CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Cabinet, Wednesday 18 June 2014 at 7.00pm

Minutes

Approved Executive 1 paper

Cabinet approved this item on Wednesday 18 June 2014. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

That the minutes of the meeting held on 15 th April 2014 be approved as a correct record and signed by the Chairman. Matters Arising The Portfolio Holder for Safer and Stronger Communities was asked for the Cabinet’s decision on proposals for a new swimming pool. Members were informed by the Portfolio Holder that the Cabinet wanted to be satisfied that whatever recommendation was taken forward it would be in the best interests of the people in Worcester and he further informed Members that a review would be put in place to consider all the options to ensure this would be the case.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 7 pages

CABINET

15th April 2014

Present: Councillor Gregson in the Chair

Councillors Berry, Boorn, L. Denham, Lamb, [name removed] and Williams (Vice-Chairman)

116 Declarations of Interest

None.

117 Public Participation

Relating to Agenda Item 5: Diglis Public Realm Project

[name removed], spoke on behalf of Worcester and District Model Engineers in favour of the proposals developed for enhancement of the public realm at Diglis.

Relating to Agenda Item 6: Provision of New Swimming Pool for Worcester

Adele Rimell, Chairman of Worcester Swimming Club and Vivienne Hewitt, a member of Worcester County Swimming Association, spoke in favour of an eight lane swimming pool for Worcester as opposed to a six lane swimming pool which was being recommended by the Perdiswell Programme Board.

118 Minutes

RESOLVED: That the minutes of the meeting held on 11th March 2014 be approved as a correct record and signed by the Chairman.

119 Provision of New Swimming Pool for Worcester Project Progress Report

The Cabinet received a progress report from the Perdiswell Programme Board in relation to the provision of a new swimming pool for Worcester. The Portfolio Holder for Health and Wellbeing explained that the purpose of the report was to provide a progress update on the Perdiswell Swimming Pool and Leisure Centre project. The Portfolio Holder also explained that the report summarised information obtained so far in support of the design and delivery of the ‘new build’ facility.

The Portfolio Holder informed Members that concerns have been raised in regard to the viability of the previously agreed approach the “new build” option. Members were informed that since the new Swimming Pool project was first initiated in 2011, the landscape within which the Council now operates had changed significantly. Government funding reductions, increased efficiency pressures, resultant service reviews, together with an increasing level of expectation from the Council’s citizens, were all influencing and prioritising what would be affordable and sustainable in terms of future service delivery. 15th April 2014 2

Given the affordability issues linked to the ‘new build’ proposal, it had been considered prudent to re-investigate and assess other ‘affordable’ options before proceeding further at this stage. Having now undertaken this exercise, a more affordable solution had been identified in terms of an ‘extend and refurbish’ option.

The Portfolio Holder for Health and Wellbeing explained that the ‘extend and refurbish’ option outlined in the report maintained a greater level of service continuity, provided a new and adjacent building for the swimming pool and, through the retention and refurbishment of the Sports Hall, would deliver a larger, flexible and modern leisure facility.

The Managing Director also provided the Cabinet with a summary of the discussions that had taken place with Sport England regarding project funding support, the Council’s financial position and the wider Perdiswell ambitions as set out in the report. The Managing Director also summarised the project options and explained that the “extend and refurbish” option based on a six-lane pool was being recommended as the original proposal “new build” was not deliverable with the budget provided.

RESOLVED: That the Cabinet:-

1. authorise Officers to progress a detailed cost estimate and prepare a business case for the ‘extend and refurbish’ option based on a six-lane pool; and

2. note that the original proposal (new build) is not deliverable within the budget provided; that changes to the operation of the business model, alongside government funding cuts fundamentally question the affordability of this level of borrowing.

120 Worcester City of Culture 2021

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MinutesMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. MinutesThis decision
  2. Minutes of Previous Planning CommitteeApproved
  3. Minutes of Previous Planning CommitteeApproved
  4. MinutesApproved
  5. MinutesApproved
  6. MinutesApproved

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies