AI summaryPolicy and Resources Committee noted Wirral's 2025/26 capital outturn of £74.986m against a revised £81.585m programme, with £17.080m deferred to 2026/27, and recommended Council approve £1.208m of virements and new bids.
Written from the decision and the officer reportPDF Pro
OutcomeNotedVirements and new bids recommended for approval
Money£74.986m capital spendFunded by £23.100m borrowing, £47.516m grants, £3.543m receipts
What happens nextCouncil to decide virements and bidsFull Council approval required
Who it affectsAll council directorates91 schemes delivered in 2025/26
What was decided
The Committee noted the total capital spend for 2025/26 of £74.986m. Report P2
The Committee noted the additional year-end net re-profiling of £17.080 million from 2025/26 to 2026/27. Report P2
The Committee noted the funding of capital expenditure in 2025/26, including £47.516m of grants and contributions, £3.543m of capital receipts and £23.100m of borrowing, and recommended that Council approve the virements in Appendix F and the bids in Appendix G. Report P2, 3.13
Why
To inform the Committee of the capital position for 2025/26 against the approved budget and to assure members that funding has been best allocated in line with the Council Plan. Report 1.1, 1.2
Regular monitoring and reporting of the Capital Programme enable faster decisions, which may produce revenue benefits and improve financial control. Report 1.3
Schemes have been reviewed and re-profiled to reduce borrowing costs in 2025/26 and delay the related Minimum Revenue Provision charges into future years. Report 3.3, 3.15
What happens next
Council is being recommended to approve the £1.208m of budget virements set out in Appendix F and the new bids in Appendix G. Report 3.13, P78
The £23.100m of new borrowing will trigger the first Minimum Revenue Provision repayment of £0.344m in 2026/27, bringing the total MRP charge to £9.074m that year. Report 3.6, 4.2
The Capital Programme will continue to be reviewed by the Corporate Change and Portfolio Board, with schemes facing inflationary or contractor insolvency risk reported as they arise. Report 3.11, 7.1
The money
£74.986m Total capital expenditure in 2025/26 across 91 schemes Report 3.4, P2
£17.080 million Net re-profiling of capital spend from 2025/26 into 2026/27 Report P2
£47.516 million Grants and contributions used to fund the 2025/26 Capital Programme Report P2, 3.14
£3.543 million Capital receipts used to fund the 2025/26 Capital Programme Report P2, 3.14
£23.100 million Borrowing used to finance the 2025/26 Capital Programme Report P2, 3.14, 4.2
£1.208 million Budget virements identified in Appendix F to be reallocated Report 3.13
£10.311 million Total capital receipts received in 2025/26, including £4.469m for debt repayment Report 3.17, P37
£4.795 million Balance on the Capital Receipts Reserve at 31 March 2026 Report 3.17, P37
£0.344 million First Minimum Revenue Provision repayment on 2025/26 borrowing, charged in 2026/27 Report 3.6
£9.074million Total Minimum Revenue Provision charge for 2026/27 on Capital Programme borrowing Report 3.6
£0.414 million Devolved Formula Capital passed directly to schools Report 3.5
£20.000m Exceptional Financial Support capitalisation direction approved for 2024/25 Report 3.23
£7.500m Exceptional Financial Support capitalisation direction approved for 2025/26, not drawn down Report 3.23
Options considered
Chosen: Quarterly reporting of the Capital Programme to Committee. Described as standard practice in the report Report 2.0, 2.1
Rejected: Other reporting frequencies. Not considered necessary as quarterly reporting is standard Report 2.1
Implications
Legal: The Council must set a balanced budget under the Local Government Finance Act 1992, and members must have regard to their fiduciary duty to council taxpayers when taking budget decisions. Report 5.1, 5.2, 5.3
Equalities: Members must consider the public sector equality duty alongside the fiduciary duty, and any decision is potentially open to challenge if the duty is disregarded. Report 9.1, 9.2
Climate: The Capital Programme includes projects that support the Council's Environment and Climate Emergency Action Plan, such as energy efficient buildings, sustainable travel infrastructure, street lighting, urban tree planting and coastal protection works. Report 10.1, 10.2
Risk: All projects carry delivery, third party and market risks including build cost inflation, and the Council may need to decide on additional funding or scheme viability if a contractor becomes insolvent. Report 3.11, 3.20, 3.21
Other: Some capital receipts are ringfenced for specific purposes such as educational schemes or IT programmes, and cannot be applied to general capital spend or to fund transformational projects. Report 3.17, P38
Other: Exceptional Financial Support of £7.500m was made available to the Council for 2025/26 but was not required to be drawn down this financial year. Report 3.23
Staffing: There are no direct staffing, IT or asset implications arising directly from the report. Report 6.0, 6.1
Who and where
All council directorates delivering the 91 capital schemes in 2025/26 Report 3.4, P18, P20
Schools receiving Devolved Formula Capital of £0.414m Report 3.5
Council taxpayers, given the members' fiduciary duty in budget decisions Report 5.2
Future revenue budgets, which will bear the Minimum Revenue Provision and interest costs of new borrowing Report 3.6, 4.2
Communities benefiting from regeneration projects within the Capital Programme Report 11.1
Timeline
19 February 2025: Policy and Resources Committee considered the Capital Programme 2025/26 Report 3.1
20 February 2025: Deputy Prime Minister minded to approve Exceptional Financial Support of £20.000m for 2024/25 and £7.500m for 2025/26 Report 3.23
3 March 2025: Council approved the Capital Programme 2025/26 Report 3.1, P87
23 February 2026: Quarter 3 capital monitoring report considered by this Committee Report 3.2
31 March 2026: End of the 2025/26 financial year, with a Capital Receipts Reserve balance of £4.795m Report 3.17, P37
2026/27: First Minimum Revenue Provision repayment of £0.344m on 2025/26 borrowing charged to revenue Report 3.6, 4.2
31 March 2030: Capital receipts flexibility for transformation of services currently extended to this date
2075/76: Modelled peak year for Minimum Revenue Provision repayments at £0.916m
Plain English for the jargon
Minimum Revenue Provision (MRP): The amount the Council must charge to its revenue budget each year to repay capital debt, calculated using the Annuity Method agreed in December 2016.
