Wirral Borough Council

2025/26 Budget Monitoring for Quarter Three (the period to 31 December 2025)

Noted Committee 1 paper

AI summaryWirral's Children, Young People and Education Committee noted a forecast overspend of £0.049m for 2025/26 at Quarter 3, with 89% of its £7.657m savings target on track. Council-wide projected overspend is £7.276m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFive items noted including £0.049m adverse variance
Money£0.049m adverse variance (committee)Against £108.904m net revenue budget
What happens nextQuarter 4 monitoringBi-monthly Directorate Budget Challenge Sessions continue
Who it affectsChildren, Young People and Education servicesIncluding social care, schools, and SEND

What was decided

The committee noted the forecast adverse position of £0.049m presented at Quarter 3. Report P2

The committee noted the progress on delivery of the 2025/26 savings programme at Quarter 3, with £6.778m (89%) of the £7.657m target on track. Report 3.36

The committee noted the forecast level of reserves and balances, budget virements, and the capital position at the end of Quarter 3. Report 3.30, 3.40

Why

Regular monitoring and reporting of revenue budgets and savings enables timely decisions, improves financial control, and supports the Council's statutory duty to set a balanced budget. Report 1.1, 5.1, 5.2

Ongoing review of reserves and balances maintains a sustainable financial position and supports effective risk management aligned with strategic priorities. Report 1.2

An Equality Impact Assessment approach and community wealth considerations have been applied where relevant, with no further equality or staffing implications identified at this stage. Report 6.1, 9.2

What happens next

Officers will continue proactive steps to stabilise the financial position, including spending controls, smarter ways of working, and delivering agreed savings. Report 3.19

Bi-monthly Directorate Budget Challenge Sessions will continue, and the Budget Oversight Panel will provide regular informal financial oversight between formal reports.

Any committee unable to fully mitigate an overspend must report to the Policy and Resources Committee, which holds ultimate responsibility for a whole-council balanced position. Report 3.23, 3.26

The money

  • £0.049m Forecast adverse variance for Children, Young People and Education Committee at Q3 Report P2, 3.7
  • £108.904m Committee's revised net revenue budget for 2025/26 Report 3.7
  • £444.72m Council-wide net revenue budget for 2025/26 Report 3.1
  • £25.446m Approved savings as part of 2025/26 budget Report 3.1
  • £7.276m Full Council projected adverse variance at Q3 after use of contingency Report 3.3, 4.2
  • £2.390m Children's Social Care forecast favourable variance Report 3.8
  • £1.705m Education Core forecast adverse variance Report 3.10
  • £0.789m SEND Statutory Services forecast adverse variance Report 3.11
  • £7.657m Total directorate savings target for 2025/26 Report 3.36
  • £6.778m Savings on track to be achieved (89% of target) Report 3.36
  • £0.712m Additional savings expected through identified mitigations Report 3.36
  • £3.219m Opening earmarked reserves on 1 April 2025 Report 3.38
  • £1.617m Forecast closing earmarked reserves at year-end 2025/26 Report 3.39
  • £7.5m Potential Government Exceptional Financial Support available Report 3.17
  • £13.18m General fund balances available Report 3.17

Options considered

  • Rejected: Maximising the use of capital receipts to finance transformational revenue expenditure (£2.6m already included). Already partially used but not adopted as primary option Report 3.17
  • Rejected: Reallocation of earmarked reserves. Held as backstop option Report 3.17
  • Rejected: Delaying the planned £3.562m contribution to General Fund Balances. Held as backstop option Report 3.17
  • Rejected: Use of potential Government Exceptional Financial Support of £7.5m. Held as backstop option Report 3.17
  • Rejected: Use of general fund balances (£13.18m available). Held as backstop option Report 3.17

Implications

  • Financial: Full Council-level projected overspend of £7.276m after use of contingency, driven primarily by social care pressures; Council-wide position improved by around £3m since Q2 due to higher Business Rates Section 31 grants. Report 3.3, 4.2
  • Legal: The Council must set a balanced budget under the Local Government Finance Act 1992 and Local Government Act 2003; failure would require the Section 151 Officer to issue a Section 114 notice. Report 3.12, 5.1, 7.2
  • Risk: Delivery of the 2025/26 budget is subject to ongoing variables; £0.167m of employee-related savings are not expected to be realised this year due to timing of implementation. Report 7.1
  • Staffing: An early voluntary retirement programme is underway, with future phases aligned to change portfolios to achieve workforce reductions. Report 3.16
  • Equalities: No further equality implications identified at this stage; any arising from further proposals will be addressed in business cases. Report 9.2
  • Climate: No direct environmental implications; due regard given in procurement and expenditure decisions. Report 10.1
  • Other: Earmarked reserves forecast to close at £1.617m, of which £1.552m is ringfenced, £0.014m non-ringfenced but committed, and £0.051m earmarked but not ringfenced. Report 3.39

Who and where

  • Children looked after in residential placements (assumed 80 in budget; actual numbers below budget level) Report 3.8
  • Children and young people with Education, Health and Care Plans (EHCPs) requiring transport support, with 13% demand increase Report 3.10
  • Schools receiving home-to-school and assisted travel services Report 3.10
  • SEND service users and families, given rising EHCP demand Report 3.11
  • Schools receiving capital investment for condition works and SEND resourced provision Report 3.42

Timeline

  • 3 March 2025: Full Council agreed 2025/26 net revenue budget of £444.72m Report 3.1
  • 17 December 2025: Bank of England reduced Bank Rate by 0.25 percentage points to 3.75% Report 3.4
  • 31 December 2025: End of Quarter 3 reporting period
  • 2025/26: Capital investment at Lingham, Mount and Raeburn Primary Schools to commence in New Year
  • Next 12 months: Capital investment planned at Wirral Hospital School, Foxfield and Stanley School Report 3.42
  • 2026/27: Full year effect of £0.167m employee-related savings to be achieved

Plain English for the jargon

  • Section 114 notice: A formal notice issued by a council's Section 151 Officer under the Local Government Act 1988 when the council cannot balance its budget.
  • EHCP: Education, Health and Care Plan, a legal document outlining support for children and young people with special educational needs and disabilities.
  • BOP: Budget Oversight Panel, an informal forum for Members to engage with Directors on financial performance between formal quarterly reports.
  • Section 31 grant: Government grant compensating local authorities for changes to business rates income.
  • CLM: Corporate Landlord Model, a council approach to centralise management of land and property assets.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item89

Resolved

Resolved – That: 1. the forecast adverse position of £0.049m presented at Quarter 3 be noted; 2. the progress on delivery of the 2025/26 savings programme at Quarter 3 be noted; 3. the forecast level of reserves and balances at Quarter 3 be noted; 4. the budget virements, as detailed in paragraph 3.30 of this report be noted; and 5. the capital position as at the end of Quarter 3 be noted.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Children Young People and Education Committee

Recommendations

The Children, Young People and Education Committee is recommended to note:

1. the forecast adverse position of £0.049m presented at Quarter 3; and 2. the progress on delivery of the 2025/26 savings programme at Quarter 3. 3. the forecast level of reserves and balances at Quarter 3, 4. the budget virements, as detailed in paragraph 3.30 of this report. 5. the capital position as at the end of Quarter 3. SUPPORTING INFORMATION

Reasons for recommendations

1.1Regular monitoring and reporting of the revenue budgets and savings achievements enables decisions to be taken in a timely manner, which may produce revenue benefits and will improve financial control of the Council.

1.2In addition, ongoing review of reserves and balances ensures that the Council maintains a sustainable financial position, supports effective risk management, and aligns resources with strategic priorities.

2.0OTHER OPTIONS CONSIDERED

2.1The Policy & Resources Committee has previously determined the budget monitoring process, as part of the Budget Recovery Action Plan presented to the Committee on 17 March 2025. Subsequently the report was presented to Children, Young People and Education Committee on 18 June 2025 and this report details the agreed course of action.

2.2In striving to manage budgets, available options have been evaluated to maintain a balance between service delivery and a balanced budget.

3.0BACKGROUND INFORMATION

3.1At the meeting on 3 March 2025, the Council agreed a net revenue budget for 2025/2026 of £444.72m to be met by government grants, council tax, business rates and flexible use of capital receipts. This budget includes approved savings of £25.446m as part of the Council’s ongoing efforts to ensure financial sustainability.

3.2At the end of Quarter 1, an adverse forecast of £6.445m was reported, primarily driven by rising social care demand. By Quarter 2, this position had further deteriorated to £10.538m, reflecting continued pressures from social care costs, assisted travel, and housing benefit subsidy loss.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Budget Monitoring for Quarter Three (the period to 31 December 2025)Report 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
SB
Councillor Stephen BennettChair, present
CC
Councillor Chris CarubiaVice-Chair, present
VW
Councillor Vida WilsonSpokesperson, apologies, sent representative
JG
Councillor Judith GrierSpokesperson, present
PJ
Councillor Paul JobsonCommittee Member, present
TL
Councillor Tom LaingCommittee Member, apologies, sent representative
TM
Councillor Tony MurphyCommittee Member, present
CB
Councillor Colin BaldwinCommittee Member, present
CC
Councillor Christopher CookeCommittee Member, present
AO
Councillor Amanda OnwuemeneCommittee Member, present
RP
Councillor Richie PittCommittee Member, absent
CP
Chris PennCo-Optee, expected

All 14 on the meeting page

On this subject at Wirral

Search all
  1. 2025/26 Budget Monitoring for Quarter Three (the period to 31 December 2025)This decision
  2. 2026/27 Revenue Budget Monitoring for Quarter One (The Period to 30 June 2026)Noted
  3. Q1 budget monitoring reportDecided
  4. 2026/27 Budget Monitoring for Quarter One (the period to 30 June 2026)Agreed
  5. 2026-27 budget monitoring report quarter 1Decided
  6. 2026/27 budget and budget monitoring processesAgreed

More from Wirral Children Young People and Education Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Retender of the Family Time ServiceResolved – That 1. A direct award to Active 8 Support Services Ltd (Company Number 05680237) for the provision of Fam... Approved Open
15 Jul 2026 Work ProgrammeResolved – That the proposed Children, Young People and Education Committee work programme for the remainder of the 2... Noted Open
17 Jun 2026 The Children's Plan 2026-2028Resolved – that the development and content of the 2026-2027 Children’s Plan be noted . Noted Open
17 Jun 2026 2026/27 Budget and Budget Monitoring ProcessesResolved – that 1. The principles outlined in this report regarding the approach to budget management and budget sett... Noted Open
17 Jun 2026 Domestic Abuse Annual Report and Domestic Abuse StrategyResolved – That 1. The Domestic Abuse Annual Update be noted; and 2. The Domestic Abuse Strategy for Wirral Domestic ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies