Performance Management and Budget Scrutiny Committee agreed this item on Tuesday 4 March 2014. Below is the council's own wording, with the papers it was decided on.
It was agreed that this was a more effective measure of performance for this service. · The new process for employee appraisals was reported to the Committee in December 2013. Reporting on take-up will be made at the end of Quarter 1 and there will be a target of 100% completion by the due date. · Fresh options for delivering the Green Deal and Energy Company Obligation in Worcester are being explored. Further information about other options for support will be provided. · Recent telephony problems were discussed and it was explained that discussions are taking place currently to decide whether to pursue a claim against the supplier as well as how to improve supplier performance. In conclusion, it was suggested that time would be set aside at the start of the next PMBS Committee for Officers to provide answers or information on the outstanding points raised in the above ... view the full minutes text for item 47.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Performance Management and Budget Scrutiny Committee, 11 pages
Purpose of report
1.1To provide a summary by exception of performance against the five Corporate Plan Priorities for Quarter 3 (October – December 2013) and 2013/14.
Background
2.1The Corporate Plan for 2011 – 2015 was agreed in June 2011 and sets out five priorities for the Council.
• Cleaner and Greener City • Safer and Stronger Communities • Economic Prosperity • Customer Service and Communications • Delivering Value for Money
2.2Performance against the Corporate Plan is monitored using a suite of performance measures which are aligned with the priorities. A summary of performance is provided in this report with more detailed information shown in Appendix 1.
2.3Following the development of the Council’s Performance Management Framework, it was agreed to develop this set of measures which includes corporate, local and service plan measures, combining traditional quantitative indicators with more qualitative measures such as case studies where appropriate. The measures also demonstrate the impact of the Council’s actions in a partnership context, particularly in those areas where our role is one of influencing as opposed to driving improved outcomes.
2.4A number of measures included in the Quarter 3 report are collected via the Viewpoint Survey which is undertaken twice a year to measure resident opinion and perception of local facilities and services. The responses to the Viewpoint Survey came from a sample of residents and therefore the results are subject to sampling tolerances. Hence, not all the differences between results are statistically significant. The confidence level is typically +/- 5-6 percentage points. These confidence intervals assume a perfectly random sample has been achieved, whereas in practice this is not the case and therefore margins of error may be slightly larger. Full results from the Viewpoint Survey will be reported to Cabinet in March and to this committee in June 2014 when comparative data is available.
2.5Delivery of the Corporate Plan priorities will be achieved through a number of workstreams and key improvement projects which have been identified on the Corporate Project Register as either Corporate Plan Improvement (CPI) Projects or Corporate Improvement (CI) Projects. Progress is monitored through project highlight reports with brief updates included in quarterly performance reports by exception. A full list of current projects and their status is provided in Appendix 2.
2.6In addition to the CPI and CI Projects reported in this report, there are also 25 Service Improvement (SI) Projects on the corporate Project Register. These are not detailed below as the focus of this report is on corporate projects.
3. Performance Summary
3.1For performance measures available for Q3, 87% of performance measures have met or exceeded target. This has increased compared to performance for the same period in 2012/13 (82%) and 75% in the last quarter although it should be noted that the basket of measures is different.
3.2Corporate Plan Improvement and Corporate Improvement Projects:
This report includes progress updates for 8 CPI Projects and 16 CI Projects from the Corporate Project Register. 64% of projects are on target compared to 59% in the last quarter.
• The percentage of green waste composted (Garden Waste) continues to be above the target of 5%, with year to date average of 5.4% collected compared to 3.4% for the same period last year.
Follow Performance Management and Budget Scrutiny Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
Q3 Financial Monitoring Report 2016/17That the Committee note the financial monitoring details including budget variances, year end forecasts and performan...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.