AI summaryWoking's Communities and Housing Scrutiny Committee noted a refreshed Housing Improvement Programme update, covering progress on six workstreams up to Local Government Reorganisation in April 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required
MoneyNo specific sums stated in the report
What happens nextContinue workstreams to April 2027Refresh covers activities up to LGR
Who it affectsCouncil tenants and leaseholdersWoking Borough Council housing service

What was decided

The Committee noted the update on progress against the Housing Improvement Programme since the previous report in July 2025. Report P6, 4.1

The Committee noted the refresh of the Housing Improvement Programme, which sets out priorities and key activities up to Local Government Reorganisation in April 2027. Report P6, 4.2, 1.3

Why

The Council is operating under a statutory government intervention and Section 114 Notice, and received a Housing Regulatory Notice in December 2023, requiring sustained improvement work. Report 5.1

Given ongoing risks around non-compliance with housing regulatory standards, regular progress updates to the Committee are considered the most appropriate approach. Report 6.2

What happens next

Validation surveys on stock condition data to be carried out in quarter 4 of 2025/26 to address data quality concerns raised with contractor Ridge. Report 7.7

A draft Current and Former Tenants Rent Arrears Policy is expected in early 2026, alongside a bin store inspection report covering 42 sites. Report 7.13, 7.15

The OneAssets project is scheduled to go live at the end of the 2025/26 financial year, with move to a cloud-based solution to follow. Report 7.30

Options considered

  • Chosen: Continue providing regular progress updates to the Committee on the Housing Improvement Programme. Given the importance of the area and the risks around non-compliance, regular scrutiny is considered the most appropriate option. Report 6.2
  • Rejected: Treat the Housing Finance workstream as a separate item of the programme. The workstream has achieved its objectives and Finance activities are now considered business as usual, so it has been removed from the refreshed programme. Report 7.11

Implications

  • Legal: No specific legal implications arising from noting the report; reviewing progress is part of the Committee's function. Report P68, 8.1, 8.2
  • Financial: No further resource or finance implications arising from the report; the Head of Housing Services and Transformation continues to oversee the programme within their wider remit. Report P71, 8.3
  • Risk: Risks are monitored bi-monthly through the board, with the top 5 reported to the Improvement and Recovery Board; stock condition survey data quality is identified as a material risk. Report P73, 8.4, 7.7
  • Equalities: A Resident Engagement and Consultation workstream feeds into the programme, with Tenant Satisfaction Survey results used as a baseline for measuring effectiveness. Report P75, 8.5, 8.6
  • Climate: No direct environment and climate change implications arising from the report. Report P79, 8.8
  • Other: The programme refresh was carried out with Commissioners to reflect the impact of Local Government Reorganisation, ensuring legacy issues are addressed in readiness for future arrangements. Report 8.9, 8.10

Who and where

  • Woking Borough Council tenants and leaseholders Report 1.2, 4.3, 5.2
  • The Housing Service staff within the Council Report 7.38, 7.39
  • Council contractors including Bailey Partnership, Ridge and MRI Report 7.3, 7.7, 7.29, 7.35
  • The Regulator of Social Housing Report 7.3
  • Resident and Landlord Partnership Panel members Report 7.16, 8.7

Timeline

  • December 2023: Housing Regulatory Notice issued; Executive approved Housing recovery and improvement as a fifth theme of the Improvement and Recovery Plan. Report 5.1
  • October 2025: Awaab's Law implemented; staff training delivered and Damp and Mould Policy development under way. Report 7.6
  • Autumn 2025: Housing Improvement Programme refreshed, now structured around six workstreams, and approved at the Housing Improvement Board. Report 5.3, 7.42
  • December 2025: Planning Committee resolved to approve the Lakeview Cladding Project application, subject to the legal agreement. Report 7.4
  • Quarter 4 of 2025/26: Validation surveys on Ridge stock condition data to be carried out; OneAssets project scheduled to go live at end of financial year. Report 7.7, 7.30
  • Early 2026: Draft Current and Former Tenants Rent Arrears Policy and bin store inspection report expected; 2025/26 Tenant Satisfaction Measures Survey closes. Report 7.13, 7.15, 7.22
  • April 2027: Local Government Reorganisation; the programme is set to deliver critical activities up to this point. Report 1.3, 4.2

Plain English for the jargon

  • HIP: Housing Improvement Programme, the Council's programme of work to bring its housing service up to regulatory standards.
  • FRA: Fire Risk Assessment, a review of fire safety in a building, with remedial actions tracked and progressed by the service.
  • HHSRS: Housing Health and Safety Rating System, the system used to assess hazards in residential properties.
  • HRA: Housing Revenue Account, the ring-fenced account that funds the Council's landlord functions.
  • IRP: Improvement and Recovery Plan, the Council's wider plan following government intervention and a Section 114 Notice.
  • LGR: Local Government Reorganisation, the planned restructuring of councils in the area, scheduled for April 2027.
  • LGSCO: Local Government and Social Care Ombudsman, the body that handles complaints about councils.
  • RLP: Resident and Landlord Partnership Panel, a group of residents working with the Council on housing matters.
  • Section 114 Notice: A formal notice issued when a council's spending exceeds its resources, triggering statutory intervention.
  • TSM: Tenant Satisfaction Measures, the standardised resident satisfaction survey required of social housing landlords.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That the report be noted.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Communities and Housing Scrutiny Committee

Summary

1.1This report provides an update on the continued progress of the Housing Improvement Programme (HIP) and outlines the key achievements, challenges, and priorities since the previous update in July 2025.

