AI summaryWirral Schools Forum notes High Needs Funding Subgroup update, which reports a £55m deficit and sets out a SEND Reform Plan awaiting government response.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo further action required
Money£55m High Needs Block deficitAim to seek DfE debt write-off
What happens nextPlan scrutiny on 19 June 2026Submit to MHCLG committee for approval
Who it affectsChildren with EHCPs in WirralForecast 1,000 EHCPs by 2029

What was decided

The Forum noted the contents of the report covering High Needs Funding Subgroup work over the past six months. Report P1, P21

Why

The High Needs Block of the Dedicated Schools Grant has a deficit of around £55m, and the subgroup is overseeing the policy, banding and sufficiency work needed to address it. Report 2.1, P3, P4

Significant progress has been made on early intervention, inclusion, SaLT services and strategic planning, but specialist provision capacity, EHCP quality and financial sustainability remain under pressure.

What happens next

The HNF subgroup will scrutinise the DSG Management Plan on 19 June 2026 before it is submitted for approval at the committee of the Ministry for Housing, Communities and Local Government. Report 1.2

The Wirral Sufficiency Strategy 2026 to 2030 is on track for publication in July 2026, and the Eastway base is scheduled to close in September 2026. Report P9, P10

The money

  • circa £55m High Needs Block deficit Report 2.1

Options considered

  • Rejected: Continue and complete EHCP banding descriptor review and policy update. Implementation paused pending clarity on national SEND reforms Report 1.1, 1.6, 5.1

Implications

  • Financial: HNB deficit stands at circa £55m; DSG Management Plan and SEND Reform Programme aim to show sustainability and support a potential DfE debt write-off. Report 2.1
  • Legal: The local authority must manage its High Needs Block spend; the DSG Management Plan is not legally binding but should give confidence in the authority's ability to manage spending. Report P15
  • Staffing: More resource may be needed to implement the new SEND Reforms and meet the requirements of the new SEND Reform Plan. Report 4.0, 4.1
  • Risk: Not completing the new High Needs Funding policy review could lead to escalation of the HNB deficit. Report 5.1
  • Risk: Without a strategic approach to sufficiency, greater costs will be incurred in non-maintained independent and special schools, increasing HNB spend. Report 5.2

Who and where

  • Children and young people in Wirral with EHCPs, including 515 pupils in current year 7 (7.7% of cohort) Report P11
  • Mainstream and special schools across Wirral, including resourced provisions and inclusion bases Report P10, P11
  • Early Years SEND provision, affected by the scheduled Eastway base closure in September 2026 Report P10
  • Post-16 and post-19 learners, where post-19 provision remains a priority Report P10

Timeline

  • 2024: EHCP funding banding review completed and new descriptors drafted Report 1.1
  • Sept 2025: National recognition for SaLT work, including a No.10 visit Report P12
  • March 2026: UNICEF Baby Friendly Gold Award Report P12
  • 19th June 2026: HNF subgroup scheduled to scrutinise the DSG Management Plan Report 1.2
  • July 2026: Wirral Sufficiency Strategy 2026 to 2030 on track for publication
  • Sept 2026: Scheduled closure of Eastway base (Early Years) Report P10
  • 2029: EHCP numbers forecast to reach circa 1,000 Report 1.2

Plain English for the jargon

  • DSG: Dedicated Schools Grant, the main ring-fenced funding for schools
  • HNB: High Needs Block, the part of the DSG that funds SEND support
  • EHCP: Education, Health and Care Plan, a legal document setting out a child or young person's special educational needs
  • SEND: Special Educational Needs and Disabilities
  • SaLT: Speech and Language Therapy
  • SEMH: Social, Emotional and Mental Health (a category of SEND need)
  • ASC: Autistic Spectrum Condition
  • SLD: Severe Learning Difficulties
  • SLCN: Speech, Language and Communication Needs
  • NMISS: Non-Maintained Independent and Special Schools, used where local provision is insufficient
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item106

Resolved

Resolved – That the Forum notes the contents of the report.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Wirral Early Years and Schools Forum

Executive summary

To provide Schools Forum with a summary of key developments, workstreams, and impact relating to the High Needs Funding (HNF) Subgroup over the past six months.

1.0BACKGROUND INFORMATION

The HNF subgroup was established to provide strategic oversight and advice on the allocation and use of the High Needs Block (HNB) of the Dedicated Schools Grant (DSG) with responsibility for the following broad areas of work:

• Overseeing the development and implementation of a revised High Needs Funding Policy. • Monitoring the financial impact of proposed banding descriptors for Education, Health and Care Plans (EHCPs). • Consider the use and allocation of non-statutory funding. • Ensure the new SALT pathways have maximum financial impact. • Any other work directed by Schools’ Forum.

The breakdown below provides an overview of the progress in each of these areas.

1.1EHCP BANDING REVIEW A review of EHCP funding banding has been completed and new descriptors drafted (2024). Testing of these descriptors identified variable EHCP quality limits accurate funding allocation and banding descriptors may require simplification. The implementation has been paused pending clarity on national SEND reforms.

1.2DSG MANAGEMENT PLAN Key projections show that EHCP numbers are forecast to reach circa 1,000 by 2029. The DSG Management Plan aims to focus on addressing the High Needs Block (HNB) deficit. Its core approach focuses on strengthening early intervention and increasing mainstream inclusion. This is supported by a multi-strand governance

1 framework and DSG tracking and aims to reduce the number of children and young people requiring an education, health and care needs assessment. The DSG Plan aligns closely with the SEND Reform Plan. The HNF subgroup are scheduled to scrutinise the plan at a forthcoming meeting on 19th June 2026 before submitting for approval at the committee of the Ministry for Housing, Communities and Local Government. 1.3 SEND REFORM PLAN The SEND Reform Plan has been developed with SEND consultant Adam Boddison. It sets out the local authority’s plan for implementation of the new SEND reforms and how it will manage its deficit within the HNB. The Plan has been co-produced with stakeholders and approved by the Local SEND Partnership Board. It has been submitted to the DfE and the outcome is pending. 1.4 SUFFICIENCY OF SEND PROVISION Strategic Progress A Sufficiency Working Group has been established to oversee provision planning. Key outputs to date: o Mapping of current provision. o Cohort and demand analysis. o Development of a live SEND data suite (Power BI, JSNA). o Wirral Sufficiency Strategy 2026–2030 on track for publication (July 2026).

Key Sufficiency Pressures The mapping exercise highlighted both needs and phase-specific gaps as outlined below:

• SEMH: Capacity fully utilised (notably KS3–4). • ASC/SLD: Special schools and resourced provisions full. • ASC (Secondary): Limited local places → reliance on out-of-borough provision. • Early Years: Reduced capacity due to scheduled Eastway base closure (Sept 2026). • Primary: Limited flexibility in ASC/SLD bases. • Secondary: Increasing SEMH demand and insufficient specialist places. • Post-16: Expansion at Wirral Met positive; Post-19 provision remains a priority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
High Needs Funding Subgroup UpdateReport 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 33 attended
JW
Jane Whisker Academy RepresentativeChair, present
HB
Holly Barker Special HeadteacherVice-Chair, present
SR
Susan Ralph Primary Headteacher (Birkenhead North)Committee Member, present
MM
Michael Melin Primary Headteacher (Wallasey)Committee Member, present
CS
Catherine Sharky Primary Headteacher (Bebington/Bromborough)Committee Member, present
NG
Natalie Grimster Primary Headteacher (Deeside)Committee Member, present
LP
Lorrain Prescott Primary Headteacher (Birkenhead South)Committee Member, present
SA
Shaun Allen Primary GovernorCommittee Member, apologies
HC
Helen Collinson Primary GovenorCommittee Member, absent
PW
Paula Waring Special GovernorCommittee Member, present
AG
Andrea Gaunt Academy RepresentativeCommittee Member, absent
AS
Anne Sheridan Academy RepresentativeCommittee Member, present

All 33 on the meeting page

On this subject at Wirral

Search all
  1. High Needs Funding Subgroup UpdateThis decision
  2. High needs funding group reportNoted
  3. Terms of Reference for Newly Formed High Needs FundingAgreed
  4. Consultation on high needs Funding ArrangementsDecided
  5. Higher Needs Funding Model ReviewNoted
  6. Delivering Better Value Update and High needs Funding Arrangement Review ProposalNoted

More from Wirral Wirral Early Years and Schools Forum

All decisions
MeetingDecisionOutcome
16 Jun 2026 Minutes of the Meeting Held on 20 January 2026Resolved – That the minutes of the meeting held on 20 January 2026 be approved as an accurate record. Approved Open
16 Jun 2026 MyHappyMind Funding RequestResolved (unanimous) – That the Forum agrees to contribute funding from the High Needs Block to a joint commission to... Agreed Open
16 Jun 2026 Early years Working Group UpdateResolved (unanimous) – That the Wirral Early Years and Schools Forum notes the report and approves the recommendation... Approved Open
16 Jun 2026 School Balances UpdateResolved – That 1. The Forum notes the report, and; 2. Notes that Schools’ balances continue to be monitored. Decided Open
16 Jun 2026 Provisional Outturn 2025-26Resolved – That 1. the Forum notes the report and the financial position of the Schools Budget for 2025-26, subject t... Agreed Open