Planned Maintenance Programme - Update Report

Noted Committee 2 papers

Hopmarket Sub - Committee noted this item on Monday 3 September 2012. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That: 1. the Sub-Committee note the planned maintenance details included in Appendix 1 to the report; 2. the Sub-Committee support a repairs fund contribution holiday for 2013/14, subject to a reassurance that there no significant repair works are expected during that period; and 3. the financial implications of a contribution holiday be brought back to the Sub-Committee in the March 2013 Grants report.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Hopmarket Sub - Committee, 2 pages

Purpose of the report

1.1To update the Hopmarket Sub-Committee on the 5 year planned maintenance programme, and the implications this has for the Hopmarket repairs fund reserve.

Background

2.1The Property maintenance team has recentlyreviewed the external maintenance programme for The Hopmarket (see Appendix 1) and revised the schedule of works to provide a rolling 5 year maintenance programme. The programme has endeavoured to take into account potential disruption to the shop tenants due to scaffolding etc. by phasing works that affect the inner courtyard and where possible avoiding peak trading periods.

2.2The estimated costs in the 5 year programme are for the first 5 years and will be reviewed and updated as appropriate. Under the terms of the lease with Worcester Community Housing the Hopmarket Charity recovers 75% of the cost of works to the external structure of the premises from WCH -items 1 -5. In item 6 the cost of external decoration to the shop fronts is recovered 75% from the shop tenantsthrough the service chargeand the remaining 25% from Worcester Community Housing to reflect the proportion of works attributable to each.

3. Policy, Legal, Financial, Equalities and Risk Management Implications

3.1Policy – it is the Charity’s policy to maintain a minimum repairs fund balance of at least £50,000.

3.2Legal – none directly arising from this report

3.3Equalities– none directly arising from this report

3.4Financial – included within this report.

3.5Risk – failure to properly maintain the Hopmarket could result in additional and non- cost effective emergency repairs, reputational damage and possible legal challenge if the terms of the lease are not met. 4. Comments of the Treasurer to the Charity

4.1The details in Appendix 1 show the planned maintenance expenditure for 5 years totalling of £219,500. This includes the total for 2011/12 of £35,500 which has already been spent, so the balance over the remaining 4 years is £184,000. Of this, the estimated cost for the Hopmarket Charity is £42,375.

4.2The Hopmarket Repairs Fund Reserve has a balance of £109,299 as at 1st April 2012. The minimum contingency balance is considered to be £50,000. The £109,299 balance is more than adequate to deal with the remaining 4 year planned maintenance programme, but obviously it should be noted that there could be unforeseen emergency requirements. The agreed position at the moment is that the annual contribution to the repairs fund is £8,000 p.a.

4.3Given that balances have built up over the past few years and that we are in an economic downturn with property rental income reduced, one option the Hopmarket Sub-Committee could consider is to take a contribution holiday, say for two years, with an annual review process. This could help maintain the level of grant payments made by the Charity at around £100k p.a. and still allows a repairs fund balance in excess of planned maintenance needs, to cover any emergency events.

5. Treasurer’s Recommendations:

5.1That the Sub-Committee note the planned maintenance details included in Appendix 1.

5.2That the Sub-Committee indicate whether they wish to take a repairs fund contribution holiday for 2013/14. The financial implications of a contribution holiday will be brought back to the Sub-Committee in the March 2013 Grants report.

Contact Officer: Lesley Meagher - Tel 01905 722595 Background Papers:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1 Repair Schedule 2012-2016Appendix 1 pages Download
PDF
Planned Maintenance Programme: Update ReportReport 2 pages DownloadRead as text

At this meeting

Whole meeting

More from Worcester Hopmarket Sub - Committee

All decisions
MeetingDecisionOutcome
7 Oct 2014 MinutesThat the minutes of the meeting held on 18 th March 2014 be approved as a correct record and signed by the Chairman. Approved Open
7 Oct 2014 Draft Annual Report and Accounts 2013-14That the Sub-Committee: 1. having reviewed the Annual Report and Accounts 2013-14 recommend their approval to the Hop... Approved Open
7 Oct 2014 Property Update - Hopmarket CharityThat the Sub-Committee: 1. note the content of this report; and 2. agree to appoint a commercial letting agent on a s... Noted Open
18 Mar 2014 MinutesThat the minutes of the meeting held on 16 th September 2013 be approved as a correct record and signed by the Chairman. Approved Open
18 Mar 2014 Financial Review 2013/14 and 2014/15That the Sub-Committee approve the setting aside of up to £100k of funding for charitable grants in 2014/15. Approved Open