1.2It highlights the steady momentum across all workstreams ranging from building safety and tenant services to data, digital transformation, and cultural development, while also recognising areas requiring ongoing focus, such as stock condition data and fire risk assessments and remedial actions.

1.3The refreshed programme sets out the critical activities needed up to Local Government Reorganisation in April 2027, ensuring the Council remains compliant with regulatory standards and continues improving services for residents.

Purpose of report

2.1The purpose of this report is to update on progress against the Housing Improvement Programme and to provide an opportunity to scrutinise the actions being taken.

Recommendations

3.1The Committee is requested to:

Resolve That the report be noted.

CHSC26-003 Housing Improvement Programme – Update and Refresh

4.0Proposal and Outcome

4.1The Committee is invited to note the update on progress against the Housing Improvement Programme since the last report in July 2025.

4.2The Committee is also invited to note the recent Housing Improvement Programme refresh which sets out the priorities and key activities up to Local Government Reorganisation (LGR) in April 2027.

4.3The desired outcome is that through regular scrutiny and oversight, residents will benefit from an improved service and the risks around building safety will continue to reduce and that the programme continues to focus on the key objectives.

Background

5.1Following the statutory government intervention and the issuing of a Section 114 Notice, the Council has established an Improvement and Recovery Plan. In response to the Housing Regulatory Notice issued in December 2023, the Executive approved a fifth theme to focus on Housing recovery and improvement.

5.2The objective of the Housing Recovery and Improvement theme is to ensure the service is compliant with all the housing regulatory standards, delivering an efficient, reliable, and modern service that meets our statutory requirements, and supports strong neighbourhoods and communities for our residents.

5.3Following a refresh of the programme in Autumn 2025, the programme is now made up of six workstreams:

• Homes & Safety

• Tenants & Communities

• Data & Insights

• Resident Engagement & Consultation

• Tools & Ways of Working

• Staff and Developing Culture

Options considered

6.1Following the decision by the Executive in December 2023, the Housing Improvement Programme is an established workstream forming part of the Council’s Improvement and Recovery Plan (IRP).

6.2Whilst there has been sustained progress against the Housing Improvement Programme since December 2023, given the importance of this area of work and the risks around non-compliance, it is deemed that regular progress updates to the Committee remains the most appropriate option. Housing Improvement Programme – Update and Refresh

7.0Progress Update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHSC26-003 Appendix 1: Housing Recovery and Improvement Highlight report December 2025Appendix 148 KB Download
PDF
CHSC26-003 Appendix 2: Key Performance Indicators (November)Appendix 442 KB Download
PDF
CHSC26-003 Appendix 3: Housing Improvement Programme RefreshAppendix 2.8 MB Download
PDF
Housing Improvement Programme: Update and Refresh CHSC26-003Report 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 18 attended
TB
Councillor Tom Bonsundy-O'BryanChair, present
DJ
Councillor Daryl JordanVice-Chair, apologies
AA
Councillor Attia AslamCommittee Member, present
SM
Councillor Swati MukherjeeCommittee Member, absent
FM
Councillor Faisal MumtazCommittee Member, apologies
TS
Councillor Tom SpenserCommittee Member, present
MS
Councillor Martin SullivanCommittee Member, present
LS
Louise StrongitharmOfficer, expected
KH
Katherine HiscockOfficer, expected
CH
Craig HumphreyOfficer, expected
JM
Julie MemeOfficer, expected
JS
John SharlandOfficer, expected

All 18 on the meeting page

On this subject at Woking

Search all
  1. Housing Improvement Programme - Update and Refresh CHSC26-003This decision
  2. Housing Improvement Programme Update CHSC25-017Agreed
  3. Housing Improvement Programme Update CHSC25-001Noted
  4. Housing Improvement Programme: Update for Communities and Housing Scrutiny Committee CHSC24-006Noted
  5. Housing Improvement Programme: Update for Communities and Housing Scrutiny Committee CHSC24-001Noted

More from Woking Communities and Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Jun 2026 MinutesThat the minutes of the meeting of the Communities and Housing Scrutiny Committee held on 24 March 2026 be approved a... Approved Open
8 Jun 2026 Tenant Satisfaction Measures 2025-26 Submission CHSC26-010That the report be noted. Noted Open
8 Jun 2026 Housing Repairs and Maintenance Policy CHSC26-011That the policy be supported. Decided Open
24 Mar 2026 MinutesThat the minutes of the meeting of the Communities and Housing Scrutiny Committee held on 20 January 2026 be approved... Approved Open
24 Mar 2026 Work Programme CHSC26-006That the work programme be noted. Noted Open