AI summaryWirral Council's Policy and Resources Committee has noted a report on compliance failings across the corporate estate, including 1,103 outstanding building actions and £4.3m of non-compliant procurement. A £1m revenue budget will support the Corporate Landlord Model, with a progress review in six months.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee to receive progress report within 6 months
Money£1mrevenue sum for asset management service and Corporate Landlord Model
What happens next6 monthsprogress report back to this committee
Who it affectsCouncil buildings, workforce, publicusers of the corporate estate and services delivered from it
What was decided
The committee noted the report's content and the actions set out to address non-compliance across the corporate estate. Report P1, 1.1
The committee noted the proposed revenue budget to be allocated to the action plan as part of the council's budget setting. Report P1, 4.1
A report on progress against the action plan will be brought back to the committee within six months. Report P1, 3.29
Why
Non-compliance has been identified within the estate and needs to be addressed to protect the council's interests, its workforce and the public. Report 1.1
Additional workforce and resources are needed to react to the issues identified and build on work already in progress. Report 1.2
Adopting an action plan allows the necessary actions to be taken and monitored, providing assurance that matters have been resolved. Report 1.4
What happens next
A progress report on the action plan will be brought back to the committee within six months. Report 3.29
Corporate Landlord Model onboarding continues, with the team now working on Neighbourhoods assets after Adult and Children's services. Report 3.6
Estates Transformation continues, with Hamilton and Conway Buildings being released from back office use. Report 3.15
The money
£1m revenue sum identified to support growth of the asset management service and ongoing implementation of the Corporate Landlord Model Report 4.1
£4.3m total value of 44 projects for works and professional services commissioned without a compliant procurement process from July 2024 Report 3.19
Options considered
Rejected: Do nothing. Not feasible, as the council would have to accept the repair and compliance issues found Report 2.1
Rejected: Do everything now. Resources are not available to deliver all changes immediately and the approach would not produce the best long-term result Report 2.2
Rejected: Cease operating assets (in whole or part). The council needs physical assets to deliver services, though reducing and consolidating assets should form part of the longer-term solution Report 2.3
Implications
Financial: Resources for the asset portfolio are misaligned or insufficient; a £1m revenue sum is proposed for the action plan; estate is one of the council's highest areas of expenditure. Report 4.1, 4.2
Legal: The Monitoring Officer may need to consider exercising duties under section 5 of the Local Government and Housing Act 1989 if the action plan does not produce a satisfactory outcome. Report 5.2, 5.3
Risk: Health and safety non-compliance and procurement breaches present risk to the council; mitigations are underway but further work is needed. Report 7.1
Staffing: There are insufficient resources to maintain the current estate size, and gaps in skills, qualifications and experience have been identified. Report 3.13, 6.1
Legal: Land and property owners and occupiers have duties to ensure premises are safe for building users, including managing fire, electrical, gas, asbestos and water safety. Report 5.1
Climate: Public Sector Decarbonisation Scheme funding has been secured for some assets and the approach should help reduce the council's carbon footprint. Report 10.1
Other: A well-managed estate reduces the risk of anti-social behaviour, vandalism and theft. Report 12.1
Other: Improvements in the built environment should have positive effects for council services and the community served. Report 11.1
Who and where
Council workforce, service users, visitors and tenants using council buildings Report 1.1, 3.5, 5.1
The council as landowner and employer, with a portfolio of operational assets it cannot currently afford Report 3.2, 3.1
Directorates and services occupying council assets, including Leisure Centres and nine PFI schools Report 3.11, 3.16
Wirral residents receiving services delivered from the council's estate Report 2.3
Suppliers and contractors working on the council's estate, including minor works providers and the PFI contractor Report 3.16, 3.22
Timeline
circa 20 years: Period over which deep-seated factors, including fiscal challenges and distributed asset management, have built up Report 3.1
2023/24: Need to introduce the Corporate Landlord Model was identified Report 3.1
From July 2024: 44 projects were commissioned without following a compliant procurement process, totalling £4.3m Report 3.19
last 12 months: CLM implementation, Estates Transformation and regulator inspections have revealed issues in the portfolio Report 3.3
prior to 24 February 2025: Public Contracts Regulations 2015 applied to procured projects Report 3.19
2026/27: A different approach to PFI summer works is being adopted Report 3.16
in advance of 26/27: Structural changes to the leadership and oversight of capital delivery are contemplated by the Interim Chief Executive Report 3.20
in six years time: The nine PFI schools will be returned to the council Report 3.16
within 6 months: A progress report on the action plan will be brought back to this committee Report 3.29
Plain English for the jargon
Corporate Landlord Model (CLM): The council's approach of managing land and property centrally, replacing a previous portfolio-based model of distributed management.
PFI: Private Finance Initiative, the funding arrangement for nine schools operated by the council.
CDM: Construction Design and Management Regulations 2015, governing health and safety on construction work.
BaU: Business as usual, the routine day-to-day work of maintaining and operating the estate.
ASB: Anti-social behaviour.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item123
Resolved
Resolved – that, 1. the content and actions set out in the report be noted 2. the revenue budget proposed to be allocated to the action plan as part of the Council’s budget setting plan be noted; and 3. that a report on progress against the action plan will be brought back to this Committee within 6 months.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to note: 1. the content and actions set out in the report; 2. the revenue budget proposed to be allocated to the action plan as part of the Council’s budget setting plan; and 3. that a report on progress against the action plan will be brought back to this Committee within 6 months SUPPORTING INFORMATION
Reasons for recommendation
1.1Non-compliance has been identified within the estate and this needs to be addressed. The Council needs to act to protect its interests, its workforce and the public. Setting aside the financial, legislative and commercial reasons for addressing this matter, it is the right thing to do.
1.2Additional workforce and resources will allow the Council to react to the various issues set out in this report and build on the work already in progress.
1.3A number of actions have been identified as part of the audit work within this report and taking those actions will improve the way the Council operates.
1.4Adopting an action plan will allow the actions needed to be taken and monitored to provide assurance that matters have been resolved.
1.5Adopting the approach set out in this report is aligned to the Council’s Asset Strategy and are in large part a consequence of having a better understanding of the Council’s assets and the way it should be managed.
1.6A streamlined, well managed estate will also mitigate financial risks associated with non-compliance, such as unplanned remedial works or enforcement action.
2.0OTHER OPTIONS CONSIDERED
2.1The do-nothing option is not feasible. Taking this approach would mean that the Council would have to accept the issues, both repair and compliance, that it has found and choose not to take the steps needed to address them.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.