Performance Management and Budget Scrutiny Committee decided this item on Tuesday 3 December 2013. Below is the council's own wording, with the papers it was decided on.
That the Committee make the following comments to Cabinet: The way in which performance measures are presented should be reviewed as the exception report is based on performance against targets and does not include all measures that show a downward direction of travel, which may not be a true representation.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Performance Management and Budget Scrutiny Committee, 10 pages
Purpose of report
1.1To provide a summary by exception of performance against the five Corporate Plan Priorities for Quarter 2 (July – September 2013) and 2013/14.
Background
2.1The Corporate Plan for 2011 – 2015 was agreed in June 2011 and sets out five priorities for the Council.
Cleaner and Greener City Safer and Stronger Communities Economic Prosperity Customer Service and Communications Delivering Value for Money
2.2Performance against the Corporate Plan is monitored using a suite of performance measures which are aligned with the priorities. A summary of performance is provided in this report with more detailed information shown in Appendices 1.
2.3Following the development of the Council’s Performance Management Framework, it was agreed to develop this set of measures which includes corporate, local and service plan measures combining traditional quantitative indicators with more qualitative measures such as case studies where appropriate. The measures also demonstrate the impact of the Council’s actions in a partnership context, particularly in those areas where our role is one of influencing as opposed to driving improved outcomes.
2.4Delivery of the Corporate Plan priorities will be achieved through a number of workstreams and key improvement projects which have been identified on the Corporate Project Register as either Corporate Plan Improvement (CPI) Projects or Corporate Improvement (CI) Projects. Progress is monitored through project highlight reports with brief updates included in quarterly performance reports by exception. A full list of current projects and their status is provided in Appendix 2.
2.5In addition to the CPI and CI Projects reported in this report, there are also 23 Service Improvement (SI) Projects on the corporate Project Register. These are not detailed below as the focus of this report is on corporate projects. 3. Performance Summary
3.1For performance measure available for Q2, 75% of performance measures have met or exceeded target. This is an improvement compared to performance for the same period in 2012/13 (45%) although it should be noted that the basket of measures is different.
3.2Corporate Plan Improvement and Corporate Improvement Projects:
This report includes progress updates for 9 CPI Projects and 13 CI Projects from the Corporate Project Register. 59% of projects are on target compared to 84% in the last quarter. The decline in projects rated green is due to project specific issues, including increased risk, external factors beyond our control such as reliance on delivery by partner organisations, delays in delivery and project management capacity.
% of reported incidents of graffiti removed within agreed timescales = 75%.
Performance equates to one of the four reported incidents of graffiti reported in quarter 2 not being removed within the agreed timescale. This was regarding an incident of offensive graffiti which was not removed within 24 hours of being reported. The incident was reported on 30 September and the details of the location were not clearly identified, however the graffiti was successfully removed by the 2 October.
Amber Project
Development of Public Realm at Diglis and adjacent areas Start date: March 2013 Completion date: April 2016 (Status moved from Green in Q1)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Performance Management and Budget Scrutiny Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
Q3 Financial Monitoring Report 2016/17That the Committee note the financial monitoring details including budget variances, year end forecasts and performan...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.