Woking Borough Council
Audit and Governance Committee, Thursday 18 June 2026 at 7.00pm

Internal Audit Annual Report 2025-26 AUD26-014

Decided Finance 2 papers

AI summaryWoking Borough Council's Audit and Governance Committee received a 'Limited' annual internal audit opinion for 2025/26, citing significant weaknesses in governance, risk management and control.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSignificant weaknesses identified in control framework
Money234 days planned, 223 deliveredTwo days difference reflects plan changes
What happens nextTwo draft reports to be finalisedApplication/Third-Party and Counter Fraud
Who it affectsWoking Borough CouncilAll services, residents and stakeholders

What was decided

The committee received the annual assurance opinion from the Head of Internal Audit on the council's control environment.

The opinion given was Limited, meaning there are significant weaknesses in the framework of governance, risk management and control that could be or could become inadequate and ineffective. Report P17, P60

Why

Of twelve audits finalised in 2025/26, one received Substantial assurance, six received Moderate, and five received Limited opinions (HR skills and succession, Housing Programme, Housing options and homelessness, Corporate Health and Safety, and S106/CIL). Report P17, P56

High priority recommendations were raised in two reviews covering HR skills capability and Corporate Health and Safety. Report P17

Cultural and behavioural observations noted generally constructive engagement by management, though resource constraints and reliance on informal or decentralised practices were recurring root causes. Report P41, P42

What happens next

Two draft internal audit reports (Application and Third-Party Management, and Counter Fraud) remain to be finalised. Report P16, P25, P28

Management has accepted all new recommendations and committed to timescales, with internal tracking of live actions reported to the committee at each meeting. Report P17, P41

The S106/CIL/SANG review had a limitation due to some requested information not being provided during fieldwork because of management capacity, reducing coverage in that area. Report P43

The money

  • 234 days Total internal audit plan days originally provided for 2025/26 Report P16
  • 223 days Final internal audit days delivered in 2025/26 after plan changes Report P16

Options considered

  • Rejected: Improvement Recovery Planning review. Cancelled at AGC June 2025 Report P36
  • Rejected: Group Companies review. Cancelled at AGC December 2025 Report P37
  • Chosen: Enhanced coverage of Community Asset Transfer, Community Centres, Housing Programme and Follow Up. Additional days transferred to these areas after cancellations Report P16

Implications

  • Risk: Limited opinion means significant weaknesses in governance, risk management and control that could become inadequate and ineffective. Report P17, P60
  • Staffing: Resource constraints and competing priorities were a consistent root cause impacting control effectiveness and audit fieldwork turnaround. Report P41, P42, P43
  • Other: Recommendation implementation rate rose to 98% in 2025/26, up from 77% in 2024/25. Report P17, P50, P53

Who and where

  • Woking Borough Council (all services) Report P16
  • Audit and Governance Committee members Report P16, P17
  • Director of Finance (s151 Officer) and Corporate Leadership Team Report P43

Timeline

  • December 2024: External Quality Assessment confirmed Forvis Mazars 'Generally Conform' with standards Report P43
  • February 2025: Internal Audit Plan approved by AGC Report P43
  • June 2025: Improvement Recovery Planning review cancelled by AGC Report P36
  • December 2025: Group Companies review cancelled by AGC Report P37
  • March 2026: S106/CIL/SANG review undertaken with noted scope limitation Report P43
  • Year ending 31 March 2026: Period covered by the internal audit work Report P16
  • 08 June 2026: Forvis Mazars draft report dated Report P3

Plain English for the jargon

  • GIAS: Global Internal Audit Standards issued by the Institute of Internal Auditors
  • S106/CIL/SANG: Section 106 planning obligations, Community Infrastructure Levy, and Suitable Alternative Natural Green Space
  • AGC: Audit and Governance Committee of Woking Borough Council
  • Limited Assurance: There are significant weaknesses in the framework of governance, risk management and control that could be or could become inadequate and ineffective.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Resolved That the annual assurance opinion of the Head of Internal Audit over the control environment be received.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Audit and Governance Committee

Woking Borough Council

Internal Audit Annual Report 2025/26 – Draft

Prepared by: Forvis Mazars LLP Date: 08 June 2026

1 Contents 01 Introduction

02 Annual Internal Audit Opinion

03 Internal Audit Work Undertaken in 2025/26

04 Cultural and Behavioural Factors

05 Cross-Organisational Themes / Insights

06 Performance of Internal Audit

A1 Implementation of Recommendations

A2 Year-on-Year Benchmarking

A3 Definitions of Assurance

Contacts and Statement of Responsibility

Disclaimer This report was prepared by Forvis Mazars LLP at the request of Woking Borough Council (WBC) and terms for the preparation and scope of the Report have been agreed with them. The matters raised in this Report are only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information provided in this Report is as accurate as possible, Internal Audit have only been able to base findings on the information and documentation provided and consequently no complete guarantee can be given that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required.

The Report was prepared solely for the use and benefit of the WBC and to the fullest extent permitted by law Forvis Mazars LLP accepts no responsibility and disclaims all liability to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification by any third party is entirely at their own risk. Please refer to the Statement of Responsibility for further information about responsibilities, limitations and confidentiality.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Annual Report 2025-26Report 709 KB DownloadRead as text
PDF
Internal Audit Annual Report 2025-26 AUD26-014Report 64 KB Download

At this meeting

Whole meeting

Who was there

6 of 12 attended
PJ
Puneet JasujaChair, present
GC
Councillor Guy CosnahanVice-Chair, present
CM
Councillor Chris MartinCommittee Member, present
SO
Councillor Stephen OadesCommittee Member, present
SM
Councillor Swati MukherjeeCommittee Member, expected
JP
Councillor John PearceCommittee Member, present
AR
Annie RenCommittee Member, present
RC
Richard CarrOfficer, expected
YE
Yusuf ErolOfficer, expected
SF
Stephen FitzgeraldOfficer, expected
AO
Adesuwa OmoregieOfficer, expected
DD
Douglas DavernSecretary, expected

On this subject at Woking

Search all
  1. Internal Audit Annual Report 2025-26 AUD26-014This decision
  2. Internal Audit Progress Report AUD26-015Decided
  3. Internal Audit Strategy, Operational Plan, and Charter AUD26-010Approved
  4. Internal Audit Progress Report AUD26-011Noted
  5. Internal Audit Progress Report AUD25-033Noted
  6. Internal Audit Progress Report STA25-028Noted

More from Woking Audit and Governance Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Work Programme and Action Tracker AUD26-020Resolved That the Work Programme and Action Tracker be noted. Noted Open
18 Jun 2026 Health and Safety Annual Report 2025-26 AUD26-018Resolved That the Health and Safety Annual Report 2025-26 be received with no matters of concern. Decided Open
18 Jun 2026 External Audit Plan 2025-26 AUD26-013Resolved That (i) the 2025-26 External Audit Plan be received, as set out in Appendix 1 of the report; and (ii) the m... Approved Open
18 Jun 2026 Internal Audit Progress Report AUD26-015Resolved That the report and progress against the Internal Audit Plan be received. Decided Open
18 Jun 2026 Annual Governance Statement AUD26-016Resolved That (i) the draft Annual Governance Statement be received and endorsed; and (ii) the updated Local Code of ... Decided Open