That the Council:- 1. agree the site at Perdiswell for the new Swimming Pool Complex; 2. agree Option 1 as its preferred option with Option 2 being the minimum specification for the new Swimming Pool Complex; 3. agree the indicative Business Plan and the significant assumptions contained with in it particularly that the model excludes in-house operations; 4. agree that the operation of the new facility will be via an external operator based on a non-business lease with a peppercorn rent which includes the option to tax; 5. agree the Capital allocation for construction and fees of £10.5 million; and 6. agree to progress to tender and evaluation stage for the construction and allocate a budget of £300,000 for the tender process. Record of Voting For: Councillors Against: Councillors Abstentions: Councillors Agar, Amos, Bayliss, Berry, Boorn, Ditta, Geraghty, Hodges, [name removed], S. Hodgson, Jones, Knight, Mitchell, Prodger, Riaz, Roberts Rowden, [name removed], G. Squires, J. Squires, Tarbuck, Tibbutt, Whitehouse, David Wilkinson, Douglas Wilkinson Carpenter, Laurenson Cawthorne, L. Denham, P. Denham, Gregson, Lamb, Udall, Williams Total For: 25 Votes Total Against: 2 Votes Total Abstentions: 7 Votes
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Worcester Swimming Pool Feasibility Study Worcester City Council
February 2013 – Final Contents
1 Executive summary 1
2 Limitations and Caveats 7
3 Introduction 9
4 Background 11
5 Site Survey Results 13
6 Concept Design 17
7 Capital Costs 21
8 Business Case 25
9 Financial Appraisal 33
10 Procurement Strategy 37
11 Capital Works Procurement 41
12 Operator Procurement 49
13 Selection of Consultants 53
14 Selection of a Contractor 57
15 Governance 59
16 Programme 67
17 Risk 69
Appendix A – Survey Tender Results
Appendix B – Design Brief
Appendix C – Architectural Plans
Appendix D – Option 2 Plan
Appendix E – Design and Access Statement
Appendix F – Cost Plan
Appendix G – Programme
Appendix H – Risk Register 1 Executive summary
Introduction 1.1 This Feasibility Study considers how Worcester City Council can develop new swimming pool facilities at Perdiswell Leisure Centre, in a financially sustainable way. The Study also advises on how the Project could be progressed in a way that would meet Worcester City Council’s key drivers.
Site Survey Results 1.2 The following surveys were commissioned and completed during the Feasibility Study. These were undertaken to inform the Outline Planning Application and the cost plan:
§ Topographical and Utilities surveys; § Site Investigations; § Ecology – Phase 1 Habitat Survey; § Arboricultural survey; § Bat survey; § CCTV Drainage survey; § Utilities Infrastructure Assessment; § Noise Survey; § Flood Risk Assessment; and § Transport Assessment and Travel Plan.
1.3The surveys mitigated a number of risks. Results informed the design process and meant that we were able to reduce the Client contingency level in the cost plan from the previous level of 10% to 8%.
1.4The final Phase 2 Site Investigation has not been completed yet. It is expected to be completed by the middle of March 2013 and we will feed in the results to a revised report at that point.
1.5The surveys are all assignable to a future contractor to avoid any abortive costs of repeating them.
Concept Design 1.6 The design progressed well to Outline Planning Stage with a high level of input from Worcester City Council.
1.7The proposed facilities for the new swimming pool consist of:
§ golf clubhouse and pro shop; § 8 external team changing rooms for outdoor sports; § 8 lane 25m swimming pool to county standard; § formal spectator seating for a minimum of 250; § teaching pool (17.5m x 8m) with moveable floor and formal spectator area on poolside; § confidence water area for children; § wet changing; § Changing Places facility; § 150 station fitness suite; § one dance studio divisible into two or three plus a specialist facility e.g. Spinning;
Worcester Swimming Pool Feasibility Study 1 § dry changing for health and fitness facilities and studio; § café / bistro for 50 / 60 with external area; § soft play; § resurfacing of the two existing 5-a-side pitches; § increased car parking provision; and § relocation of the first golf tee.
1.8The plans also show a crèche. Through detailed financial modelling, it was decided that the crèche would be omitted from the scheme. The plans included at Appendix C have not been updated, however they should be updated at the next stage to show this alteration.
1.9The Outline Planning Application was validated on 14 November 2012. The application was referred to Committee as the proposed development was a major planning application submitted by Worcester City Council.
1.10The application was heard at a Planning Committee meeting on 24 January 2013. The Committee unanimously agreed to the proposal on the basis that:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.