RESOLVED That (i) a provision of £1m be included in the project cost for Woking Town Centre Wayfinding, with implementation being subject to formal approval of detailed proposals by the Executive; (ii) a provision of £6m be included in the project cost for Lockfield Drive/Victoria Arch Pedestrian/Cycle Bridge, with implementation being subject to: (a) seeking at least partial grant funding to reduce Victoria Square Woking Limited’s contribution; (b) confirming the route proposed is the optimum solution; (c) formal approval of detailed proposals by the Executive; (iii) the Victoria Square Project Budget and Loan Facility be increased to £700m; and (iv) in order to achieve a final outcome as far below £700m as possible, Officers come back to the Victoria Square Oversight Panel and subsequently to Council with details of efficiency savings that can be made without compromising the quality of the final product.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
The Council at its meeting on 30 July 2022 received and approved a confidential recommendation from the Executive to provide additional resources in respect of the Victoria Square Development. The Council received and considered a report from Victoria Square Woking Limited that set out the likely outturn of cost for the Victoria Square development based on the impacts of additional delays to deliver caused, amongst other things, by the Covid lockdown and changed working arrangements necessitated by Covid.
The Council on the 30 July 2020 authorised a £30m increase in the project contingency, total project cost and loan facility.
This report results from extensive work establishing the likely final cost of the project and taking into account a range of activities the Council would normally have financed by the Council but due to the significant revenue impacts of Covid cannot prudently do so.
The report sets out the update on the Project Budget now sought, the optional items that are currently included and report by the Hawnby Group on the financial viability of this significant regeneration project.
Appendix 1 of the report provides some images of the new spaces being created by this regeneration project. The quality of these spaces and activities should positively support the Council as part of its “Post Covid” economic recovery.
Appendices 2 and 3 of the report provide Project Mandates for the two elements of the increased project cost that are optional, Woking Town Centre Wayfinding (£1m) and Lockfield Drive/Victoria Wat Pedestrian/Cycle Bridge (£6m).
The Council is request to approve an overall Project Budget and Loan Facility of £700m as set out in the report.
Recommendations
The Council is requested to:
RESOLVE That
(i) a provision of £1m be included in the project cost for Woking Town Centre Wayfinding, with implementation being subject to formal approval of detailed proposals by the Executive;
(ii) a provision of £6m be included in the project cost for Lockfield Drive/Victoria Arch Pedestrian/Cycle Bridge, with implementation being subject to formal approval of detailed proposals by the Executive; and
(iii) the Victoria Square Project Budget and Loan Facility be increased to £700m
EXE21-010 Victoria Square Update
Reasons for decision
Reason: To enable the successful completion of the Victoria Square regeneration project.
The Council has the authority to determine the recommendations set out above.
Background Papers: Confidential Report from W H Stephens for Victoria Square Woking Limited. – Not for publication but previously supplied to all Members of the Council
Date Published: 5 February 2021 Victoria Square Update
1.0Introduction
1.1The Victoria Square development is a major regeneration project within Woking Town Centre.
1.2The project has been adversely affected by the need to replace the Red Car Park; this delayed the project from a planned October 2020 completion until May 2021. The Deed of Variation with Sir Robert McAlpine incorporating the Red Car Park in the project was agreed on 14 November 2019.
1.3At the Victoria Square Oversight Panel (Panel) meeting on the 15 January the Panel was advised that there were delays in delivery of the project, particularly the new Red Car Park, and that the contingency was under pressure. Accordingly, it was advised that the adequacy of the contingency would be reviewed. Whilst this was underway, the COVID 19 crisis arose and has had a major impact on the progress of the project; the review was therefore extended to a potential for completion/opening being delayed from April/May 2021 until November/December 2021.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
ThamesWey Energy Limited (TEL) EXE26-078Resolved That following the acquisition of the shares of ThamesWey Limited in ThamesWey Energy Limited by the Council...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.