Resolved
RESOLVED That (i) the report and presentation be noted; and (ii) a further report be brought to a future meeting of the Committee.
Overview and Scrutiny Committee noted this item on Monday 22 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That (i) the report and presentation be noted; and (ii) a further report be brought to a future meeting of the Committee.
At its meeting on 24 July 2017, the Overview and Scrutiny Committee received a presentation from Thameswey Housing Limited (THL) which reviewed and detailed the outcomes of the Rayne’s Close Development and the performance of the pioneering energy-efficient technology installed within the properties. The purpose of the review was to highlight key areas of consideration for future development projects undertaken by Woking Borough Council.
Ian Lelliott of THL will attend the meeting of the Overview and Scrutiny Committee to provide an update on the position of the properties in Raynes Close. For the benefit of the Members of the Committee, the relevant extract from the minutes of the meeting held on 24 July 2017 is attached.
None
Reporting Person:
Ian Lelliot, Head of Residential Services, Thameswey Housing Ltd Email: [email removed]
Contact Person:
Frank Jeffrey, Democratic Services Manager Email: [email protected]
Date Published:
10 January 2018
REPORT ENDS
OSC18-002 1 Update on Rayne's Close
2 Update on Rayne's Close
Appendix 1
Extract From the Minutes of the Meeting of the Overview and Scrutiny Committee Held on 24 July 2017
1. LESSONS LEARNT FROM THE RAYNES CLOSE DEVELOPMENT
The Chairman welcomed Ian Lelliot from Thameswey Housing Limited and [name removed] and [name removed], residents of the Raynes Close development, to the meeting. [name removed] gave a detailed presentation which set out the background to the Raynes Close development and outlined the issues that had faced the residents in respect of the pioneering energy efficient technology installed, including a heat exchanger, rain water harvester and the heating. A report had been prepared to support the presentation.
[name removed] was invited to outline the main issues faced by the residents since the development had been completed in 2011, in particular the poor communication between Thameswey and the residents. Whilst it was clear that some of the equipment was not fit for purpose, little had been done by Thameswey to address the issues. Servicing was sporadic, often limited to a cursory inspection and only ever reactive rather than proactive, despite significant charges being raised with the residents. In the case of the property occupied by [name removed], both toilet mechanisms had been replaced five times, and a mains bypass had been installed because of problems with the rain water harvester.
Thameswey was aware of the issues but the service undertaken a week before had again been limited to a fifteen minute inspection. The water in the rain water harvester had now been stagnating for 18 months. [name removed] reported that, at a meeting in April 2017, Thameswey Housing Limited had offered to ‘gift’ the energy efficient technology to the residents. However, the residents did not consider the offer to be adequate in view of the problems faced by each property, and would result in the residents becoming responsible for any repairs. In advising the Committee of the issues, [name removed] referred to a list of problems which had been drawn up by the residents. It was agreed that the list would be circulated to the Members of the Committee.
The Members of the Committee were concerned with the issues raised and thanked both Ian Lelliot and [name removed] for the information they had provided. However, it was felt that, in view of the years of problems experienced by the residents, steps had to be taken to seek a resolution.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Supplementary Report: Update on Raynes CloseSupplementary | 265 KB | Download |
PDF |
Update on Raynes CloseReport | 63 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Mar 2024 | Matters Arising from the Previous Minutes OSC24-017Resolved That the report be noted. | Noted | Open |
| 18 Mar 2024 | Review of Council Meeting Structure OSC24-020RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Annual Review of Complaints - 2023 OSC24-012RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Ukspf osc24-021RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Brookwood Cemetery HS2 Task and Finish Group Report OSC24-022RESOLVED That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.