Resolved
That: 1. the Financial and Service Performance for 2014/15 to the end of October 2014 be noted; and 2. the revised Budget for 2014/15 and the Budget Strategy for 2015/16 be approved.
South Worcestershire Shared Services Partnership Joint Committee noted this item on Thursday 27 November 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That: 1. the Financial and Service Performance for 2014/15 to the end of October 2014 be noted; and 2. the revised Budget for 2014/15 and the Budget Strategy for 2015/16 be approved.
1.1This report sets out the Financial and Service Performance of the IT Shared Service for 2014/15 to the end of October 2014 and presents the Revised Budget for 2014/15 and Budget and Strategy for 2015/16 for the Service for approval by the Joint Committee, in line with the Partnership Agreement.
2.1That the Financial and Service Performance for 2014/ 15 to the end of October 2014 be noted.
2.2The Revised Budget for 2014/15 and the Budget and Strategy for 2015/16 be approved
3.1Financial Performance to end of October 2014
The financial performance (budget monitoring) of the IT Shared Service for the 7 months to the end of October 2014 is shown at Appendix 1.
The overall position is that there is an underspend against profiled budget of £11,185, of which £4,557 is shown against the employee costs budget head. There have been some significant staff vacancies during the year and a pay award has not been made so it would have been expected that this underspend should have been higher. However, the employee costs budget is understated due to the reasons explained in 3.3. Once this is corrected there should be adequate budget to allow the filling of vacancies during the latter part of the year. In addition, there is an underspend of £1,922 on supplies and services which is due mainly to the fact that there has not been an insurance charge to the Shared Service, although it has been budgeted for, offset by some variations due to profiling of hardware and software licences.
Finally, £4,706 of the underspend is due to income received that was not budgeted for and this offsets some of the costs incurred.
3.2Service Performance
A Service Desk performance report is shown at Appendix 2.
3.3Revised Budget 2014/15
In setting the budget for 2014/15 it was noted that the budget requirement for the year was £721k less than when the shared service was formed, reflecting a reduction in staff from 39.5 FTE to 30.6 FTE and lower software costs from combining systems etc. It was also noted that provisions had been made for a 1% pay award from April 2014 and 2.7 % for inflation on hardware and software licences. In addition, a System Support Technician post had been deleted in light of the setting up of the Strategic Partnership for Revenues and Benefits as it was thought that this post would not be required.
However, following the setting of the budget, Civica asked the IT Shared Service to provide Application and Development support for the Revenues and Benefits IT system and the System Support Technician post has, therefore, been re-instated.
Also, due to the need to progress the ‘self serve’ programme across South Worcestershire with the aim of creating future staff savings, it was agreed that two staff be seconded from the Wychavon DC Business Improvement team, on a part time basis, and additional budget was provided by partner Districts for this as part of their budget processes for 2014/15. The IT Shared Service Revised Employees budget for 2014/15 has, therefore, been amended to reflect the above items.
Other changes made in the Revised Budget are:
• Insurance budget of £16k deleted as no longer required
• Hardware and Software Licences budget reduced by £20k to reflect an ongoing underspend from the previous year and actual spend to date in the current year
• Estimated Income to the Shared Service from work done for Civica £20,760
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring Summary to end of OctoberAppendix 1 | 1 pages | Download |
PDF |
Appendix 2Appendix 2 | 1 pages | Download |
PDF |
Budget 2015-16Appendix 3 | 1 pages | Download |
PDF |
ICT Shared Service Budget and Strategy ReportReport | 4 pages | DownloadRead as text |
Follow South Worcestershire Shared Services Partnership Joint Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Nov 2016 | MinutesThat the minutes of the meeting held on 16 th September 2016 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 25 Nov 2016 | Revenues & Benefits Shared Service Performance Report April to October 2016That the Joint Committee note the performance of the Revenue and Benefits Shared Services for the period April – Octo... | Noted | Open |
| 25 Nov 2016 | South Worcestershire Revenues and Benefits Shared Service - Revised Budget 2016-17 and Budget for 2017-2018That the Joint Committee: 1. note the financial performance (budget monitoring) of the Shared Service for the 7 month... | Noted | Open |
| 25 Nov 2016 | Worcestershire Hub Shared Service – Quarter 2 2016/17 and 2017/18 BudgetThat the Joint Committee: 1. note the operational performance and levels of customer satisfaction for the Worcestersh... | Noted | Open |
| 25 Nov 2016 | IT Shared Service Budget And Strategy ReportThat the Joint Committee: 1. note the Financial and Service Performance for 2016/17 to the end of October 2016; and 2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.