Resolved
RESOLVED That the Freedom Leisure Performance Review be noted.
Overview and Scrutiny Committee noted this item on Monday 22 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Freedom Leisure Performance Review be noted.
This report sets out the performance review of Freedom Leisure, including assessments on quality and performance management, KPIs and the priorities for year 2020/2021. Complaints, feedback and achievements are reviewed in the report as Freedom Leisure provide a wide range of services to the public.
The reporting period starts just after the first national lockdown, meaning that any comparisons to previous years are very difficult.
This report will assist in identifying the support that Freedom Leisure has received during the pandemic during this period and what they have done to minimise the impact of the pandemic.
The Committee is requested to:
RESOLVE That the content of this report be noted.
The Committee has the authority to determine the recommendation set out above.
Background Papers: None
Reporting Person: Steve May, Leisure Services Manager Email: [email protected], Extn: 3302
Contact Person: Steve May, Leisure Services Manager Email: [email protected], Extn: 3302
Portfolio Holder: Councillor Kemp Email: [email protected]
Shadow Portfolio Holder: Councillor Johnson Email: [email protected]
Date Published: 12 November 2021
OSC21-041 Freedom Leisure Performance Review Freedom Leisure Performance Review 1.0 Introduction
1.1The Leisure Partnership Agreement commenced on 1st December 2011. The Woking and Guildford partnerships were procured as part of a joint process that required a turnover threshold/scale of organisation that would have been challenging for Freedom Leisure to have met at the time on their own. Freedom Leisure therefore asked GLL to be the “principal” contractor, with Freedom Leisure delivering the contract, as a sub-contractor to them. The bid was written by Freedom Leisure who are fully responsible for its delivery. GLL receive an annual fee from Freedom Leisure for underwriting the original bid and holding the risk of Freedom Leisure failing to perform.
1.2Since the original agreement, the contract has had several major changes which include 3 new pavilions and the Sportsbox at Hoe Valley.
1.3The inclusion of Sportsbox also triggered the contract extension clause in the main contract which is for a further 4 years. Contract end is now 30th November 2025
1.4Separate to the contract, following an open tender process Freedom Leisure has also been successful in securing the contract to run the kiosk in Woking Park from Summer 2018.
1.5In September 2018, Woking Park Tennis Courts were removed from the Leisure Contract and returned to the management of Woking Borough Council. This was to allow a funding bid to improve the courts from the Lawn Tennis Association and for us to be included in the LTA led Club Spark community tennis programme.
1.6In February 2021 the Eastwood Leisure Centre was also added to the remaining contract.
2.0Priorities for 2020-2021
2.1Freedom Leisure in consultation with Officers and their customers set a list of key priorities for 2020-2021. These were presented to the Leisure Partnership Board at the end of 2019 and agreed by this Board. However due to the circumstance around COViD 19 these priorities could not be achieved and the whole landscape of the contract changed significantly.
3.0Performance during the 2020-2021
3.1What happened Time line Freedom Leisure Performance Review 3.2 Woking Borough Council took a cautious and pragmatic approach to the early stages of the pandemic. WBC instructed Freedom Leisure to close all its leisure centres before the national lockdown came into force. At this time WBC agreed to cover all financial losses of the contract on an open book basis but expected Freedom to do everything possible to mitigate these losses. WBC also requested 40 staff to work for the Council. These staff were then utilised in community support.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Freedom Leisure Performance Review OSC21-040Report | 777 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Mar 2024 | Matters Arising from the Previous Minutes OSC24-017Resolved That the report be noted. | Noted | Open |
| 18 Mar 2024 | Review of Council Meeting Structure OSC24-020RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Annual Review of Complaints - 2023 OSC24-012RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Ukspf osc24-021RESOLVED That the report be noted. | Noted | Open |
| 18 Mar 2024 | Brookwood Cemetery HS2 Task and Finish Group Report OSC24-022RESOLVED That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.