That: 1. Cabinet approve refurbishment of Astwood Crematorium, within the available financing, as detailed within this report; 2. the Corporate Director, as chair of the Bereavement Services Programme Board, approves the final specification for works under existing officer delegation, in consultation with the relevant Cabinet Member; and 3. Cabinet authorise officers to submit relevant planning applications if these are required.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
2.1In September 2012 Cabinet received a report outlining options for the future management of Astwood Cemetery and Crematorium and the Council’s Bereavement Service. At that time Cabinet took the decision to continue with delivery of the service in house and to progress service improvements including investment in the physical assets and development of an operational business plan.
2.2During 2013/14 actions were progressed at service level, and are managed through a corporate Bereavement Services Programme Board.
2.3Currently the Board is overseeing the following workstreams: 1. Investment in the service buildings & refurbishment of Astwood Crematorium 2. Introducing flexible and integrated team working & improved customer service 3. Extending the provision for burial space 4. Cremator asset management
2.4The proposals within this report relate directly to workstreams 1 and 2.
2.5The 2014/15 Budget Report recognises “that capital investment in facilities is required in order to maintain infrastructure and improve the customer offer”.
2.6A provisional sum of £300k is included in the Council’s Capital Programme for Crematorium Improvements. The financing for this capital investment is estimated to be £100k to be funded from increased fees and charges income over two years, and a further £200k predicated on the disposal of a surplus asset at the Crematorium.
3. Progress
3.1Workstream 1 is the subject of this report.
3.2Workstream 2 has commenced with a staffing restructure that has enabled multi skilling and flexible working to be implemented and delivered revenue savings of over £20k p.a. To sustain this improvement and fully realise the benefits, which will include improved customer service, co-location of staff at the main Crematorium building is required. This co-location is an integral feature of the works detailed within this report. 3.3 Workstream 3 is identifying potential additional burial space at Astwood which will meet demand for at least the next 25 years.
3.4Workstream 4 has identified that the cremators will not require replacement in the short to medium term. This position will be reviewed annually.
3.5This report sets out the Business Case in support of work streams 1 and 2 in section 4, and recommends that funding is allocated to undertake refurbishment works. This will provide an improved environment for service users and facilitate more efficient operation of the service. Appendix 1 of this report sets out a breakdown of the estimated costs.
3.6The proposed scheme has been subject to first stage feasibility assessment which indicates a total budget of £200k will be required. The final details of the scheme will be developed following further consultation with key stakeholders, the Friends of Astwood Crematorium and the Cemeteries and Crematorium Forum. Initial consultation, including a meeting of the Forum on 7th October 2014, showed strong support for a refurbishment of the chapel and other public facing areas, and indicated that further consultation will be required to establish detail such as the alignment and type of seating and internal décor.
3.7It is to be expected that some amendments to the works currently proposed will be made as a result of the consultation process, and officers will manage this within the available financing for this capital programme scheme.
3.8On completion of the works proposed within this report, the land and buildings currently used as an office and operational staff facilities will become surplus to requirements and available for disposal.
4. Business Case for the refurbishment of Astwood Crematorium
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.