Capitalisation direction: Approval under Exceptional Financial Support that allows a council to meet revenue costs using capital resources.
Exceptional Financial Support (EFS): Support from the Ministry of Housing, Communities and Local Government for councils that cannot set a balanced budget, normally via a capitalisation direction.
Capital receipts: Proceeds from the sale of fixed assets, available to fund future capital investment, with some ringfenced for specific purposes.
Devolved Formula Capital: Direct funding delegated to schools to maintain their buildings and fund small scale capital projects.
Virement: Movement of budget from one scheme to another within the Capital Programme without changing the overall total.
Re-profiling: Moving budget and spending from one financial year to a later one, often to reflect revised scheme delivery timetables.
Section 106 (S106): Developer contributions towards infrastructure and services, listed alongside grants as a source of capital funding.
Annuity Method: Method of repaying debt where annual principal repayments start low and increase over time, reflecting the time value of money.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Resolved – That, 1 the total Capital spend for 2025/26 of £74.986m be noted. 2 the additional year-end net re-profiling of £17.080 million from 2025/26 to 2026/27 be noted. 3 the funding of capital expenditure in 2025/26 including the use of £47.516 million Grants and Contributions, £3.543 million capital receipts and £23.100 million of borrowing be noted. 4 That Council be recommended to approve; a. approval of the virements of budget referred to in Appendix F of this report, and b. the bids in Appendix G of this report
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to:
1 Note the total Capital spend for 2025/26 of £74.986m. 2 Note the additional year-end net re-profiling of £17.080 million from 2025/26 to 2026/27. 3 Note the funding of capital expenditure in 2025/26 including the use of £47.516 million Grants and Contributions, £3.543 million capital receipts and £23.100 million of borrowing. 4 Recommend to Council; a. approval of the virements of budget referred to in Appendix F of this report, and b. the bids in Appendix G of this report SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To inform the committee of the capital position for 2025/26 against the approved budget, revisions, including income and expenditure. To assure the committee that funding available has been best allocated in accordance with the Council Plan,
1.2To present to the committee the final outturn position for 2025/26
1.3Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control within Wirral Borough Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1The Capital Programme 2025/26 was considered by Policy and Resources Committee on 19th February 2025 and approved by Council on 3rd March 2025. It was highlighted that the Council’s revenue budget position limited scope for unsupported capital expenditure.
3.2This Committee receives regular updates in respect of capital monitoring throughout the year. The last monitoring report, for Quarter three, was considered by this Committee on 23rd February 2026. Since then, work has been on-going in order to conclude the accounts for the financial year.
3.3During the year the Capital Programme was regularly reviewed which resulted in schemes being deferred to future years along with the supporting funding. This resulted in reduced Treasury Management costs through a reduced need to borrow in 2025/26.
Capital Outturn
3.4The capital expenditure for the year was £74.986 million of spend, over 91 schemes during the year, compared to the revised programme of £81.585 million which was reported in February 2026 (Quarter 3). This is summarised in Table 1.
3.5The outturn also includes the Devolved Formula Capital of £0.414 million. This is direct funding delegated to schools to maintain their buildings and fund other small scale capital projects. Please see Appendix A Table 1.2.
3.6As a result of the £23.100 million borrowed to finance the Capital Programme in 2025/26, the General Fund will be charged with its first repayment via the Minimum Revenue Provision (MRP) in 2026/27 of £0.344 million. This will bring the total MRP charge for 2026/27 to £9.074million for borrowing associated with delivering the Capital Programme. Capital Programme 2025/26 Position by Directorate
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.