Resolved
That:- 1. The Committee note the report. 2. Clarification be sought from the Government of the arrangements for their new scheme. 3. A further update be submitted when more information becomes available.
Scrutiny Committee noted this item on Wednesday 25 September 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That:- 1. The Committee note the report. 2. Clarification be sought from the Government of the arrangements for their new scheme. 3. A further update be submitted when more information becomes available.
1.1To provide an update on the Local Authority Mortgage Scheme (LAMS) that the Council entered into with Lloyds TSB (now Lloyds) called “Lend a Hand”. This report provides an update to the position reported to Scrutiny Committee on the 28 August 2013.
2.1The report to Scrutiny Committee on the 28 August, attached at Appendix 1, sets out the background and approvals already given to the Lend a Hand scheme. This report gives an update on the latest take-up on the scheme and sets out the latest development on the various Government schemes and the immediate implications for our local scheme.
3. The Worcester Lend a Hand Scheme – The Current Position
3.1As of the 31 July 2013, there are a total of 30 households who have accessed and been accepted onto the scheme to purchase a home. Of this number, 20 households have “completed” with an indemnity amount of £568,068, which means that all the legal processes are finalised by the conveyancer and the monies have been transferred to the seller.
3.2There are 7 householders at the “offer not completed” stage – with a potential indemnity value of £205,835. This means that all the credit checks and affordability assessments have been completed and are acceptable and a formal offer of the loan has been made to the customer. At “offer not completed” the Lender is expecting the mortgage to complete.
3.3There are 3 householders at application stage and have not progressed to either offer or completion. These three have a potential indemnity value of £80,125. If all the “offers not completed” and “application” stage householders move to completion then the overall indemnity amount, as at the end of July 2013, will be £854,028 against the initial £1m placed in the scheme at the start of the current financial year.
3.4The properties purchased have ranged between a value of £90,000 and £178,000. Where the property exceeds the threshold level of £171,000 the purchaser has to have a larger deposit to ensure the total loan available does not exceed the threshold level. The average price of a property purchased is £143,693 and the average loan is £136,172.
3.5The location and number of properties either purchased or at application stage is shown in the table below. This shows a good spread across the city.
1 Bedwardine
St Stephen Arboretum
Parish Nth Battenhall
Parish sth Gorse Hill
Warndon
Warndon
Warndon Rainbow Nunnery
St John Claines 1 1 5 3 2 5 3 2 1 1 5 1
3.6Prior to launching the scheme there were concerns regarding inward migration. Statistics provided by Lloyds confirm that in excess of 96% of completions on a national basis are from individuals who already live or work in their local area. The majority of applicants buying properties using the Lend a Hand Scheme have been local to the Worcester area. Lloyds have found the main reason applicants were taking advantage of the scheme was because they had either read about it in the local paper or by word of mouth from a friend who had already applied using the scheme.
3.7Nationally, over 94% of the first time buyers, based on statistics provided by Lloyds, are purchasing houses over flats and apartments. This was the position as at 31 March 2013 and due to changes with the data extraction process, Lloyds has not been able to update this so far this year. The average first time buyer age is 29.6 years.
3.8The scheme is operating well and if all applications move to the completion stage a further £145,972 will be available for indemnities – the average indemnity amount for all 30 household currently accepted is £28,468 meaning that on average there remains sufficient funds to cover 5 more householder applications.
4. Other Mortgage Support Schemes and their impact on LAMS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Authority Mortgage Scheme: The Current PositionReport | 9 pages | DownloadRead as text |
Follow Scrutiny Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Mar 2017 | MinutesThat the minutes of the meeting held on 1 st February 2017 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 8 Mar 2017 | Scrutiny Review - Impact of Individual Electoral Registration - Final ReportThat the Cabinet be recommended to consider the report and approve the recommendations of the Review Group, as set ou... | Approved | Open |
| 8 Mar 2017 | Scrutiny Review - Street Cleansing - Final ReportThat the Cabinet be recommended to consider the report and approve the recommendations of the Review Group and the ad... | Approved | Open |
| 8 Mar 2017 | Service Review - HeritageThat Committee note the presentations and the responses to questions. | Noted | Open |
| 8 Mar 2017 | Service Review - Planning (Development Management)That Committee note the presentation and the responses to questions. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.