report within 6 months
Money£1mrevenue sum for asset management service and Corporate Landlord Model
What happens next6 monthsprogress report back to this committee
Who it affectsCouncil buildings, workforce, publicusers of the corporate estate and services delivered from it

What was decided

The committee noted the report's content and the actions set out to address non-compliance across the corporate estate. Report P1, 1.1

The committee noted the proposed revenue budget to be allocated to the action plan as part of the council's budget setting. Report P1, 4.1

A report on progress against the action plan will be brought back to the committee within six months. Report P1, 3.29

Why

Non-compliance has been identified within the estate and needs to be addressed to protect the council's interests, its workforce and the public. Report 1.1

Additional workforce and resources are needed to react to the issues identified and build on work already in progress. Report 1.2

Adopting an action plan allows the necessary actions to be taken and monitored, providing assurance that matters have been resolved. Report 1.4

What happens next

A progress report on the action plan will be brought back to the committee within six months. Report 3.29

Corporate Landlord Model onboarding continues, with the team now working on Neighbourhoods assets after Adult and Children's services. Report 3.6

Estates Transformation continues, with Hamilton and Conway Buildings being released from back office use. Report 3.15

The money

  • £1m revenue sum identified to support growth of the asset management service and ongoing implementation of the Corporate Landlord Model Report 4.1
  • £4.3m total value of 44 projects for works and professional services commissioned without a compliant procurement process from July 2024 Report 3.19

Options considered

  • Rejected: Do nothing. Not feasible, as the council would have to accept the repair and compliance issues found Report 2.1
  • Rejected: Do everything now. Resources are not available to deliver all changes immediately and the approach would not produce the best long-term result Report 2.2
  • Rejected: Cease operating assets (in whole or part). The council needs physical assets to deliver services, though reducing and consolidating assets should form part of the longer-term solution Report 2.3

Implications

  • Financial: Resources for the asset portfolio are misaligned or insufficient; a £1m revenue sum is proposed for the action plan; estate is one of the council's highest areas of expenditure. Report 4.1, 4.2
  • Legal: The Monitoring Officer may need to consider exercising duties under section 5 of the Local Government and Housing Act 1989 if the action plan does not produce a satisfactory outcome. Report 5.2, 5.3
  • Risk: Health and safety non-compliance and procurement breaches present risk to the council; mitigations are underway but further work is needed. Report 7.1
  • Staffing: There are insufficient resources to maintain the current estate size, and gaps in skills, qualifications and experience have been identified. Report 3.13, 6.1
  • Legal: Land and property owners and occupiers have duties to ensure premises are safe for building users, including managing fire, electrical, gas, asbestos and water safety. Report 5.1
  • Climate: Public Sector Decarbonisation Scheme funding has been secured for some assets and the approach should help reduce the council's carbon footprint. Report 10.1
  • Other: A well-managed estate reduces the risk of anti-social behaviour, vandalism and theft. Report 12.1
  • Other: Improvements in the built environment should have positive effects for council services and the community served. Report 11.1

Who and where

  • Council workforce, service users, visitors and tenants using council buildings Report 1.1, 3.5, 5.1
  • The council as landowner and employer, with a portfolio of operational assets it cannot currently afford Report 3.2, 3.1
  • Directorates and services occupying council assets, including Leisure Centres and nine PFI schools Report 3.11, 3.16
  • Wirral residents receiving services delivered from the council's estate Report 2.3
  • Suppliers and contractors working on the council's estate, including minor works providers and the PFI contractor Report 3.16, 3.22

Timeline

  • circa 20 years: Period over which deep-seated factors, including fiscal challenges and distributed asset management, have built up Report 3.1
  • 2023/24: Need to introduce the Corporate Landlord Model was identified Report 3.1
  • From July 2024: 44 projects were commissioned without following a compliant procurement process, totalling £4.3m Report 3.19
  • last 12 months: CLM implementation, Estates Transformation and regulator inspections have revealed issues in the portfolio Report 3.3
  • prior to 24 February 2025: Public Contracts Regulations 2015 applied to procured projects Report 3.19
  • 2026/27: A different approach to PFI summer works is being adopted Report 3.16
  • in advance of 26/27: Structural changes to the leadership and oversight of capital delivery are contemplated by the Interim Chief Executive Report 3.20
  • in six years time: The nine PFI schools will be returned to the council Report 3.16
  • within 6 months: A progress report on the action plan will be brought back to this committee Report 3.29

Plain English for the jargon

  • Corporate Landlord Model (CLM): The council's approach of managing land and property centrally, replacing a previous portfolio-based model of distributed management.
  • PFI: Private Finance Initiative, the funding arrangement for nine schools operated by the council.
  • CDM: Construction Design and Management Regulations 2015, governing health and safety on construction work.
  • BaU: Business as usual, the routine day-to-day work of maintaining and operating the estate.
  • ASB: Anti-social behaviour.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item123

Resolved

Resolved – that, 1. the content and actions set out in the report be noted 2. the revenue budget proposed to be allocated to the action plan as part of the Council’s budget setting plan be noted; and 3. that a report on progress against the action plan will be brought back to this Committee within 6 months.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendation

The Policy and Resources Committee is requested to note: 1. the content and actions set out in the report; 2. the revenue budget proposed to be allocated to the action plan as part of the Council’s budget setting plan; and 3. that a report on progress against the action plan will be brought back to this Committee within 6 months SUPPORTING INFORMATION

Reasons for recommendation

1.1Non-compliance has been identified within the estate and this needs to be addressed. The Council needs to act to protect its interests, its workforce and the public. Setting aside the financial, legislative and commercial reasons for addressing this matter, it is the right thing to do.

1.2Additional workforce and resources will allow the Council to react to the various issues set out in this report and build on the work already in progress.

1.3A number of actions have been identified as part of the audit work within this report and taking those actions will improve the way the Council operates.

1.4Adopting an action plan will allow the actions needed to be taken and monitored to provide assurance that matters have been resolved.

1.5Adopting the approach set out in this report is aligned to the Council’s Asset Strategy and are in large part a consequence of having a better understanding of the Council’s assets and the way it should be managed.

1.6A streamlined, well managed estate will also mitigate financial risks associated with non-compliance, such as unplanned remedial works or enforcement action.

2.0OTHER OPTIONS CONSIDERED

2.1The do-nothing option is not feasible. Taking this approach would mean that the Council would have to accept the issues, both repair and compliance, that it has found and choose not to take the steps needed to address them.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Action Plan: Compliance within the Corporate EstateAppendix 1 90 KB Download
PDF
Compliance within the Corporate EstateReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

22 of 22 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, present
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, apologies, sent representative
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, apologies, sent representative
MS
Councillor Mark SkillicornCommittee Member, present

All 22 on the meeting page

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies