REVIEW OF THE STATUTORY WIRRAL BROWNFIELD LAND REGISTER
ApprovedPlanning7 papers
AI summaryWirral Planning Committee has approved updated Brownfield Land Registers for 2023, 2024 and April 2025, and delegated authority for future Part 1 annual updates to the Assistant Director Chief Planner.
Written from the decision and the officer reportPDF Pro
OutcomeApproved2023, 2024 and April 2025 versions, plus delegated authority
MoneyNew burdens grant usedPaid in 2017-18 and 2018-19, no longer available
What happens nextPublish on council websiteAnd upload to national Ministry of Housing register
Who it affectsBrownfield sites in WirralPart 1 sites only, no planning permission granted
What was decided
Planning Committee approved the Brownfield Land Registers and site plans for 2023, 2024 and the updated register at April 2025, to be published on the council website and uploaded to the national brownfield land register on the Ministry of Housing, Communities and Local Government website.
Delegated authority was granted to the Assistant Director Chief Planner, in consultation with the Chair and party Spokespersons of the Committee, to publish future annual updates where changes relate to Part 1 of the register only.
Why
The Council is required to maintain a statutory Brownfield Land Register under the Town and Country Planning Brownfield Land Register Regulations 2017, made under Section 151 of the Housing and Planning Act 2016. Report 5.1, 5.2
The sites put forward for inclusion have already obtained planning permission, are subject to a current planning application, or are identified as suitable for residential development in the Wirral Local Plan, an associated Neighbourhood Framework or a Masterplan. Report 7.3
The Part 1 register does not require Strategic Environmental Assessment because inclusion does not allocate land or grant permission, and the register mostly contains sites with planning permission or Local Plan allocation. Report 5.7
What happens next
The 2023, 2024 and April 2025 registers, with site plans and mapping, are to be published on the council website and uploaded to the national register on the Ministry of Housing, Communities and Local Government website.
Future annual Part 1 updates will be published by the Assistant Director Chief Planner under delegated authority, in consultation with the Chair and party Spokespersons of the Committee.
The money
new burdens grant payments in 2017-18 and 2018-19 Used in preparation of the Brownfield Land Register, no longer available Report 4.1
Options considered
Chosen: Include sites in Part 1 of the register only. No statutory consultation required and no planning permission granted, meeting the basis on which the register has been prepared to date Report 5.7, 8.1, 8.2
Rejected: Include sites in Part 2 of the register (permission in principle). No current proposal to include sites in Part 2; would require additional statutory publicity, consultation and environmental assessment work Report 4.3, 8.3
Implications
Financial: No fee is payable to the Council for entering a site in either Part of the Register, but a planning fee would be payable for any later technical details consent application after a Part 2 entry. Report 4.2
Financial: Land value of Part 2 sites could rise because the risk to developers is reduced by the grant of permission in principle for a fixed range in the number of dwellings. Report 4.4
Legal: The register must comply with the Town and Country Planning Brownfield Land Register Regulations 2017, the Government Brownfield Land Registers Data Standard published on 17 October 2025, and Section 14A of the Planning and Compulsory Purchase Act 2014. Report 5.1, 5.4, 5.5
Equalities: Part 1 amendments are unlikely to have significant equality implications; Part 2 entries could depending on location, nature, scale and impact. Brownfield sites are more likely to be in deprived areas, where the register may help stimulate development. Report 9.3
Climate: Re-use of brownfield sites in accessible, sustainable locations instead of greenfield land can have a more positive impact on climate change, and Biodiversity Net Gain requirements may apply on individual sites. Report 10.1
Risk: Inclusion in Part 1 does not grant permission and development may still not be delivered, particularly on challenging sites; the same risk applies to Part 2 even though permission in principle reduces some uncertainty. Report 7.1, 7.2
Staffing: Preparation, maintenance and review of the register is done with existing staff in the Strategic Planning Team within the Regeneration and Place Directorate; Part 2 entries and future technical details consent applications would add to existing Development Management workload. Report 6.1, 6.2
Other: No crime and disorder implications arise directly from the report. Report 12.1
Who and where
Developers and landowners of brownfield sites in Wirral Report 4.4, 7.1, 7.2
Residents and local communities, particularly in deprived areas where brownfield sites are more likely to be located Report 9.3, 11.1
The Strategic Planning Team and Development Management staff in the Regeneration and Place Directorate Report 6.1, 6.2
Timeline
December 2017: Wirral Brownfield Land Register first published Report 10.2
16 March 2023: Last Planning Committee review of the statutory Brownfield Land Register (Item 133) Report P40
1 April 2025: Town and Country Planning Fees in force Report P37
2017-18 and 2018-19: New burdens grant payments received for preparation of the register Report 4.1
17 October 2025: Government Brownfield Land Registers Data Standard updated Report 5.4
16 April 2026: Planning Committee approves the 2023, 2024 and April 2025 Brownfield Land Registers and delegates future Part 1 updates
Plain English for the jargon
Brownfield land: Previously developed land available for new building, as defined in the Regulations
Part 1 of the register: List of brownfield sites considered suitable, available and achievable for residential development; inclusion does not grant planning permission
Part 2 of the register: Sites granted permission in principle for residential development after statutory publicity, consultation and notification
Permission in principle: Consent in principle for residential development for a fixed range in the number of dwellings, with technical details consent required later
Strategic Environmental Assessment: Assessment process for plans and programmes likely to have significant environmental effects, here considered not required for the Part 1 register
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42
Resolved
Resolved (unanimously) – That Planning Committee approves: 1. The Brownfield land Registers and associated site plans for 2023 (Appendix 1 and 1a), 2024 (Appendix 2 and 2a) and the updated Brownfield Land Register at April 2025, as set out in Appendix 3 and 3a to this report, and their associated mapping, are published on the Council’s website and uploaded to the national brownfield land register on the Ministry of Housing, Communities and Local Government website. 2. Delegated authority be granted to the Assistant Director Chief Planner (in consultation with the Chair and party Spokespersons of this Committee) to publish future annual updates to the Brownfield Land Register where changes relate to Part 1 of the register only.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
REVIEW OF THE STATUTORY WIRRAL REPORT TITLE: BROWNFIELD LAND REGISTER
REPORT OF: ASSISTANT DIRECTOR CHIEF PLANNER
REPORT SUMMARY
The Town and Country Planning Brownfield Land Register Regulations 2017 require the Council to prepare, maintain and publish a statutory register of previously developed brownfield land within Wirral. This is known as the Brownfield Land Register.
The Register is in two parts. Part 1 of the Register is to include land with an area of at least 0.25 hectares or capable of supporting 5 or more dwellings, which is suitable, available and achievable for new housing development. Part 2 of the Register can include sites taken from Part 1 where permission in principle would be granted by the Town and Country Planning Permission in Principle Order 2017 for a range of dwellings to be specified by the Council, subject to the further submission and approval of technical details consent.
The Council first prepared its Brownfield Land Register in 2017, and this was published in December 2017. The Council is required to review the Register annually. The last review, for April 2022, was reported to Planning Committee on 16 March 2023. Annual position statements for April 2023, April 2024 and April 2025 are now attached to this report. Publication of the Registers for 2023 and 2024 was delayed due to work on progressing the Wirral Local Plan to Adoption
The amended Register at April 2023, would have contained 141 sites with a potential minimum capacity of 11,507 dwellings. The amended Register at April 2024, would have contained 135 sites with a potential minimum capacity of 8,577 dwellings. The amended Register as at April 2025 now contains 148 sites with a potential capacity of 9,305 dwellings.
There is no proposal to include sites in Part 2 of the Register and to grant permission in principle for any development on these sites. This report recommends that delegated authority be granted to the Assistant Director Chief Planner (in consultation with the Chair and party Spokespersons of this Committee) to publish future annual updates to the Brownfield Land Register where changes relate only to Part 1 of the register but any proposals to include sites in Part 2 would continue to be reported to Planning Committee.
The publication of the updated Register is consistent with the delivery of an efficient, effective and accessible Council, as set out in The Council Plan: Wirral Working Together 2023-27, and will particularly contribute towards Theme 4 - people focused regeneration and Theme 5 - protect our environment, by providing for the re- development of vacant and under-used previously developed brownfield land, in accessible locations at the heart of existing communities. RECOMMENDATIONS
Planning Committee is recommended to approve that:
1. The Brownfield land Registers and associated site plans for 2023 (Appendix 1 and 1a), 2024 (Appendix 2 and 2a) and the updated Brownfield Land Register at April 2025, as set out in Appendix 3 and 3a to this report, and their associated mapping, are published on the Council’s website and uploaded to the national brownfield land register on the Ministry of Housing, Communities and Local Government website.
2. Delegated authority be granted to the Assistant Director Chief Planner (in consultation with the Chair and party Spokespersons of this Committee) to publish future annual updates to the Brownfield Land Register where changes relate to Part 1 of the register only. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1The proposals within this report will enable the Council to comply with the legal and procedural requirements in the Town and Country Planning Brownfield Land Register Regulations 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.